LISA Mission System Engineering - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

LISA Mission System Engineering

Description:

Atlas family has more 'steps' due to strap-on options. Impact : Will stay on intermediate launch vehicle. ... Rationale : the strap down concept do not allow ... – PowerPoint PPT presentation

Number of Views:75
Avg rating:3.0/5.0
Slides: 32
Provided by: colleen98
Category:

less

Transcript and Presenter's Notes

Title: LISA Mission System Engineering


1
LISA Mission System Engineering
  • LIST Meeting
  • Roger Diehl
  • Tupper Hyde
  • Marcello Sallusti
  • December 10, 2005

2
Agenda
  • Error Budgets Technical Performance Measures
  • Trade Studies Status
  • Technical Baseline

3
MRD Requirements (Jan 05)
This allocation slightly misses Hard point at 5
mHz
4
Look at moving IMS low end up
This allocation also slightly misses Hard point
at 5 mHz
5
Astrium Performance Outlook
0.65 SRD 3.0 science requirements Makes hard
point at 5 mHz
6
IMS Error Budget Needs Work
7
CBEs for DRS
8
CBEs for IMS
9
Technical Performance Measures
10
Telemetry Budget
11
Trade Studies Completed
  • Strap Down
  • Old Baseline One proof mass to proof mass
    measurement
  • New Baseline Three measurements (proof mass to
    optical bench in first sciencecraft, optical
    bench to optical bench between two sciencecraft,
    optical bench to proof mass in second
    sciencecraft)
  • Rationale
  • Decouples inertial sensor and inter-spacecraft
    interferometry
  • Optimizes each functional assembly for its prime
    objective
  • Strong heritage from LTP
  • Impact Requires point-ahead-angle actuator on
    optical bench
  • Optical Readout
  • Old Baseline None
  • New Baseline Minimum design- 3 axis
    (x,theta-y,theta-z) from back side bench
    interferometer
  • Rationale Relax stiffness and crosstalk
    requirement, no extra hardware
  • Impact Minor increase in interface complexity

12
Trade Studies Completed
  • Photodiode Sampling
  • Old Baseline None
  • New Baseline 50 MHz
  • Rationale Provides require 2.5 times factor to
    20 MHz max expected doppler frequency.
  • Impact Implies orbit design requirement of 15
    m/s max arm length rate (with margin to 20 MHz).
    Implies frequency management scheme where doppler
    is only 1 times rate effect.
  • Arm Locking
  • Old Baseline None
  • New Baseline Direct arm locking without
    reducing requirements on laser, cavity,
    phasemeter, clocks or TDI.
  • Rationale Provides technology off-ramps (risk
    reduction) for reference cavity stability,
    clocks, and phasemeter dynamic range
  • Impact No new hardware needed. Detailed
    simulations are underway to define hardware
    requirements implied by armlocking (method of
    cavity tuning).

13
Trade Studies Completed
  • Science Data Rate
  • Old Baseline 1500 bps to TDI master though
    inter SC comm (TDI ver I on board)
  • New Baseline 400 bps per sciencecraft
    (allocation), TDI on ground
  • Rationale Interpolation allows resampling for
    TDI processing on ground.
  • Impact 400 bps includes margin on top of
    front, back and LO-LO phasemeters (each
    with two redundant quad output photodetectors).
  • Telemetry Rate
  • Old Baseline 0.45 kbps per SC continuous
  • New Baseline 5 kbps per SC continuous
  • Rationale Housekeeping reality and
    sciencekeeping first cut estimate, (first cut
    bottoms up telemetry estimate showed 4.1 kbps
    with margin)
  • Impact relook at comm hardware (see next trade)

14
Trade Studies Completed
  • End-to-End Data Architecture
  • Old Baseline 30 cm HGA, 5 W X-band SSPA, DSN 8
    hours/2days, inter S/C comm over laser link
  • New Baseline 30 cm HGA, 25W Ka TWTA (TBD), DSN
    8 hours/2days, inter S/C comm over laser link
    using spread spectrum on carrier
  • Rationale Meet telemetry allocation. Inter SC
    comm required to support ranging and clock tone
    transfer. No extra hardware.
  • Impact Software to support spread spectrum mod
    and demod.
  • Dynamics Parameters
  • Old Baseline Multiple sets of simulation
    parameters with no CM.
  • New Baseline Database of parameters agreed to
    by lead dynamicists at both Astrium and NASA.
  • Rationale All simulation should reference a
    common baseline.
  • Impact Parameter database kept under CM by MSE
    (Tupper).

15
Work In-Progress
  • Orbits
  • Old Baseline NASA and ESA trajectories based on
    different launch dates with different delta-Vs
  • Recommended New Baseline Select delta-V that
    envelopes all launch dates
  • Rationale Provide flexibility to launch any day
    of the year
  • Impact Operations orbits will either lead or
    trail Earth depending on launch date.
  • Getting-To-Orbit
  • Old Baseline Solar electric propulsion, Delta
    IV Med (4,2) (4045 kg capability)
  • Recommended New Baseline Chemical (Dual-Mode)
    propulsion, Atlas V 531 (5185 kg capability)
  • Rationale Chemical propulsion less risk due to
    less complexity and lower cost. Atlas family has
    more steps due to strap-on options.
  • Impact Will stay on intermediate launch
    vehicle. Further LV options to be considered
    after further mass and delta-V reduction studies.

16
Work In-Progress
  • PAA Actuator
  • Old Baseline No PAA
  • Rejected option rotating wedges (Risley
    prisms), periodic operation.
  • Recommended New Baseline 1 DOF actuator, TNO
    Design (Ti-6Al-4V integral structure with piezo
    actuation and front face centered cross blade
    flexure). Continuous operation.
  • Rationale the strap down concept do not allow
    to use the PM to steer the incoming laser beam on
    the science photodiode
  • Impact Addition of actuator, delta mass on
    optical bench of 75g, additional noise due to
    actuator in the measurement path
  • Pointing (TA) Mechanism
  • Old Baseline 2-stage linear actuator with pivot
    bearings (FTR)
  • Options 2 lever tiller with OTS linear
    actuators, rotary piezo stepper motors.
  • Recommended New Baseline TBD
  • Rationale TBD
  • Impact TBD

17
Work In-Progress
  • Wave Front Error Impact
  • Old Baseline far-field effect budgeted to 8
    nrad/rtHz, 30 nrad offset, periodic calibration
    (TBD), flat spot centering.
  • Rejected Options continuous dither, bright spot
    (not flat spot) centering, no on-ground
    correction.
  • Recommended New Baseline periodic calibration
    (2 weeks), flat spot centering, near field
    pointing (phase center moment arm) budgeted, near
    and far field effects cancelled on ground
  • Rationale flat spot centering results in only 2
    loss of power, pointing knowledge is 2-40 times
    better than pointing error
  • Impact send down quadrant info from front
    science phasemeters, two tone dithering during
    calibrations to pick out near and farfield
    effect, PAA pointing noise directly degrades
    pointing knowledge
  • Telescope
  • Old Baseline Dall-Kirkham 40 cm (up from 30 cm
    in FTR), optical assy articulation
  • Rejected options Off axis, Three mirror
    anistigmat, in-field pointing (/- 1.5 deg),
    telescope only pointing.
  • Recommended New Baseline Cassegrain 40 cm,
    optical assy articulation
  • Rationale Cassegrain is least complex but still
    allows for placement of pupils at PAA steering
    mirror and at quad science photodetector.
    Potential for larger FOV to support option of
    through telescope natural star tracking (TBD).
  • Impact Additional reflective or transmissive
    optics required between secondary and first
    beamsplitter

18
Trade Studies In-Progress
  • Redundancy Philosophy
  • Old Baseline No credible single point failure
    shall degrade the mission below the minimum
    mission performance.
  • Rejected Options A single failure cannot degrade
    the mission below the minimum mission success
    criteria (assuming two arm LISA is still a
    success).
  • Recommended New Baseline No credible single
    point failure shall degrade the mission below the
    full science requirements. LISA system must be
    one failure tolerant (fail safe).
  • Rationale Such a philosophy is appropriate for
    the scale of the LISA mission.
  • Impact Design has to implement full redundancy.
    Failures must be detected before extant
    capability is damaged. Waivers are required for
    credible single point failures which are
    prohibitively expensive to make redundant and
    whose failure would degrade but not end the
    mission.
  • The GRS may require such a waiver since there is
    no redundant GRS and its loss still allows two
    arm science operations).

19
Trade Study (Dec 05- Feb 06)
  • The 2 million km arm Study
  • ESA and NASA quick-look to find significant
    mass/complexity/risk/cost reductions
  • Goal to maintain full science performance
  • Evaluate cost payoff of slight relaxation at 5
    mHz requirement point
  • Reduce Arm Length to 2 million km
  • Cruise deltaV reduced from 1000 m/s to under
    700 m/s, 500 kg savings, opens monoprop option
    again
  • Use PM forcing on sensitive axis (1x10-9 m/s2)
    to buck out earth induced perturbation
  • Max doppler reduced from 15 to 1 MHz
  • Triangle breathing angle reduced from 1.5 deg to
    0.15 deg
  • Eliminate optical assy articulation
  • Removes large structural stage, large mechanism
    and launch locks
  • Replaced with in-field pointing (perhaps
    periodically)
  • Phasemeter bandwidth reduced from 50 Mhz to 3 Mhz
  • Laser power reduced from 1 W to just meet
    requirements (300 mW?)
  • Reduce electronics box count (combine functions)
  • Payload mass, power, and size savings
  • SC diameter reduction from 2.7m to 2.0 m
  • Average thruster force reduced from 9 to 5
    micronewtons
  • Bus mass savings due to size reduction and
    smaller payload

20
Short Arms (full science)
21
Short Arms (missing 2 points)
22
Future Trade Studies
  • Trade Studies due Feb 06
  • Spacecraft Mass Reduction
  • Acquisition
  • No Vacuum
  • Optical Bench Layout
  • Arm Locking Details
  • Trade Studies due April 06
  • Thermal Interfaces
  • Grounding/Power Distribution
  • Frequency Plan
  • Avionics Arch
  • Flight SW Arch
  • Magnetic Zones/PM mag reqs
  • Ranging/Clock
  • DRS Cal
  • Critical Alignments

23
Timeline for Chemical Transfer
24
Optimal Chemical Transfer
25
Structural Baseline
  • Sciencecraft mass estimate down to 550 kg
    (including 30 percent margin)
  • Analyzed several spacecraft/prop module
    configurations
  • Electric (SEP) and Chemical Prop Module Versions
  • Chem Prop Module looks promising with spaceframe
    construction
  • Outer cylinder of prop module is the main load up
    the launch path
  • Spacecraft not required to carry full launch
    stack
  • Spacecraft designed for 40cm telescope
  • Y-tube opening housed inside of tuna can,
    providing thermal protection from sunlight and
    contamination shielding during launch and cruise
    phase.
  • Develop spacecraft to prop module and PM to PM
    separation systems
  • Only six separation systems are required (3 PM to
    PM and 3 S/C to PM)
  • Eliminate release mechanisms on top deck

26
LISA Spacecraft Configuration
  • Volume and mass are design drivers!!
  • Coordinated electronics boxes in solid model with
    agreed to mass/power budget
  • Currently 35 electronic boxes are housed inside
    of the Sciencecraft
  • Redundancy philosophy needs to be worked (combine
    functions)
  • Placement of electronics boxes need to address
    self gravity, thermal, magnetics (adopt zone
    philosophy)
  • Consider requirements carefully!

VIEW Top of structure with Solar Array and Top
Panel removed
27
Top Hat/Redundant Thruster Clusters
  • Current design puts redundancy in cluster (there
    are only 3 clusters, not 6 as shown)

28
Welcome to crowded LISAapolis
29
Telescope to Bench Options
Astrium MAR (Oct 05) design
Astrium lightweight (Dec 05) design
NASA Large FOV (Nov 05) design
30
Laser Subsystem Configuration
  • Old Baseline
  • 2 2 laser subsystems (everything out to fiber
    to bench)
  • Switching to backup laser was by TBD fiber
    positioner mechanism
  • Under evaluation
  • 3 laser units modulators to provide redundancy
  • A single box serving the three laser heads and
    amplifiers
  • A single box serving the three modulators
    electronics
  • A single box for switching the lasers
    (switchyard)
  • A single box for the electronics needed for the
    cavity and power stabilization of each laser
  • Total mass of system unchanged at 29 kg

31
LIMAS Functions Overview
GRS
3 phase msrmts Laser freq. GRS tilt GRS
position Clock msrmnt Range msrmt Comm
message (all to ground)
Phase/range/clock/comm/GRS
In from distant Sc/C
Phase Measurement
InterSc/C comm demod signal
Laser phase lock signal (inc. armlocking)
S/C Bus
Frequency distribution
LIMAS Avionics
Inter-Sc/C Comm message Ground
commands Acquisition commands
Laser Freq. offset Clock tone Ranging
tone InterSc/C comm signal
laser
Out to distant Sc/C
Write a Comment
User Comments (0)
About PowerShow.com