Transcript and Presenter's Notes

Title: INTERREG IIIA


1
INTERREG IIIA
OFF SITE MANUFACTURING (OSM) AND SUSTAINABLE
DEVELOPMENT Co-ordinated by
Regeneration Projects Division
Daniel Salisbury MRICS Sustainable Construction
Advisor
2
Procurement Options
Traditional Brick Block
with pre-fab components (Roof / Floors / Kitchens
/ Bathrooms)
New Build
Modular
MMC
SIPS Composites
Volumetric Construction
Steel / Concrete / Timber or Laminates
Panellised (Open or Closed)
Hybrid (Part Traditional)
Pre fabricated units or pods bolted together
Sectional (Steel / p.c.c.)
3
Modular Systems
Agreed Specification
Manufactured under factory conditions
Reduced waste
Comparison of main contractors on similar sites
and shared experience
Advantages
Reduced labour
Reduced vandalism during site operations
Early Completion
Optional façade treatment
Reduced architectural / design costs
Consistency across all units
4
Modular System
Nominal site tolerances
Changes to design limited once fabrication and
installation underway
Limitations of structural grid system on unit
design
Material sustainability limited compared to
timber framed solutions
Access requirements to site (positioning)
Disadvantages
Geographic distance between supply
manufacturer/installer and site
Limitation of structural system for future
alterations
Co-ordination of interface between main
contractor and modular installer
Installation maintenance of concealed services
5
Modular System Case Study
  • Mayweed Avenue / Wiltshire Close Chatham
  • Client
  • - mhs Homes, Rochester
  • Main Contractor
  • - Epps Construction
  • - GSE Design Build ltd
  • Modular Supplier
  • - The Elliott Group
  • Consultants
  • - Appleyards Ltd
  • Architect
  • - CYMA

6
Modular SystemConstruction
7
System BuildTimber Frame Panel Construction
Flexibility of design
Off site manufacturer under factory conditions of
main building frame
Use on sites where access for modular system not
suitable
Advantages
Changes of design possible on site
Healthier building for end user
Use of traceable timber from managed resources
Breathable Construction
Use of environmentally friendly insulation
materials
8
System BuildTimber frame Panel Construction
Cost
Co-ordination of timber frame with cladding/
finishing systems
Disadvantages
Historic perception of timber frame design
Warranties/ insurances
9
Timber frame Case Study
  • Yarrow Road, Chatham
  • Client
  • - mhs Homes, Rochester
  • Main Contractor
  • - Epps Construction
  • Modular Supplier
  • - Timber Framed Solutions (Excel
    Tradispanel System)
  • Consultants
  • - Appleyards Ltd
  • Architect
  • - CYMA

10
Timber frame Construction
11
Timber frame Case Study
  • Cliff / Lower Stoke, Rochester
  • Client
  • - mhs Homes, Rochester
  • Main Contractor
  • - GSE Design Build - Epps Construction
  • Modular Supplier
  • - Timber Framed Solutions (Hybrid System)
  • Consultants
  • - Appleyards Ltd
  • Architect
  • - CYMA

12
Timber frame Construction
13
Concrete Systems
Cast in-situ framing
Tunnel Form Construction
Crosswall construction
Concrete Systems
Lightweight slab - form
Components
Insulating concrete Formwork (ICF)
Thin bed joint systems
Hybrids with cast in-situ and pre-cast
14
Suppliers
System Builds
Steel
Timber
Modular
Concrete
CORUS
PACE TIMBER
DELTA
THE CONCRETE CENTRE
SPACEOVER
KINGSPAN
ELLIOT
TERRAPIN
ADVANCE HOUSING
GENERAL
E-CON
METEK
SCANDICOM
SPACE 4
PROJECT DEVELOPMENTS
  • Modular Units
  • System Build
  • Components

ECONSTRUCTION LTD
HANSON
WAVE
BULLIVANT
SMARTPLY
VORKON
SYSTEM FIRST
FUSION
SCOTTSDALE
POWERWALL
  • Modular 6 Storey
  • Through frame
  • 15 Storey

FRAMING SOLUTIONS
15
Conclusion
  • Design Process / Repetition
  • On Site Operations / Co-ordination / Uncertainty
    / Responsibility
  • Cost
  • End User Feedback
  • Whole Life Costing - Energy / Maintenance
  • Alterations and Adaptations / Insurance
  • Sustainability
  • Traditional (waste _at_ 20)
  • Timber
  • Steel
  • Concrete
  • Modular