PILLEIR - PowerPoint PPT Presentation

1 / 45
About This Presentation
Title:

PILLEIR

Description:

PIL/LEIR. Presented by M. CHANEL. April 4th 2002 -PILLEIR. CONTENTS. LEAD on LEAD. Baseline scheme ... 7 107 Lead ions/bunch in LHC at 2.7 TeV/n in a ... – PowerPoint PPT presentation

Number of Views:163
Avg rating:3.0/5.0
Slides: 46
Provided by: chanelH
Category:
Tags: pilleir | chanel

less

Transcript and Presenter's Notes

Title: PILLEIR


1
PIL/LEIR
Presented by M. CHANEL
April 4th 2002 -PILLEIR
2
CONTENTS
  • LEAD on LEAD
  • Baseline scheme
  • Why not other alternatives
  • LINAC3
  • LEIR
  • PS
  • Different systems
  • Cost
  • Planning
  • Summary

3
Performance needed for LEAD ions
  • 7 107 Lead ions/bunch in LHC at 2.7 TeV/n in a
    normalised emittance of 1.5 mm(bg s2/bh,v). (
    quench limit and central detector limit)
  • Overall transfer efficiency of 30,
  • elt1.2 mm at the exit of SPS,
  • elt1 mm at the entrance of SPS after final
    stripping,
  • elt0.7 mm at the entrance of PS.
  • A total of 0.9 109 ions extracted from LEIR

4
GENERAL SCHEME
LHC.LEAD.new.PUB
5
(No Transcript)
6
(No Transcript)
7
Stacking tests of lead ions
requested
Sourceefficiency
Lossescharge state
With the lattice used, it was not possible to
accelerate the beam
8
Other solutions
9
Measured by GC/MCEmit_Pb_R4.new.xls
10
LIS
  •  6mA, 5.5ms would suffice. But about 14MF
    investment.
  • As the 6mA Laser Ion Source for lead production
    is still an untested prototype and many
    parameters are yet unknown, thus it is not
    recommended to base the LHC ion program on this
    alternative (S. Maury, Reflection on the
    Different Lead Ion Injection Variants for LHC,
    PS/AE Note 2001-019).

11
LINAC3
  • Improved afterglow pulsed ECR source (450ms
    pulse length but increased current from 100mA to
    120mA-lower stability- to 200mA (RF heating
    from14 to 18GHz) Lead 27 LEIR uses 200 ms).
    If more ions needed than change the
    spectrometer, move the sourceexpensive.
  • Accelerate to 4.2 MeV/n, b0.0945
  • Add a cavity to ramp the momentum up to 1
  • Stripping afterwards and use of Lead 54
    (Slightly less intensity than for Lead53, but
    acceptable lifetime with electrons of the cooler
    )
  • Pulsing from 0.8 Hz up to 5 Hz (10 Hz possible).
    (10 pulsed power supplies and thermal switches on
    magnets)

Collaboration Catania, Grenobles, Cern, GSI
12
LEIR
  • Combined H/V/P multiturn injection inclined
    septum momentum variation of incoming beam such
    the injection orbit (D dp/pbump) remains the
    same during injection. 50 injection efficiency
    reachable(75 on paper). Recuperate magnetic
    septum, bumpers.
  • Cool and stack the freshly injected beam by
    electron cooling in 400 ms max.
  • 4 injection-cooling-stacking cycles should be
    enough (timelt1.6s).
  • Acceleration and ejection (h2) at T72MeV/n
    energy choice is a compromise between the limit
    of incoherent tune shift in PS, the time between
    bunches for the ejection kicker, the min RF
    frequency in PS and the stacking time in SPS/LHC.

13
LEIR Injection
  • Combined injection gives lower et (better cooling
    time) compared to normal multiturn but increases
    mom. spread (good long. cool.).
  • Combined injection implies large D and D/??h
    5m1/2 (D10, bh3).

14
X-Y plane105 turns tracked
Cooled beam
E-SEPTUM
New beam from linac D0
15
  • X-Y plane after 100 turns
  • 75 injected
  • x and y and momentum projected distributions

16
LEIR INJECTION LINE
17
Cooling and Stacking
  • Electron cooling theory gives
  • where q is the relative difference in angle
    between the ions and electrons qi?(?/?)
  • the parameter hecool Lcooler/Lmachine
  • and Ie is the electron current.
  • A and Q atom mass and charge state
  • Large b desirable but ion beam size should remain
    smaller then e-beam size and mind the effect of
    the e-beam space charge. optimum around b5m
  • With D0, stack and injected beam are in the
    centre of the e-beam, but this not the best value
    for cooling.

18
Lattice
  • Good for injection and coolingstill 2 periods
  • tune(1.8,2.7)
  • longitudinal acceptance reduced to dp/p 1
  • 5 quad families, more flexibility.

19
Electron cooling
20
(No Transcript)
21
GUN
Dipole
Toroïd
DRIFT
22
(No Transcript)
23
(No Transcript)
24
LEIR cycle for LEAD ions
25
LEIR RF
  • 2 RF cavities using Finemet built in
    collaboration with KEK

26
OTHERS
  • With an electron beam of 200mA, the cooling rate
    is sufficient to counteract the IBS growth rate
    and get the emittances wanted.
  • The beam will be maintained stable mainly during
    cooling (coasting beam) by a 100MHz bandwidth
    transverse active feedback.

27
SPACE CHARGE ALONG THE CHAIN
  • Takes into account all the new features
  • Note the stripping between LEIR and PS gives
    large De

28
LEIR EJECTION TO PS
29
A word on vacuum
  • During the tests in 1997, the Lear vacuum was
    good (5E-12T without beam) but the lost lead
    ions (e-ion recombination..lead 54 or res. gas
    charge exchange or..) degas the chamber walls.
    One lead ion releases 105 molecules!!!!
  • At end of linac3, tests of different vacuum
    chamber treatment are under way.
  • Hope outgassing can be reduced by appropriate
    treatment of the vacuum chamber.
  • Already known when ions are lost perpendicularly
    to walls, outgassing is decreased.

30
(No Transcript)
31
(No Transcript)
32
LEIR TDR E. Mahner
  Figure 2 Dynamic pressure simulation for a 15
m long part, including a bending magnet, of the
LEIR vacuum system. As input parameters the
measured (at Linac3) desorption yield of ?tot 2
? 104 molec./ion and a typical gas composition
(CO (72), CO2 (18), CH4 (7), H2 (3)) at the
beginning of beam scrubbing has been chosen. Two
scenarios are displayed a) open symbols lumped
pumps (existing from LEAR) resulting in an
average pressure of 3 ? 10-11 Torr, b) closed
symbols lumped pumps plus linear getter (St707
strips) giving an average dynamic pressure of
about 5 ? 10-12 Torr, a number very close to the
design value. The position of the about 6 m long
vacuum chamber inside the bending magnet is
indicated on the x-axis.
33
PS
  • Inject (change septum-modif. kicker) and
    accelerate on h16 up to ..
  • h16?14?12, split 2b. to 4 bunches and finally
    h24 ?21
  • h21 is chosen to have 100ns b. separation at
    flatop in LHC and it is compatible at 6.01 GeV/n
    with 200MHz RF system in SPS.
  • Acceleration to 6.01 GeV/n(g7.45), cp/Q26.
    GeV/c/charge.
  • Stripping in TT2. Change of TT2 line to have a
    low beta at stripper.

Steves talk
34
TT2(from PS to SPS, has to be changed)
  • At stripper bh,v20m?5m, D-1m
  • Blow-up reduced by a factor 4 compared to
    old(normal)optic.needs MD for SPS matching.
    De0.2mm after re-matching in SPS?.
  • Need of 4 quads, 6 power supplies
    building.(mostly recuperated)

35
Different Systems (not detailed)
  • RECUPERATION AS MUCH AS POSSIBLE
  • Inj./Ej. Line magnet spec. 8 QTWs, 2 BHN 1.7 and
    0.4 Tm2 cores, 2-4 DVN instrumentation. One
    inclined SEH , one pulsed magnetic septum, and
    pulsed power supplies. All others recup. But some
    power supplies modifications or renewal(kickers,
    bumpers)
  • Electron cooling- new by Novosibirsk 2 DHVs and
    Old quad power supplies for solenoids.
  • Machine magnets- all recuperated (even 4 reserve
    quad added ) but 6 big powers supplies (BHN5
    quads families) . renewal of controls.
  • RF-2 cavities specified-
  • Machine instrumentation- specifs known, most of
    the hardware is recuperated.

36
Different Systems (suite)
  • MechanicsAll elements position known
  • Vacuum specified as lifetime of lead30s. The
    final study is nearly to be finished.
  • Controls ok but not detailed.

37
PLANNING
  • x work on machine d design m
    manufacture t test
  • l linac3 design/modif. p ps design
  • R Runs L LHC runs

38
LEIR COST (and only LEIR)
/specifications/cost-recapitule/cost.2008..xls
39
Staffing (LEIR only)
40
PIL cost
41
Total PILLEIR
42
Summary
  • Lead ion scheme nearly finished (draft DR)
  • Electron cooling of heavy ions is defined.
  • Space charge limits both in LEIR, PS, SPS are
    harmonised.
  • Vacuum degradation due to losses is well
    understood.
  • IBS and conservation of high beam density is , as
    for protons, the main challenge.
  • Planning established, cost known without
    contingencies, but some points are evolving.
  • All technical systems are specified.

43
OUTLOOK
  • People are ready to start the final design of
    their systems.
  • Awaiting for financial resources.

44
Why a difference with the original price (1994)
45
TUNE SHIFT
Write a Comment
User Comments (0)
About PowerShow.com