Title: Catskill Aqueduct Pressurization
1NYWEA 2008 Watershed Conference
Pressurizing the Catskill Aqueduct to Increase
NYCs Water System Reliability
September 17, 2008
Roopesh Joshi, Hazen and Sawyer
2Cat-Del Water Supply System
Project Background
- Cat/Del system supplies approximately 90 of New
York Citys water supply
Project Site
Kensico Eastview Section of Catskill Aqueduct
3Project Background
- UV Facility to be designed and constructed in
lieu of starting final design of a 2,000-mgd
Water Filtration Plant
- UV Facility to be located on City property at
Eastview
4Schematic of Flow to and from UV Facility
- Pressurization of a segment of the Catskill
Aqueduct needed for aqueduct to service UV
Facility at Eastview
5Pressurization of the Catskill Aqueductas Raw
Water Supply to Eastview
- Eliminates the need for pumping to the UV
Facility if using Catskill Aqueduct for raw water
supply
- Increases reliability of raw water supply to
Eastview by providing a second conduit
6Pressurization
- Goal Determine the rehabilitation measures
needed for pressurization of Catskill Aqueduct
from Kensico Reservoir to the Eastview Site to
convey raw water to the UV Facility - Lower Effluent Chamber (LEC) currently controls
flow, operates on Kensico HGL Elev. 355 - Aqueduct currently operates under free-surface
gravity flow conditions, Elev. 311 - UV Facility requires raw water at Kensico HGL,
Elev. 355
72004 Aqueduct Inspections
- Aqueduct inspected from Upper Effluent Chamber
(UEC) to Catskill Connection Chamber (CCC) - Length 12,443 feet
- Structures also inspected, where possible
8Aqueduct Sections Inspected
- Dike Grade Tunnel (1,165 feet)
- Kensico Cut-and-Cover (CC) Tunnel (2,176 feet)
- Kensico Grade Tunnel (1,515 feet)
- Kensico Steel Pipe Siphon (1,612 feet) center
pipe only - Eastview CC (99 feet)
- Eastview Grade Tunnel (5,456 feet between
Eastview CC and Elmsford North CC) - Includes brick-lined section
- Elmsford North CC (176 feet)
- Kensico (Catskill) Venturi Meter (could not be
dewatered for inspection)
9Existing Aqueduct Conditions - Summary
- Sections of Aqueduct between Kensico Reservoir
and Eastview in good condition. - Samples of concrete lining extracted during
coring indicate structurally sound concrete. - Concrete reinforcement in circular reinforced
concrete sections in good condition and free of
rust. - Ultrasonic measurements indicate competent lining
or minor deterioration. - Majority of deficiencies found at locations of
groundwater infiltration. Results of GPR and
ultrasonic testing indicate presence of voids and
cavities behind the liner in these locations.
10Aqueduct Pressurization
- Rehabilitation
- Aqueduct Sections
11Rehabilitation Options
- All options considered both operating (primarily
exfiltration) - and dewatered (infiltration) aqueduct conditions
in - determining type and extent of rehabilitation
work - Option A Watertight Tunnel no leakage allowed
in any section (1 gpm/ft dia/mi) - Option B Reduced Leakage no leakage allowed to
surface, reduced leakage in sections where
aqueduct HGL is below ground surface
12Rehabilitation Options (Continued)
- Option C Minimum Rehabilitation required for
- pressurization no leakage allowed to surface
- For any section of aqueduct, rehabilitation cost
is - proportional to the work required. From Option A
- most costly, to Option C least costly
- Option A Watertight Tunnel
- Option B Reduced Leakage
- Option C Minimum Rehabilitation
13Aqueduct RehabilitationGrouting Program for
Base Case and Drift Tunnel Alternatives
- Purpose
- Fill voids
- Achieve good contact between lining and
surrounding media - Consolidate the ground
- Cut off water infiltration and exfiltration
14Contact Grouting
Option C
15Materials Evaluated for Aqueduct Rehabilitation
- Strengthening
- Waterproofing
- Corrosion Proofing
- Strengthening through the addition of 2-inch
to 12-inch shotcrete lining with or without
reinforcement. - Waterproofing through the use of an internal
membrane concrete admixture.
16Replacement of Brick Lining in the Eastview Grade
Tunnel
- For Options A, B and C
- Replace brick lining with new reinforced concrete
section apply waterproofing
17Aqueduct Pressurization
- Rehabilitation
- Existing Structures
18Rehabilitation of Existing Structures
- Floor elevation of existing structures is
approximately 330 feet too low for
pressurization to 355 feet. - Structures must be modified to withstand the
increased hydraulic grade. - Existing Screen Chamber
- Currently undersized for anticipated flows and
operates below future HGL of 355. - Remove equipment within existing Screen Chamber.
- Screening for Catskill Aqueduct to be replaced by
new Screen Chamber sized for increased flows to
over 1,000 mgd.
19Rehabilitation of StructuresExisting Screen
Chamber
- Aqueduct will pass through this structure as a
17-foot diameter pressure conduit partially
demolish four piers in flow path
- Balance of structure will be backfilled between
new pressure conduit and chamber walls - Access into aqueduct through modified structure
will be provided
20New Structures
- Screen Chamber
- Screening of Catskill Aqueduct flow from Kensico
Reservoir - Sized for anticipated flows of over 1,000 mgd
- Bypass Chamber
- Provides the connection point along the Catskill
Aqueduct for transmitting raw water to the new UV
Facility at the Eastview Site. - Bypass Chamber is the point up to which the
aqueduct will be pressurized. - Drift Tunnel
- Connects the Bypass Chamber to the new UV
Facility at the Eastview Site through a new 17-ft
diameter rock tunnel.
21New Screen Chamber - Plan
- Construct between LEC and abandoned Catskill
Aerators
22New Screen Chamber - Plan
- Build structure off-line (while aqueduct is
active)
23New Screen Chamber - Plan
- Connect structure, and plug unused aqueduct
section during shutdown
24New Bypass Chamber
- Construct BC adjacent to existing Aqueduct,
off-line - During an Aqueduct shutdown, make connections to
and from BC, and bulkhead aqueduct directing flow
through BC
Catskill Aqueduct
To Hillview
From Kensico
Air Gap
To UV Facility
Bypass Chamber
25Bypass Chamber and Drift Tunnel Alternatives
- Location depends on selected conveyance route
- Maximum aqueduct capacity is different for each
Drift Tunnel alternative.
26Bypass Chamber for Drift Tunnel 1 - Section
27Bypass Chamber for Drift Tunnel 3 - Section
28Aqueduct Pressurization
29Recommendation
30Recommended Plan Catskill Aqueduct
Pressurization
- Recommended Plan Provides the Greatest Hydraulic
Capacity at the Least Cost - Rehabilitation Option C (Minimum
Rehabilitation) - Drift Tunnel Alternative 1
- New 1,000 mgd Screen Chamber
- Modifications to existing structures
31Overall Schedule for Recommended Alternative
32Acknowledgements
- Mike Broder, Hazen and Sawyer
- Rich Peters, Hazen and Sawyer
- David Tanzi, CDM
- Leszek Glodkowski, Jenny Engineering
- Paul Smith, New York City DEP
33Questions?
REHABILITATION
Catskill Aqueduct
In association with
34Leakage Analysis of Ex-filtration
Aqueduct Rehabilitation
- Based on Dr. Ronald E. Heuers review, there is
no calculable expected seepage outflow after
conducting Option C.
35Updated Construction Costs for Recommended
Alternative
Summary of Recommended Alternative