Title: THE BEACONSFIELD MINE RESCUE
1THE BEACONSFIELD MINE RESCUE
- THE ROLE OF
- THE SURVEYORS
- 25 April to 9 May 2006 Simon Arthur
2THE BEACONSFIELD MINE RESCUE
- The Beaconsfield Mine tragedy on ANZAC Day 2006
saw what human endeavour could achieve in a time
of crisis. - The successful rescue was a result of meticulous
planning, teamwork, patience and the commitment
to utilise whatever resources that were available
to enable a successful outcome. - No stone was left unturned.
3THE BEACONSFIELD MINE RESCUE
- During the course of the rescue many people of
varying skills were put to the test, not least of
which were the mine surveyors. - A brief summary of the mining method employed in
the vicinity of the rock fall and a chronological
account of the surveying activities during the
rescue will be given in this presentation.
4OVERVIEW OF THE MINING METHOD
- The Beaconsfield Mine tragedy and associated
rescue was centred around the 925 Sill Drive. - The 925 Level is situated approximately 925
metres below the surface at the mine headframe. - See Fig. 1 for a plan showing the location of the
925 Level relative to the headframe (Hart Shaft)
and the township of Beaconsfield.
5OVERVIEW OF THE MINING METHOD
Fig. 1 Beaconsfield township - green shading
indicates the 925 Level.
6OVERVIEW OF THE MINING METHOD
- The mining method used in this region of the mine
is referred to as the Modified Avoca Mining
Method. - This method involves initially mining three sill
drives (horizontal mining) and then stoping
between the sill drives (vertical drilling and
blasting) as shown in Fig. 2. - The 925 Sill drive is the central sill drive of
the 940 stoping block.
7OVERVIEW OF THE MINING METHOD
Fig. 2 A schematic of the long section view of
the 940 Stoping Block
8OVERVIEW OF THE MINING METHOD
- Fig. 3 represents the long section after the
ANZAC Day rock fall, showing the extent of the
rock fall (broken line not surveyed), the
extent of mining, the rock fill placed and the
approximate location of vehicles in the 925 sill
drive. Just prior to the rock fall a mesh
barricade was being erected back from the brow of
the open stope so that a panel in the 925 Lift 1
could be backfilled so that stoping could take
place in the 915 Level.
9OVERVIEW OF THE MINING METHOD
Fig. 3 Long section view of the 925 sill drive
after the rock fall
10THE MINE SURVEYORS ROLE
- Over the course of the rescue mission a variety
of tasks were carried out. These tasks are no
different to those carried out during normal day
to day mining operations on this site and other
sites. In this presentation I will outline the
survey teams involvement during the rescue in a
chronological manner without going into great
detail about the surveying techniques employed. - The fortnight can be broken up into two parts.
Firstly the first five days after the rock fall
and secondly the nine days after two of the
missing miners were found alive.
11THE MINE SURVEYORS ROLE
- The first five days Wednesday 26th to Sunday
30th of April 2006 - In the early hours of Wednesday 26th of April
2006, Mine Surveyor Peter Wylie was called into
work to start producing the most current plans
and section views in the vicinity of the 925
Level to enable the Emergency Operations Control
Group (EOCG) to determine what options were
available.
12THE MINE SURVEYORS ROLE
- After careful deliberation and investigation by
the EOCG it was decided that an alternative
access to the location where three miners, Brant
Webb, Todd Russell and Larry Knight were last
seen working, was needed. - Once the design was decided upon we were required
to produce sections along the alignment. - Once extra ground support was installed the new
access drive was marked up and an alignment laser
installed to guide the mining of the drive.
13THE MINE SURVEYORS ROLE
- Communicating progress to the miners families
and mining of the access drive to design meant
that 24 hour a day survey coverage was required. - New survey control was established in the
vicinity of the access drive. - A refinement of the breakthrough of the new
access drive into the 925 Sill Drive meant more
sections and the installation of a new alignment
laser were required. - At approximately 530 pm on Sunday 30th April
verbal contact was made with Brant Webb and Todd
Russell. Mining ceased while the EOCG considered
their options.
14THE MINE SURVEYORS ROLE
- The last nine days Monday 1st to Tuesday 9th of
May 2006 - In the early hours of Monday the 1st of May the
last cut fired in the access drive was surveyed.
A plan of the drive was produced and the
co-ordinates of a probe hole to target the
trapped miners last known location were
determined.
15THE MINE SURVEYORS ROLE
- The probe hole was then set out. The probe hole
which hit its target first time was reamed and
lined with some PVC piping, thus establishing a
safe means of communicating and providing
supplies to the miners. - Initially it was decided to access the trapped
miners by mining a small airleg drive following
the left hand wall of the larger access drive. In
order to mine this smaller drive a new laser was
installed to control the mining. Fig 4. below is
the plan produced and supplied to the sites
Mining Department to ensure correct mining of the
rescue drive.
16THE MINE SURVEYORS ROLE
Fig. 4 Plan used for ensuring mining to design.
17THE MINE SURVEYORS ROLE
- After a lengthy deliberation the EOCG decided
that a slightly inclined, 1.07 m diameter
raisebore hole would be mined instead. - A collar survey (location, direction dip) of
the lifeline hole was carried out. Information
obtained from the two miners along with the
details obtained from the collar survey of the
lifeline hole enabled a better estimate of the
location of the trapped miners to be determined.
18THE MINE SURVEYORS ROLE
- The raisebore hole was designed to come in
directly below the men and telehandler basket. - A concrete pad design and the correct alignment
for the raisebore hole had to be determined. - The finished surface level of the concrete pad
was marked up to enable the rig to be set up
close to the designed inclination of the
raisebore hole (approximately 2 degrees
difference). Two dynabolt hooks were placed in
the drive walls on the correct orientation to
enable the raisebore rig to be set up to hit the
designed target.
19THE MINE SURVEYORS ROLE
- The concrete pad was surveyed as soon as the pad
was completed. - Once the concrete had cured the raisebore rig was
set up using the alignment dynabolts and the
designed dip of the proposed hole. Prior to
bolting down, the rig was surveyed to confirm
that the set up was correct. - After the rig was bolted down another survey was
undertaken to confirm the orientation and dip of
the rig were correct.
20THE MINE SURVEYORS ROLE
- The raisebore operators were then given the go
ahead to collar the drill head. A final survey of
the drill rods once the drill head had been
collared was required. The survey indicated the
hole orientation had moved 1 degree to the west
and the hole dip lifted by 1 degree.
21THE MINE SURVEYORS ROLE
- On completion of the smaller raisebore pilot
hole, surveys of both the lifeline hole and the
pilot hole were undertaken. This was critical to
ensure that the lifeline hole to the two miners
was not compromised in any way. - The raisebore pilot hole was then reamed out to
its full size of 1.07 m diameter. Early on Sunday
(7th May) morning a survey of the raisebore
tunnel was completed. The survey was processed,
3D solids created and plans including section
views produced, which were forwarded to the EOCG.
22THE MINE SURVEYORS ROLE
- The remaining 1.4 metres of tunnelling was
completed in two parts using a material call PCF
(penetrating cone fracture). A survey was
completed after the first firing occurred. - The final survey was completed after the tunnel
was bogged clean following the second firing.
At the same time a reference point was marked up
on the backs of the tunnel. This point was later
used for locating probe holes drilled upwards to
break into the 925 sill drive.
23THE MINE SURVEYORS ROLE
- The survey was processed and a complete 3D solid
model of the rescue tunnel, access drive, the
lifeline hole and the 940 stoping block
generated. Plans and sections were produced so
that the EOCG could determine how best to proceed
to ensure the safe rescue of the trapped miners.
24THE MINE SURVEYORS ROLE
Fig. 6 - Section view of Access Drive, Rescue
Tunnel, Comms/food hole, Stope and Raisebore rig.
25THE MINE SURVEYORS ROLE
Fig. 7 a 3D solid model of the rescue site
generated in Surpac.
26THE MINE SURVEYORS ROLE
- Probe holes were drilled with one breaking
through that the two miners could touch. A few
hours later in the early hours of the 9th of May,
2006 the two miners were freed and the rescue
mission successfully completed.
27FACTORS THAT CONTRIBUTED TO A SUCCESSFUL OUTCOME
- The involvement of the BMJV mine surveyors was
obviously essential to the overall success of the
rescue mission. The survey team formed part of
the collective rescue team comprised of the BMJV
workforce, other mining professionals, miners and
mines rescue team from other mines and emergency
services personnel that facilitated the rescue of
the two miners. - There were a number of factors from a surveying
point of view that enabled the BMJV mine
surveyors to undertake their work in an effective
manner with a high degree of confidence.
28FACTORS THAT CONTRIBUTED TO A SUCCESSFUL OUTCOME
- Of great benefit to the overall success of the
rescue was that a comprehensive CMS survey of the
925 Lift 1 stope completed on the morning of the
25th of April. - The application of wall stations in conjunction
with the Leica TCRA 1105 theodolite and its on
board free station" software.
29FACTORS THAT CONTRIBUTED TO A SUCCESSFUL OUTCOME
- Our role was confined to providing survey
expertise during the rescue. - Comprehensive survey pickups of all headings,
particularly the production headings. 3D solids
of all excavations, in particular active
production headings are generated monthly along
with the updating of the mine long section. - Regular Check Surveys of the primary survey
network.
30CLOSING OUT
- At the time of submission of this presentation it
is still not possible to comment on the rescue or
other related issues or provide additional plans
or images. - I would like to thank my fellow Mine Surveyors,
Damian Gardiner and Peter Wylie for their
unwavering efforts during the rescue and those
who extended support and praise at the completion
of the rescue.
31CLOSING OUT
- The overall success of the rescue was a result of
a focused, committed effort by every person on
site at Beaconsfield, lead by Mine Manager,
Matthew Gill and his management team. - The loss of Larry Knight during the tragedy and
the impact on his partner Jacquie and their
children is never far from our thoughts.