Tunnelling Methods - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Tunnelling Methods

Description:

Drill and blast. Shields and tunnel boring machines (TBMs) New ... Excavation (or blasting) Supporting. Transportation of muck. Lining or coating/sealing ... – PowerPoint PPT presentation

Number of Views:3689
Avg rating:1.0/5.0
Slides: 16
Provided by: yasemin1
Category:

less

Transcript and Presenter's Notes

Title: Tunnelling Methods


1
Tunnelling Methods
2
  • The choice of tunnelling method may be dictated
    by
  • geological and hydrological conditions,
  • cross-section and length of continuous tunnel,
  • local experience and time/cost considerations
    (what is the value of time in the project),
  • limits of surface disturbance, and many others
    factors.

3
  • tunnel construction methods
  • Classical methods
  • Mechanical drilling/cutting
  • Cut-and-cover
  • Drill and blast
  • Shields and tunnel boring machines (TBMs)
  • New Austrian Tunnelling Method (NATM)
  • Immersed tunnels
  • Special methods (Tunnel jacking, etc.)

4
  • The process for bored tunnelling involves all or
    some of the following operations
  • Probe drilling (when needed)
  • Grouting (when needed)
  • Excavation (or blasting)
  • Supporting
  • Transportation of muck
  • Lining or coating/sealing
  • Draining
  • Ventilation

5
  • Classical Methods
  • Among the classical methods are the Belgian,
    English, German, Austrian, Italian and American
    systems. These methods had much in common with
    early mining methods and were used until last
    half of the 19th century.
  • Excavation was done by hand or simple drilling
    equipment.
  • Supports were predominantly timber, and
    transportation of muck was done on cars on narrow
    gauge tracks and powered by steam.
  • Progress was typically in multiple stages i.e.
    progress in one drift, then support, then drift
    in another drift, and so on.
  • The lining would be of brickwork.
  • These craft-based methods are no longer
    applicable, although some of their principles
    have been used in combination up to present day.
    Nevertheless some of the worlds great tunnels
    were built with these methods.

6
  • The English method (crown-bar method, figure
    left) started from a central top heading which
    allowed two timber crown bars to be hoisted into
    place, the rear ends supported on a completed
    length of lining, the forward ends propped within
    the central heading. Development of the heading
    then allowed additional bars to be erected around
    the perimeter of the face with boards between
    each pair to exclude the ground. The system is
    economical in timber, permits construction of the
    arch of the tunnel in full-face excavation, and
    is tolerant of a wide variety of ground
    conditions, but depends on relatively low ground
    pressures.

7
  • The Austrian (cross-bar) method required a
    strongly constructed central bottom heading upon
    which a crown heading was constructed. The
    timbering for full-face excavation was then
    heavily braced against the central headings, with
    longitudinal poling boards built on timber bars
    carried on each frame of timbering. As the lining
    advanced, so was the timbering propped against
    each length to maintain stability. The method was
    capable of withstanding high ground pressures but
    had high demand for timber.

8
  • The German method (core-leaving method) provided
    a series of box headings within which the
    successive sections of the side walls of the
    tunnel were built from the footing upwards, thus
    a forerunner of the system of multiple drifts.
    The method depends on the central dumpling being
    able to resists without excessive movement
    pressure transmitted from the side walls, in
    providing support to the top 'key' heading prior
    to completion of the arch and to ensuring
    stability while the invert arch is extended in
    sections.
  • The Belgian system (underpinning or flying arch
    method) started from the construction of a top
    heading, propped approximately to the level of
    the springing of the arch for a horseshoe tunnel.
    This heading was then extended to each side to
    permit construction of the upper part of the
    arch, which was extended by under- pinning,
    working from side headings. The system was only
    practicable where rock loads were not heavy.
  • The first sizeable tunnel in soft ground was the
    Tronquoy tunnel on the St Quentin canal in France
    in 1803, where the method of construction, based
    on the use of successive headings to construct
    sections of the arch starting from the footing,
    was a forerunner to the German system described
    above.

9
The Rove Tunnel near Marseille measured 22 x
15,40 m, and was excavated with multiple drifts.
10
Classical multiple face excavation
11
Mechanical Drilling and Cutting-Crushing Strength
of rock
12
Roadheaders
13
Cut and Cover Method
14
  • The principal problem to be solved in connection
    with this construction method is to how to
    maintain surface traffic, with the least
    disturbance during the construction period. One
    method is to restrict traffic to a reduced street
    width, another to direct traffic to a bypassing
    street.
  • Another way of supporting the sidewalls of open
    trenches is to substitute sheet-pile walls by
    concrete curtain walls cast under bentonite
    slurry (ICOS method), and using steel struts.
    This is especially a requisite in narrower
    streets trimmed with old sensitive buildings with
    their foundation plane well above the bottom
    level of the pit. This type of trench wall
    becomes a requirement for maintenance of surface
    traffic due to the anticipation of vibration
    effects potentially harmful to the stability of
    buildings with foundations lying on cohesionless
    soils.

15
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com