Title: VCCS SIS V8 Upgrade Project Technology Council Presentation
1VCCS SIS V8 Upgrade ProjectTechnology Council
PresentationOctober 7, 2004
2VCCS SIS V8 Upgrade Project - Working with
PeopleSoft
- PeopleSoft eBusiness Architecture Assessment
- On-site review and assessment completed August 16
26 for Version 7.6 and Version 8 - Recommendations incorporated into Technology
Architecture plan - PeopleSoft Upgrade Lab assessment and upgrade
preparation - Completed August 23 September 24
- Reports and analysis reviewed by ITS staff
- Clean-up steps taken
- PeopleSoft Project planning
- Completed September 20 24
- Upgrade project plan based on PeopleSoft COMPASS
methodology published on September 30 - Project charter being revised based on planning
workshop - PeopleSoft certified Version 8 Demo install
- Completed September 27 - 30
- Hands-on training and knowledge transfer to ITS
staff - PeopleSoft Upgrade Lab on-site install
3PeopleSoft Upgrade Lab review of VCCS 7.6
Production Database August / September 2004
4PeopleSoft Upgrade Lab review of VCCS 7.6
Production DatabaseAugust / September 2004
5PeopleSoft Upgrade Lab review of VCCS 7.6
Production DatabaseAugust / September 2004
- Almost all modifications to objects are well
documented. Most are minor in nature. Also good
naming conventions were used for custom added
objects. They begin with the identifier 'VCCS' or
'VC'. Many of the customizations and custom added
objects are for the EPOS project. - The changes to records and record fields are
minor in nature. These modifications can be
carried forward. For many of the records, only
the long description has been changed. There are
some modifications to records that have not been
documented. - Most of the modifications are well commented. A
few undocumented changes could be the result of
applying fixes. Reapplying customizations will be
the most challenging part of the upgrade, as
PeopleCode has changed significantly in
PeopleSoft 8.0. It may be difficult to determine
how to reapply your modifications. - Most of the modifications are documented and
consist mostly of additional fields. Three
modified panels are not documented. You may find
though, that your current modifications, if
carried forward, will have to be made to new
panels and / or sub-panels. Modifications to PS
panels will be examined and reapplied where
possible. - Minor modifications were made to the PeopleSoft
panel groups and all but two are documented. All
of these modifications can be carried forward
where possible. Again, these objects have
changed extensively and changes may have to be
made to the new panel groups. - Very minor field changes were made and are
documented. Most of the modifications consisted
of changes in description changes for translate
modifications. All field changes can be carried
forward. - Most of the changes to the PeopleSoft delivered
translate values exist because of inactive
setting changes. These changes will be carried
forward. - No indexes were modified. One index was added to
PSOPRDEFN for the field EMPLID. None of the
modifications to 5 menus are documented. They
could be the result of applying fixes. There is
a custom tablespace VCINDEX but only one record
uses it - VC_ADJCNT_RCTL. - Â
6VCCS SIS V8 Upgrade Project PeopleSoft Compass
Methodology
- Phases Strategy, Planning, Structure,
Construct, Transition, - Deploy
- Activities major sections of a Phase,
consisting of Steps that - conclude in a project
deliverable or milestone - Steps similar tasks that are part of
an Activity - Application specific information includes table
setup sequences, - application features,
integration detail, and - application-specific
tasks
Scalable
7VCCS SIS V8 Upgrade Project PeopleSoft Compass
Methodology
- Strategy Phase
- Usually pre-sales
- Planning Phase
- Includes the Upgrade Planning Technology
Assessment Packaged Services - Structure Phase
- Includes detailed implementation planning,
specifically defining requirements and developing
a project charter, fit/gap analysis, and
functional specs
- Construct Phase
- Includes designing, building, and initial testing
of the PeopleSoft system - Transition Phase
- Includes System Test, other testing activities,
and getting ready for Production (Production
Readiness) - Deploy Phase
- Includes go-live and production support
8VCCS SIS V8 Upgrade Project Plan - Summary
- VCCS SIS Version 8 Upgrade Project (Peoplesoft
Compass Methodology) Sun 8/15/04 Wed 3/23/05 - Structure Phase Sun 8/15/04 Fri 10/29/04
- Planning and Project Charter Sun 8/15/04 Fri
10/29/04 - Delta Fit/Gap Functional Requirements and
Specifications Sun 8/15/04 Fri 10/22/04 - Close Structure Phase Fri 10/22/04 Fri
10/22/04 - Construct Phase Sun 8/15/04 Tue 12/21/04
- Design Sun 8/15/04 Wed 11/3/04
- Build and Test Sun 8/15/04 Tue 12/21/04
- Close Construct Phase Tue 12/21/04 Tue
12/21/04 - Transition Phase Sun 8/15/04 Mon 2/14/05
- Build Comprehensive Technical Architecture for
Production Tue 11/16/04 Tue 12/14/04 - Perform Test Move to Production 2 Mon
12/13/04 Fri 1/7/05 - System Test Sun 8/15/04 Fri 1/7/05
- Perform Test Move to Production 3 Fri
1/14/05 Thu 1/27/05 - Production Readiness Sun 8/15/04 Mon 2/14/05
- Close Transition Phase Mon 2/14/05 Mon
2/14/05 - Deploy Phase Sun 8/15/04 Wed 3/23/05
- Perform Test Move to Production 4 Fri
1/28/05 Thu 2/10/05 - Deploy Sun 8/15/04 Fri 2/18/05
9VCCS SIS V8 Upgrade Project Plan Moves to
Production
- First Test Move to Production
- October 6th through November 5th
- 23 days 8 hours 184 hours
- Go-Live / Move to Production
- February 15th _at_ 600pm through February 21st _at_
600am - 5.5 days 24 hours 132 hours
Copy of Production Version 7.6 target for Test
Move to Production created October 5th
10VCCS SIS V8 Upgrade Project Test Plans
- Rik Gillette named as Test Coordinator
- Request sent for colleges to submit a set of
scenarios to be used as a template for
functionality testing of Version 8 - As of October 5th responses received from
- NVCC
- PDCCC
- RCC
- TCC
- VWCC
- Queries used during Version 7.6 conversion for
data validation have been identified
11VCCS SIS V8 Upgrade Project Training Plans
- Jeff Mitchell named as Training Coordinator
- Objectives
- Just-In-Time Training Provides best retention
corresponds with reinforcing usage - College Application Expertise Development of
functional and technical knowledge - VCCS ITS Expertise Product implementation and
support knowledge - End-User Expertise Self-sufficient end-user
product use and knowledge - Business Process Documentation Enable future
analysis and streamlining - Scope of Training Planned
- College Project Team Members (Functional
Technical) - College Super-Users (Functional Technical) and
Functional Leads - College End-Users (Faculty, Staff, Student)
- VCCS ITS Staff (Functional Technical)
- Training will be geared to provide
- PeopleSoft instruction on changes in the Version
8 SA products - Hands-on seminars on the new VCCS SIS
- End-user documentation and automated training
materials development - Alternative training options to meet specific
college needs - Training Planning Next Steps
- Complete Provide V8 PeopleSoft Delta Training CD
Courses
12VCCS SIS V8 Upgrade Project Security Update
- All existing security related data (logon ids,
passwords, security classes, and the model
operator identifiers) will be automatically
recreated under PeopleTools version 8. - College Roles and Responsibilities during
Migration - Review the security classes and model operator
ids. - Request deletion of model operator ids not
currently active or assigned to an active user. - Request deletion of all unnecessary security
classes. - VCCS Information Security Officer
- Create all roles used.
- Distribute a list of roles and permission lists
assigned to each role. - Make the necessary changes to security classes
and model operator ids in PS 7.6 - College Information Security Officer or person(s)
fulfilling that role - Review the roles to make sure they are the
equivalent of the existing model operator ids. - Submit any changes to permission list or model
operator ids - Test every model operator id
- Other Version 8 Tasks
- An audio conference will be scheduled in late
October to review the security plan and migration
strategy.
13VCCS SIS V8 Upgrade Project Query Update
- Misty Coles is coordinating the Query review
project. - Over 4,000 college queries currently exist.
- Many are no longer used or are duplicates of
other queries. - Use different strategies and table sources to
report data - inconsistent results - The majority of the queries will not function
without significant changes. - Opportunity to rebuild and streamline our use of
queries - Opportunity to convert existing queries into
Version 8 is consistent with PeopleSoft best
practices - Develop a pool of common queries for use in
PeopleSoft Version 8 - Create and maintain a searchable query catalog so
users may easily locate a query to meet their
needs. - A project website was developed and released
through VCCS Discuss - track the project progress,
- see the outcome of the review for each query
described, - See the selection of a model query as a guide
for development in version 8, - take a sneak peak of how the query catalog might
work.
14VCCS SIS V8 Upgrade Project IVR Update
- The TEST IVR box has the VCCS modifications
installed by EPOS - Darrell Scruggs currently testing many options
within the IVR - read from and update the V8 database using the
Pin change option - broadcast message option is working.
- list students class schedules initial testing is
complete - College logons have been created and given to the
colleges to test connection and to start looking
into the setup issues in preparation for them to
be able to start testing on the IVR system
themselves. - IVR documentation from EPOS as well as a helpful
hints document created for the colleges has been
placed on a shared drive for their access.. - Completed the creation of 180 translate tables
files on the TEST IVR system that EPOS was not
able bring forward from the old IVR Production
system.
15VCCS SIS V8 Upgrade Project More Information
- http//helpnet.utility.vccs.edu/ASC/Psoft/PSoft8/P
soft8menu.htm - . The VCCS initial version will be SAS V8 SP1
and PeopleTools 8.2x. All released updates and
fixes for SP1 will be applied. - Client Services Version 8 Communications
- http//peoplesoft8vanilla.vccs.edu
- PeopleSoft SIS Version8 Demonstration Database
- Version 8 Student Administration Upgrade Project
Plan Task List - HTML version MS Project version
- Version 8 Student Administration Upgrade Project
High Level Task List - SIS Version 8 upgrade Project Planning Guide
- SIS Security Overview
- PeopleBooks8
- Customizations to Migrate to PeopleTools 8.0
- Customization Left Behind in 7.6.3
- Message of the week
- We are pleased to announce a major milestone for
the Student Administration (SA) Version 8
Upgrade Project.  During the week of September
27th, 2004, the "Student Administration
PeopleSoft 8 System Certified Installation was
completed. This is the first step toward
creating your test database! Continue to watch
this web site for weekly updates to SA Project
16VCCS SIS V8 Upgrade Project - Discussion