Catskill Aqueduct Pressurization - PowerPoint PPT Presentation

1 / 35
About This Presentation
Title:

Catskill Aqueduct Pressurization

Description:

Catskill Aqueduct Pressurization – PowerPoint PPT presentation

Number of Views:487
Avg rating:3.0/5.0
Slides: 36
Provided by: JV84
Category:

less

Transcript and Presenter's Notes

Title: Catskill Aqueduct Pressurization


1
NYWEA 2008 Watershed Conference
Pressurizing the Catskill Aqueduct to Increase
NYCs Water System Reliability
September 17, 2008
Roopesh Joshi, Hazen and Sawyer
2
Cat-Del Water Supply System
Project Background
  • Cat/Del system supplies approximately 90 of New
    York Citys water supply

Project Site
Kensico Eastview Section of Catskill Aqueduct
3
Project Background
  • UV Facility to be designed and constructed in
    lieu of starting final design of a 2,000-mgd
    Water Filtration Plant
  • UV Facility to be located on City property at
    Eastview

4
Schematic of Flow to and from UV Facility
  • Pressurization of a segment of the Catskill
    Aqueduct needed for aqueduct to service UV
    Facility at Eastview

5
Pressurization of the Catskill Aqueductas Raw
Water Supply to Eastview
  • Eliminates the need for pumping to the UV
    Facility if using Catskill Aqueduct for raw water
    supply
  • Increases reliability of raw water supply to
    Eastview by providing a second conduit

6
Pressurization
  • Goal Determine the rehabilitation measures
    needed for pressurization of Catskill Aqueduct
    from Kensico Reservoir to the Eastview Site to
    convey raw water to the UV Facility
  • Lower Effluent Chamber (LEC) currently controls
    flow, operates on Kensico HGL Elev. 355
  • Aqueduct currently operates under free-surface
    gravity flow conditions, Elev. 311
  • UV Facility requires raw water at Kensico HGL,
    Elev. 355

7
2004 Aqueduct Inspections
  • Aqueduct inspected from Upper Effluent Chamber
    (UEC) to Catskill Connection Chamber (CCC)
  • Length 12,443 feet
  • Structures also inspected, where possible

8
Aqueduct Sections Inspected
  • Dike Grade Tunnel (1,165 feet)
  • Kensico Cut-and-Cover (CC) Tunnel (2,176 feet)
  • Kensico Grade Tunnel (1,515 feet)
  • Kensico Steel Pipe Siphon (1,612 feet) center
    pipe only
  • Eastview CC (99 feet)
  • Eastview Grade Tunnel (5,456 feet between
    Eastview CC and Elmsford North CC)
  • Includes brick-lined section
  • Elmsford North CC (176 feet)
  • Kensico (Catskill) Venturi Meter (could not be
    dewatered for inspection)

9
Existing Aqueduct Conditions - Summary
  • Sections of Aqueduct between Kensico Reservoir
    and Eastview in good condition.
  • Samples of concrete lining extracted during
    coring indicate structurally sound concrete.
  • Concrete reinforcement in circular reinforced
    concrete sections in good condition and free of
    rust.
  • Ultrasonic measurements indicate competent lining
    or minor deterioration.
  • Majority of deficiencies found at locations of
    groundwater infiltration. Results of GPR and
    ultrasonic testing indicate presence of voids and
    cavities behind the liner in these locations.

10
Aqueduct Pressurization
  • Rehabilitation
  • Aqueduct Sections

11
Rehabilitation Options
  • All options considered both operating (primarily
    exfiltration)
  • and dewatered (infiltration) aqueduct conditions
    in
  • determining type and extent of rehabilitation
    work
  • Option A Watertight Tunnel no leakage allowed
    in any section (1 gpm/ft dia/mi)
  • Option B Reduced Leakage no leakage allowed to
    surface, reduced leakage in sections where
    aqueduct HGL is below ground surface

12
Rehabilitation Options (Continued)
  • Option C Minimum Rehabilitation required for
  • pressurization no leakage allowed to surface
  • For any section of aqueduct, rehabilitation cost
    is
  • proportional to the work required. From Option A
  • most costly, to Option C least costly
  • Option A Watertight Tunnel
  • Option B Reduced Leakage
  • Option C Minimum Rehabilitation

13
Aqueduct RehabilitationGrouting Program for
Base Case and Drift Tunnel Alternatives
  • Purpose
  • Fill voids
  • Achieve good contact between lining and
    surrounding media
  • Consolidate the ground
  • Cut off water infiltration and exfiltration

14
Contact Grouting
  • Options A and B

Option C
15
Materials Evaluated for Aqueduct Rehabilitation
  • Strengthening
  • Waterproofing
  • Corrosion Proofing
  • Strengthening through the addition of 2-inch
    to 12-inch shotcrete lining with or without
    reinforcement.
  • Waterproofing through the use of an internal
    membrane concrete admixture.

16
Replacement of Brick Lining in the Eastview Grade
Tunnel
  • For Options A, B and C
  • Replace brick lining with new reinforced concrete
    section apply waterproofing

17
Aqueduct Pressurization
  • Rehabilitation
  • Existing Structures

18
Rehabilitation of Existing Structures
  • Floor elevation of existing structures is
    approximately 330 feet too low for
    pressurization to 355 feet.
  • Structures must be modified to withstand the
    increased hydraulic grade.
  • Existing Screen Chamber
  • Currently undersized for anticipated flows and
    operates below future HGL of 355.
  • Remove equipment within existing Screen Chamber.
  • Screening for Catskill Aqueduct to be replaced by
    new Screen Chamber sized for increased flows to
    over 1,000 mgd.

19
Rehabilitation of StructuresExisting Screen
Chamber
  • Aqueduct will pass through this structure as a
    17-foot diameter pressure conduit partially
    demolish four piers in flow path
  • Balance of structure will be backfilled between
    new pressure conduit and chamber walls
  • Access into aqueduct through modified structure
    will be provided

20
New Structures
  • Screen Chamber
  • Screening of Catskill Aqueduct flow from Kensico
    Reservoir
  • Sized for anticipated flows of over 1,000 mgd
  • Bypass Chamber
  • Provides the connection point along the Catskill
    Aqueduct for transmitting raw water to the new UV
    Facility at the Eastview Site.
  • Bypass Chamber is the point up to which the
    aqueduct will be pressurized.
  • Drift Tunnel
  • Connects the Bypass Chamber to the new UV
    Facility at the Eastview Site through a new 17-ft
    diameter rock tunnel.

21
New Screen Chamber - Plan
  • Construct between LEC and abandoned Catskill
    Aerators

22
New Screen Chamber - Plan
  • Build structure off-line (while aqueduct is
    active)

23
New Screen Chamber - Plan
  • Connect structure, and plug unused aqueduct
    section during shutdown

24
New Bypass Chamber
  • Construct BC adjacent to existing Aqueduct,
    off-line
  • During an Aqueduct shutdown, make connections to
    and from BC, and bulkhead aqueduct directing flow
    through BC

Catskill Aqueduct
To Hillview
From Kensico
Air Gap
To UV Facility
Bypass Chamber
25
Bypass Chamber and Drift Tunnel Alternatives
  • Location depends on selected conveyance route
  • Maximum aqueduct capacity is different for each
    Drift Tunnel alternative.

26
Bypass Chamber for Drift Tunnel 1 - Section
27
Bypass Chamber for Drift Tunnel 3 - Section
28
Aqueduct Pressurization
  • Costs

29
Recommendation
30
Recommended Plan Catskill Aqueduct
Pressurization
  • Recommended Plan Provides the Greatest Hydraulic
    Capacity at the Least Cost
  • Rehabilitation Option C (Minimum
    Rehabilitation)
  • Drift Tunnel Alternative 1
  • New 1,000 mgd Screen Chamber
  • Modifications to existing structures

31
Overall Schedule for Recommended Alternative
32
Acknowledgements
  • Mike Broder, Hazen and Sawyer
  • Rich Peters, Hazen and Sawyer
  • David Tanzi, CDM
  • Leszek Glodkowski, Jenny Engineering
  • Paul Smith, New York City DEP

33
Questions?
REHABILITATION
Catskill Aqueduct
In association with
34
Leakage Analysis of Ex-filtration
Aqueduct Rehabilitation
  • Based on Dr. Ronald E. Heuers review, there is
    no calculable expected seepage outflow after
    conducting Option C.

35
Updated Construction Costs for Recommended
Alternative
Summary of Recommended Alternative
Write a Comment
User Comments (0)
About PowerShow.com