Title: Project GreenShores
1Project GreenShores Site 2 Status / Update
2PGS-Site 1
PGS-Site 2
- Key Milestones/Limitations
- All permits obtained April 06
- In Water work allowed between May 1 and August
30 of each year. - Total cash budget 975k (does not include
in-kind services) - Contract for breakwater material issued
- Contract for construction pending signatures
3Construction Phase Has Begun!!
Concrete recovery at NAS
4Concrete Processing at Pensacola Shipyard
Final Quantity 7,000 Cubic Yards of Aggregate
18,000 Cubic Yards of Rip Rap 25,000 Cubic
Yards total Cost to project - 630k
Original Design 1,200 Cubic Yards of
Limestone 11,000 Cubic Yards Concrete Rip Rap
20,000 Cubic Yards Concrete Aggregate 32,000
Cubic Yards total
5Sand Delivery from Gulf Power (Crist Plant) to
Project Site has been completed (thanks to
Escambia County Roads!!)
Final Quantity 20,000 cubic yards
Original Design 60,000 cubic yards
6All submerged breakwaters-recycled concrete
7Lagoon to Hawkshaw will be dredged to allow for
tidal exchange
8Project Greenshores Restoration Site 1
Project Greenshores Restoration Site 2
9What Else is Going On
- OYSTER GARDENING Approximately 1,000 oyster
mobiles have been hung from area docks to help
seed the new breakwater reefs (more to come!!) - NURSERY PRODUCTION approximately 20,000 plants
have been propagated with a goal of 50,000 by
September for initial marsh plantings
10Volunteers neededat DEP NurseryNow-July 30th
Volunteering
11Volunteer planters neededmid-September(well
need lots of help!!)
12To Volunteer please call 595-8300 ext 1158 or
email amy.baldwin_at_dep.state.fl.us
13Questions?