Title: PILLEIR
1PIL/LEIR
Presented by M. CHANEL
April 4th 2002 -PILLEIR
2CONTENTS
- LEAD on LEAD
- Baseline scheme
- Why not other alternatives
- LINAC3
- LEIR
- PS
- Different systems
- Cost
- Planning
- Summary
3Performance needed for LEAD ions
- 7 107 Lead ions/bunch in LHC at 2.7 TeV/n in a
normalised emittance of 1.5 mm(bg s2/bh,v). (
quench limit and central detector limit) - Overall transfer efficiency of 30,
- elt1.2 mm at the exit of SPS,
- elt1 mm at the entrance of SPS after final
stripping, - elt0.7 mm at the entrance of PS.
- A total of 0.9 109 ions extracted from LEIR
4GENERAL SCHEME
LHC.LEAD.new.PUB
5(No Transcript)
6(No Transcript)
7Stacking tests of lead ions
requested
Sourceefficiency
Lossescharge state
With the lattice used, it was not possible to
accelerate the beam
8Other solutions
9Measured by GC/MCEmit_Pb_R4.new.xls
10LIS
- Â 6mA, 5.5ms would suffice. But about 14MF
investment. - As the 6mA Laser Ion Source for lead production
is still an untested prototype and many
parameters are yet unknown, thus it is not
recommended to base the LHC ion program on this
alternative (S. Maury, Reflection on the
Different Lead Ion Injection Variants for LHC,
PS/AE Note 2001-019).
11LINAC3
- Improved afterglow pulsed ECR source (450ms
pulse length but increased current from 100mA to
120mA-lower stability- to 200mA (RF heating
from14 to 18GHz) Lead 27 LEIR uses 200 ms).
If more ions needed than change the
spectrometer, move the sourceexpensive. - Accelerate to 4.2 MeV/n, b0.0945
- Add a cavity to ramp the momentum up to 1
- Stripping afterwards and use of Lead 54
(Slightly less intensity than for Lead53, but
acceptable lifetime with electrons of the cooler
) - Pulsing from 0.8 Hz up to 5 Hz (10 Hz possible).
(10 pulsed power supplies and thermal switches on
magnets)
Collaboration Catania, Grenobles, Cern, GSI
12LEIR
- Combined H/V/P multiturn injection inclined
septum momentum variation of incoming beam such
the injection orbit (D dp/pbump) remains the
same during injection. 50 injection efficiency
reachable(75 on paper). Recuperate magnetic
septum, bumpers. - Cool and stack the freshly injected beam by
electron cooling in 400 ms max. - 4 injection-cooling-stacking cycles should be
enough (timelt1.6s). - Acceleration and ejection (h2) at T72MeV/n
energy choice is a compromise between the limit
of incoherent tune shift in PS, the time between
bunches for the ejection kicker, the min RF
frequency in PS and the stacking time in SPS/LHC.
13LEIR Injection
- Combined injection gives lower et (better cooling
time) compared to normal multiturn but increases
mom. spread (good long. cool.). - Combined injection implies large D and D/??h
5m1/2 (D10, bh3).
14X-Y plane105 turns tracked
Cooled beam
E-SEPTUM
New beam from linac D0
15- X-Y plane after 100 turns
- 75 injected
- x and y and momentum projected distributions
16LEIR INJECTION LINE
17Cooling and Stacking
- Electron cooling theory gives
- where q is the relative difference in angle
between the ions and electrons qi?(?/?) - the parameter hecool Lcooler/Lmachine
- and Ie is the electron current.
- A and Q atom mass and charge state
- Large b desirable but ion beam size should remain
smaller then e-beam size and mind the effect of
the e-beam space charge. optimum around b5m - With D0, stack and injected beam are in the
centre of the e-beam, but this not the best value
for cooling.
18Lattice
- Good for injection and coolingstill 2 periods
- tune(1.8,2.7)
- longitudinal acceptance reduced to dp/p 1
- 5 quad families, more flexibility.
19Electron cooling
20(No Transcript)
21GUN
Dipole
Toroïd
DRIFT
22(No Transcript)
23(No Transcript)
24LEIR cycle for LEAD ions
25LEIR RF
- 2 RF cavities using Finemet built in
collaboration with KEK
26OTHERS
- With an electron beam of 200mA, the cooling rate
is sufficient to counteract the IBS growth rate
and get the emittances wanted. - The beam will be maintained stable mainly during
cooling (coasting beam) by a 100MHz bandwidth
transverse active feedback.
27SPACE CHARGE ALONG THE CHAIN
- Takes into account all the new features
- Note the stripping between LEIR and PS gives
large De
28LEIR EJECTION TO PS
29A word on vacuum
- During the tests in 1997, the Lear vacuum was
good (5E-12T without beam) but the lost lead
ions (e-ion recombination..lead 54 or res. gas
charge exchange or..) degas the chamber walls.
One lead ion releases 105 molecules!!!! - At end of linac3, tests of different vacuum
chamber treatment are under way. - Hope outgassing can be reduced by appropriate
treatment of the vacuum chamber. - Already known when ions are lost perpendicularly
to walls, outgassing is decreased.
30(No Transcript)
31(No Transcript)
32LEIR TDR E. Mahner
 Figure 2 Dynamic pressure simulation for a 15
m long part, including a bending magnet, of the
LEIR vacuum system. As input parameters the
measured (at Linac3) desorption yield of ?tot 2
? 104 molec./ion and a typical gas composition
(CO (72), CO2 (18), CH4 (7), H2 (3)) at the
beginning of beam scrubbing has been chosen. Two
scenarios are displayed a) open symbols lumped
pumps (existing from LEAR) resulting in an
average pressure of 3 ? 10-11 Torr, b) closed
symbols lumped pumps plus linear getter (St707
strips) giving an average dynamic pressure of
about 5 ? 10-12 Torr, a number very close to the
design value. The position of the about 6 m long
vacuum chamber inside the bending magnet is
indicated on the x-axis.
33PS
- Inject (change septum-modif. kicker) and
accelerate on h16 up to .. - h16?14?12, split 2b. to 4 bunches and finally
h24 ?21 - h21 is chosen to have 100ns b. separation at
flatop in LHC and it is compatible at 6.01 GeV/n
with 200MHz RF system in SPS. - Acceleration to 6.01 GeV/n(g7.45), cp/Q26.
GeV/c/charge. - Stripping in TT2. Change of TT2 line to have a
low beta at stripper.
Steves talk
34TT2(from PS to SPS, has to be changed)
- At stripper bh,v20m?5m, D-1m
- Blow-up reduced by a factor 4 compared to
old(normal)optic.needs MD for SPS matching.
De0.2mm after re-matching in SPS?. - Need of 4 quads, 6 power supplies
building.(mostly recuperated)
35Different Systems (not detailed)
- RECUPERATION AS MUCH AS POSSIBLE
- Inj./Ej. Line magnet spec. 8 QTWs, 2 BHN 1.7 and
0.4 Tm2 cores, 2-4 DVN instrumentation. One
inclined SEH , one pulsed magnetic septum, and
pulsed power supplies. All others recup. But some
power supplies modifications or renewal(kickers,
bumpers) - Electron cooling- new by Novosibirsk 2 DHVs and
Old quad power supplies for solenoids. - Machine magnets- all recuperated (even 4 reserve
quad added ) but 6 big powers supplies (BHN5
quads families) . renewal of controls. - RF-2 cavities specified-
- Machine instrumentation- specifs known, most of
the hardware is recuperated.
36Different Systems (suite)
- MechanicsAll elements position known
- Vacuum specified as lifetime of lead30s. The
final study is nearly to be finished. - Controls ok but not detailed.
37PLANNING
- x work on machine d design m
manufacture t test - l linac3 design/modif. p ps design
- R Runs L LHC runs
38LEIR COST (and only LEIR)
/specifications/cost-recapitule/cost.2008..xls
39Staffing (LEIR only)
40PIL cost
41Total PILLEIR
42Summary
- Lead ion scheme nearly finished (draft DR)
- Electron cooling of heavy ions is defined.
- Space charge limits both in LEIR, PS, SPS are
harmonised. - Vacuum degradation due to losses is well
understood. - IBS and conservation of high beam density is , as
for protons, the main challenge. - Planning established, cost known without
contingencies, but some points are evolving. - All technical systems are specified.
43OUTLOOK
- People are ready to start the final design of
their systems. - Awaiting for financial resources.
44Why a difference with the original price (1994)
45TUNE SHIFT