Title: GENERATION
1GENERATION RENOVATION MODERNISATION
R. K. Jain Director (Technical) NTPC Limited
India Electricity 2006 11th May, 2006
2INDIAN POWER SECTOR
- Present Status
- Per capita consumption about 600 units per annum
- Installed Capacity 1,24,287 MW (April, 2006)
- Indias Projected Growth is 7-8 of GDP
Projected power requirement by year 2012 - Per capita consumption 1000 units per annum
- Installed capacity over 2,00,000 MW
- Projected power requirement by year 2032
- Per capita consumption about 3000 units per annum
- Installed capacity about 6,00,000 to 7,00,000 MW
- However government of India is targeting double
digit growth rate (10) and hence projections are
likely to get revised upwards. The above
necessitates - Sustainable Large Capacity Addition Program at
higher efficiency - Upgrading fleet of Old Power Stations which are
inefficient and have poor availability
3RM and Re-powering
- India has large number of old plants which are
inefficient and running below design capacity - Operating pressure and temperature of these old
plants are lower and there is no reheating in
some of the units - Fuel available at present is different from what
plant were designed for - Some of the equipments have degraded
- Re-powering of these plant can quickly increase
the power generation at relatively lower cost to
consumer - Re-powering can increase the cycle efficiency
and hence reduce emission of greenhouse gases and
pollutants
4RM and Re-powering
- RM will involve up gradation of milling system,
APH, ESP, firing system etc and refurbishment of
turbine, condenser, pressure parts, fans etc. - Re-powering may involve following changes in
plant design - Adoption of higher steam parameters
- Introduction of topping cycle, old turbine may be
retained in bottoming cycle. - Bottoming turbine cycle efficiency improvement by
adoption of high efficiency blade design - Thus, Renovation Modernization of old existing
units is an important tool for capacity
enhancement, life extension and improvement in
availability, reliability efficiency. - Re-powering is challenging from technology as
well as engineering point of view and offers
huge potential for capacity addition
augmentation.
5RATIONALE FOR RM
- New Plants costly.
- Longer gestation period of new plant.
- Limited availability of new site.
- Old plants can be renovated and Modernised at
lower costs and life extension achieved. - Availability and efficiency can be improved.
- Minimum environmental impact and RR problems for
additional capacity. - RM is an efficiency improvement tool and can
improve generation by 30, environment impact by
47 and efficiency by 23 (Source TERI)
6 APPROACH TO RM
- Depends on
- Age of the plant, its existing condition and
generic problems in its inherited design - Operational History Problems being faced to run
the plant - Major modifications carried out from the original
design condition - Type of fuel its cost
- To cater to changes in the input / output of the
plant coal, water, power evacuation - Source of availability of inputs for future
- Cost of generation
- Cost of Technology
7WHY RM?
- To restore the original rated parameters by one
to one replacements - Improve performance by introduction of new
technology. - To upgrade the units to comply with fast changing
Environmental / statutory standards / guidelines. - To cater to technological obsolescence.
- Mega RM Technology Upgrades. This would aim at
both leveraging the technological advancements,
as well as driving down the Cost Of Generation,
while factoring in the emerging business scenario
to meet the market determined price for power
8Technological Options
- Clean Coal Technology
- To reduce SOX ,NOX CO2 Emissions
- Energy extraction from coal
- PC fired
- Fluidized bed combustion-Reduces Sox, NOx
Emissions - Indirect combustion through coal gasification
- Sub Critical Steam Parameters To Supercritical
Parameters - Increase in Pressure and temperature to
like 250bar and 565 deg C - Re-powering Technology
- For better efficiency, pollution control and
less cost besides life extension -
9Technological Options
- BOILER AUXILIARIES
- Replacement/Augmentation Of Pressure Parts.
- Retrofitting/ Modifications Air Pre Heater.
- Augmentation Of Milling System.
- Provision Of Flame Scanners, ignitors.
- Renovation of Draft System.
- Retrofitting Of ESPs.
-
10Technological Options
- TG AUXILIARIES
- Replacement of turbine blades with latest
design. - Modernization of condensors by change in type
and material of tubes, augmenting with tube
cleaning mechanism. - Modernisation of power cycle equipments with
more efficient pumps and improved Regenerative
Heaters. - Modification of air evacuation system with
Vacuum pumps. -
11Technological Options
- Gas Turbine
- Inlet Air Cooling system.
- Online Compressor Washing System
- Dry Low NOx Burners.
- Improved metallurgy for improved life of Hot
Gas Path Components - Improved efficiency
- Thermal Barrier Coatings of Blades Vanes.
- Improved major inspection intervals.
- Multi Fuel Firing
12Technological Options
- ELECTRICAL
- Up gradation of insulation of rotating machines
from Class B to Class F. - Up gradation of protection systems including
diagnostic tools. - Replacement of HV , EHV circuit breakers with SF6
/ Vacuum breakers for stability and to overcome
obsolescence. - CI
- Modernization of obsolete CI systems with
State- of-Art-Technology. - MISCELLANEOUS
- Augmentation Of CHP
- Augmentation Of Water Treatment Plants
- Introduction of Ash Water Re-circulation System.
13EXPECTED BENEFITS
- Increase in generation with improved performance
- Increase in safety, reliability, availability and
operational flexibility - Recapturing and/ or enhancing of unit capacity
- Extension of economic useful life by 15-20 years
at comparatively lower capital cost - Benefit by way of additional life
- Possibility of reducing cost of generation
14RM with Efficiency Increase
Increased power output resulting from efficiency
increase is free of fuel cost, free of
operational cost and free of emissions.
Rehabilitation
Rehabilitationw/o efficiency improvement
Fuel consumption per kWh
Rehabilitationwith efficiency improvement
0 20 40 years
15Mega RM
- Opting for higher steam pressure temperatures
due to the availability of better material suited
for these parameters improves heat rate and
reliability - Therefore, for old plant it may be worthwhile to
consider mega RM schemes to bring these plants
up to the contemporary state of the art plants in
terms of efficiency and availability - Typically, such mega RM may include up-rating,
re-powering, higher process parameters resulting
in enhanced efficiency, improved operational
safety, reliability, advanced diagnostics etc. - Mega RM typically consists of replacements of
major equipment / systems of the plant at
marginally higher cost longer shutdowns of the
Units are inherent.
16Plans for RM
- The importance of RM was recognised by the
Government of India way back in 1984 when PHASE-I
RM Programme for 34 thermal power stations in
the country was launched by the Central
Electricity Authority as a Centrally Sponsored
Scheme - The Government of India has now accorded high
priority to RM and Life Extension (LE) of old
existing power plants. The funds in the form of
loan assistance at concessional interest rates
are being provided by the Government through
Power Finance Corporation (PFC) for RM works
17LIFE EXTENSION PROGRAMME DURING 10TH PLAN
S. No. PARTICULARS PARTICULARS
i) Number of thermal power stations 32
ii) Number of thermal units 106
iii) Estimated Cost Rs. 9200 crores
iv) Total Capacity involved 10,413 MW
v) Average PLF of the units before LE programme 49
vi) Anticipated PLF after completion. 75
vii) Anticipated additional generation/ annum 23700 MU
viii) Capacity expected after completion of LE works 10,747 MW
18RM PROGRAMME DURING 10TH PLAN
S.No. PARTICULARS PARTICULARS
i) Number of thermal power stations 13
ii) Number of thermal units 57
iii) Estimated Cost Rs.977 crores
iv) Total Capacity involved 14270 MW
S.No. PARTICULARS PARTICULARS
i) Number of thermal power stations 13
ii) Number of thermal units 57
iii) Estimated Cost Rs.977 crores
iv) Total Capacity involved 14270 MW
1911TH PLAN PROGRAMME
Sl. No. Particulars LEP RM
i) Number of thermal power stations 18 12
ii) Number of thermal units 34 31
iii) Estimated Cost Rs.6000 Crores Rs. 751 Crores
iv) Total capacity involved 6,000 MW 7,090 MW
20Thermal Units for RM in 10th and 11th Plan
21environmental control updating
availability improvement
efficiency upgrading
life extension
reduced fuel consumption
emissions within new norms
increased electrical output
improved reliability
operation free of restrictions
increased power output
reduced power generation cost
plus CDM BENEFITS
22Challenges in RM
- Limited Agencies for RM implementation in the
country. - Prohibitive cost of New Technologies impediment
for introduction on wider scale. - Unfavorable cost benefit analysis.
- RM activity to be linked with planned shut
down.
23CDM Potential in RM
- Offers substantial CDM benefits through
reduction/substitution of coal by - Enhancement of efficiency by upgrading cycle
parameters - Co-firing of biomass with coal in coal fired
furnaces
24RM SCENARIO IN NTPC
- Department formed in 1995 to Cater to RM of its
own Stations - RM is identified as Key Thrust Area as the many
NTPC plants are crossing 1,00,000 operating hours - RM of power plants of 10,799 MW capacity has
been undertaken / in progress - RM of power plants of 7,642 MW capacity is under
planning - The cost of RM may be up to Rs. 1.5 crores per
MW depending on the life and condition of the
plant.
- NTPC RM Project under CDM
- NTPC has taken up Badarpur RM project under CDM
- PIN is already prepared
25NTPCs EXPERIENCE SO FAR
- NTPC Talcher TPS (4x60 2x110 MW)
- RM Scope
- Extensive RLA and RM of SG and TG
- Retrofitting of existing ESP and addition of new
fields - Replacement of Static Excitation System, Power
Control cables, replacement/ Retrofit of HT/LT
Switchgear ,Augmentation of H2 plant - Renovation of Cooling Towers
- Augmentation of Ash Handling
- New AWRS
- New Railway Siding inside the plant
- New Coal Handling Plant
- RM of Switchyard
- RM cost - Rs 1.50 Crs/MW
- PLF is around 88 as against 19 during takeover
in Jun 1995.
26NTPCs EXPERIENCE SO FAR
- NTPC Tanda TPS (4x110 MW)
- RM Scope
- Extensive RLA and RM of SG and TG
- ESP Renovation
- Replacement of 6.6 KV 11 KV Switch gear
- Replacement of LT Switch Gear
- Renovation of Fire Fighting system
- New Stacker Reclaimer
- Additional DM Stream
- New DDCMIS for Units 12 and Upgradation of DAS
for Unit 4 - Clarification of CW Make up water system
Effluent Treatment plant - RM cost - Rs 1.17 Crs/MW
- PLF is around 85 as against 21 at the time of
takeover in Jan 2000
27EXPERIENCE OF TECHNOLOGY UPGRADES
- The 60 MW boilers at Talcher TPS have been
redesigned taking into account the current coal
characteristics. Milling system have been
upgraded. -
- The 110 MW Units at Kothagudam have been upgraded
to 120 MW by PPIL with a Turbine HR less than
2000 Kcal/Kwh. -
- 110 MW Unit at AECO, Sabarmati has been upgraded
to 120 MW by NASL with Turbine HR improvement of
approximately 140 Kcal/Kwh. - No. of 200/210 MW LMZ Units have been upgraded to
225 MW in other countries with considerable
improvement in Heat rate. These are now being
planned in India.
28Governments Initiatives
Partnership in Excellence CEA has identified 26
stations which are operating at a PLF of less
than 40. These stations would have a
Partnership in Excellence with better
performing utilities, so as to achieve an
improvement in performance in the shortest
possible time. Subsidized funds would be made
available for this programme through PFC / REC.
The target is to achieve a PLF of 60 in two
years time. Role of NTPC NTPC has been entrusted
the responsibility of 14 stations out of the
identified 26. Site office has been opened at all
the 14 stations and experts have been posted at
all sites. The teams will aim to implement the
customized OM systems and will carry out one
cycle of overhauls.
29Governments Initiatives
- RM of SEB stations
- The 10th Plan envisaged RM of an installed
capacity of 11,055 MW with a target of achieving
75-80 PLF and 20 years of Life Extension. - Role of NTPC
- NTPC has taken up consultancy services for a few
of these stations. - NTPC initially took up four power stations for
RM/LE (Total 1332.5 MW). - Subsequently another six stations (1512.5 MW)
were taken up for RM / Life Extension (LE) /
Re-commissioning / Residual Life Assessment (RLA)
- Funds being provided by PFC / REC
30APDP-RM
Highlights of Achievement
Proj. PLF bef. PLF aft. imp. in PLF SOC bef. SOC aft. imp. in SOC APC bef. APC aft. imp. in APC
CTPS 3x140 MW 23.97 72.66 203.13 28.60 0.80 97.20 22.30 11.43 48.75
DTPS 1x140 MW 36.78 65.41 77.84 5.28 1.88 64.40 12.59 9.88 21.52
GTPS 2x210 MW 45.00 84.00 93.19 3.00 0.70 76.67 12.40 10.23 17.50
31International Best Practices in RM
- Internationally, RM program are focused on
leveraging technological developments in various
fields to upgrade candidate plants bring them
at par with contemporary machines - International best practices range from
one-to-one replacements to Mega RM - In USA and other advanced countries utilities
have largely gone for Mega RM because of the age
of their units rapid changes in their business
environment which required them to remain
competitive and efficient - Hence, Mega RM schemes such as up-gradation of
process parameters, improved balding in turbines,
Re-powering, even installing machines of higher
capacity on the same footprint were adopted
32Case Study of a German Power Plant
- Improvement of efficiency and environmental
conditions by retrofitting the units - This was mainly achieved due to using low NOx
burners in boiler, redesigning of LP turbine and
cooling tower modernisation - The emission levels of the units was reduced
drastically due to use of low NOx burners,
installing Flue Gas Desulfurification plant and
optimisation of operation of ESP - Flue gas discharge through cooling towers,
automatic concrete cutter for existing chimneys
33Conclusion
- Implementation of the RM Schemes has benefited
the stations by way of - Overcoming Technological obsolescence.
- Low cost capacity addition
- Extending the life of equipment / components.
- Complying with Statutory and Environmental Norms
- Sustaining availability and improved performance
- There is huge potential in India for RM
activities because of large number of old plants
which are inefficient and running below design
capacity - RM to be planned in advance before major
deterioration or breakdown of unit - Urgent need to enhance manufacturing capacity to
handle load of RM / Creation of new
manufacturing base
34(No Transcript)