HALDANE CENTRAL SCHOOL DISTRICT CAPITAL PROJECTS REFERENDUM - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

HALDANE CENTRAL SCHOOL DISTRICT CAPITAL PROJECTS REFERENDUM

Description:

... Boy's and Girl's Locker Rooms. Steering Committee Recommendations ... Replace Locker Room air handling units and exhaust fans. Add Choral Room ventilation ... – PowerPoint PPT presentation

Number of Views:66
Avg rating:3.0/5.0
Slides: 23
Provided by: jospehf
Category:

less

Transcript and Presenter's Notes

Title: HALDANE CENTRAL SCHOOL DISTRICT CAPITAL PROJECTS REFERENDUM


1
(No Transcript)
2
HALDANE CENTRAL SCHOOL DISTRICTCAPITAL PROJECTS
REFERENDUM
3
Steering Committee Guidelines
4
Areas of Focus
Roof Systems Flashings Exterior Masonry
Heating Plant Air Handling Units Piping and
Controls
Site Interior Renovations
5
Roofing and Masonry
1964 Wing
1934 Wing
Elementary Wing
6
Roofing and Masonry
1934 Wing
Hypalon Membrane Deteriorated Coping
Stones Defunct Ventilation Equipment Undersized
drains Open parapet masonry joints Open water
course joints
7
Roofing and Masonry
1964 Wing
PVC Membrane Poor Drainage Poorly Flashed
Ventilation Equipment Deteriorated Coping
Joints Poor Flashing Details Extensive Patched
areas Limited Masonry Repairs
8
Roofing and Masonry
Elementary Wing
EPDM Membrane Deteriorated Coping Joints Open
Masonry Joints
Miscellaneous
Stage Roof Copings and Drain Sump Old Gym Bus
Garage/ Administration Roof
9
Mechanical Systems
Heating Plant
Steam Boilers Heat Exchanger to Hot Water System
in 1964 Wing Steam Baseboard Elementary Wing
10
Mechanical Systems
Air Handling Units
Cafeteria / Locker Rooms Gym Old Gym /
Auditorium Elementary Wing Classroom Unit
Ventilators 1934 Wing Toilet Exhaust
11
5 Year Capital Plan
Site
Paving Repairs Fencing Bleacher
Replacement Oil Tank Removal
Interior Renovations
Locker Room Training Room / Storage Cafeteria
Flooring
12
Plumbing and Electrical Systems
Plumbing
Backflow Prevention Gas Piping Sanitary System
Electrical
Convenience Outlets Computer Power Fire
Alarm Security System
13
Steering Committee Recommendations
Priority 1
Remove buried fuel oil tanks, Bus Garage and
Merrit Building Site drainage repairs Repoint
and seal parapet masonry and watercourse cast
stone Roof Replacement Main Roof (1934
Wing) Cafeteria / Gym (1964 Wing) Bus Garage /
Administration Stage Roof Elementary Wing
Copings Repair Chimney Bus Garage
Fascia Replace Cafeteria Floor
14
Steering Committee Recommendations
Priority 1
Provide backflow preventer on domestic water
service line and boiler feed line Add sealed
sump pump in boiler room Remove unused gas line
to former science lab Emergency gas shut-off in
kitchen Add grease trap to kitchen pot
sink Replace 3 existing electrical panels in
1934 Wing Upgrade fire alarm to current code and
ADA standards Upgrade existing security system
15
Steering Committee Recommendations
Priority 2
Replace areas of deteriorated paving Merrit
Building Parking Cedar Street Entrance Renovate
existing Boys and Girls Locker Rooms
16
Steering Committee Recommendations
Priority 3
Repave areas of deteriorated paving Lower
Parking Area Craigside Drive parking and
roadway Rehabilitate tennis courts Replace home
and visitors bleachers Install new chain link
fencing Drainage retention basin Playground Ret
aining wall behind Merrit Building Replace
handicapped entrance ramp Administration
Building Renovate Weight Room, Team Room and
Storage Emergency communications to existing
elevators
17
Steering Committee Recommendations
Priority 3
Install occupancy sensors in Storage Rooms,
Closets and Toilets Add additional power panels
and convenience outlets to each classroom Add
dedicated computer wiring panels, devices and
wiring to all classrooms Provide additional
computer and power wiring to offices Provide
additional surface raceway, outlets and wiring to
Computer Room Upgrade existing computer panels
to provide surge suppression and isolated
ground Provide exterior emergency lighting at
exits Install new wireless clock system
18
Steering Committee Recommendations
Mechanical Systems (Retain Steam)
Replace existing steam boilers and ancillary
equipment Upgrade unit ventilator controls and
actuators Provide roof mounted energy recovery
ventilation units and ductwork to all classrooms
in Elementary Wing Replace Old Gym/ Auditorium
air handling unit. Replace Cafeteria air handling
units and exhaust fans Replace Gymnasium air
handling units Replace Locker Room air handling
units and exhaust fans Add Choral Room
ventilation Add additional air conditioning
capacity to Library Add controls to radiators in
corridors and Old Gym (1934 Wing)
19
Steering Committee Recommendations
Mechanical Systems (Hot Water Conversion)
Replace existing steam boilers with new hot water
boilers Replace unit ventilators with roof
mounted energy recovery ventilation units and
ductwork to all classrooms, replace steam
radiators with new perimeter fin-tube radiation
in 1934 Wing Provide roof mounted energy recovery
ventilation units and ductwork to all classrooms
in Elementary Wing Replace Old Gym/ Auditorium
air handling unit. Replace Cafeteria air handling
units and exhaust fans Replace Gymnasium air
handling units Replace Locker Room air handling
units and exhaust fans Add Choral Room
ventilation Add additional air conditioning
capacity to Library
20
Steering Committee Recommendations
Hot Water Conversion Pros -Cons
Pro Removal of Unit Ventilators Energy
efficiency Classroom noise Classroom
space Reduced maintenance costs 1 system
throughout building Complete new system
Cons Increased Cost Expanded project scope and
complexity
21
Cost Summary
Priority 1-
2,247,364
Priority 2-
493,899
Priority 3-
1,309,413
Mechanical Systems Retain Steam
3,710,493
Mechanical Systems Hot Water Conversion
5,916,632
22
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com