Title: LISA Mission System Engineering
1LISA Mission System Engineering
- LIST Meeting
- Roger Diehl
- Tupper Hyde
- Marcello Sallusti
- December 10, 2005
2Agenda
- Error Budgets Technical Performance Measures
- Trade Studies Status
- Technical Baseline
3MRD Requirements (Jan 05)
This allocation slightly misses Hard point at 5
mHz
4Look at moving IMS low end up
This allocation also slightly misses Hard point
at 5 mHz
5Astrium Performance Outlook
0.65 SRD 3.0 science requirements Makes hard
point at 5 mHz
6IMS Error Budget Needs Work
7CBEs for DRS
8CBEs for IMS
9Technical Performance Measures
10Telemetry Budget
11Trade Studies Completed
- Strap Down
- Old Baseline One proof mass to proof mass
measurement - New Baseline Three measurements (proof mass to
optical bench in first sciencecraft, optical
bench to optical bench between two sciencecraft,
optical bench to proof mass in second
sciencecraft) - Rationale
- Decouples inertial sensor and inter-spacecraft
interferometry - Optimizes each functional assembly for its prime
objective - Strong heritage from LTP
- Impact Requires point-ahead-angle actuator on
optical bench - Optical Readout
- Old Baseline None
- New Baseline Minimum design- 3 axis
(x,theta-y,theta-z) from back side bench
interferometer - Rationale Relax stiffness and crosstalk
requirement, no extra hardware - Impact Minor increase in interface complexity
12Trade Studies Completed
- Photodiode Sampling
- Old Baseline None
- New Baseline 50 MHz
- Rationale Provides require 2.5 times factor to
20 MHz max expected doppler frequency. - Impact Implies orbit design requirement of 15
m/s max arm length rate (with margin to 20 MHz).
Implies frequency management scheme where doppler
is only 1 times rate effect. - Arm Locking
- Old Baseline None
- New Baseline Direct arm locking without
reducing requirements on laser, cavity,
phasemeter, clocks or TDI. - Rationale Provides technology off-ramps (risk
reduction) for reference cavity stability,
clocks, and phasemeter dynamic range - Impact No new hardware needed. Detailed
simulations are underway to define hardware
requirements implied by armlocking (method of
cavity tuning).
13Trade Studies Completed
- Science Data Rate
- Old Baseline 1500 bps to TDI master though
inter SC comm (TDI ver I on board) - New Baseline 400 bps per sciencecraft
(allocation), TDI on ground - Rationale Interpolation allows resampling for
TDI processing on ground. - Impact 400 bps includes margin on top of
front, back and LO-LO phasemeters (each
with two redundant quad output photodetectors). - Telemetry Rate
- Old Baseline 0.45 kbps per SC continuous
- New Baseline 5 kbps per SC continuous
- Rationale Housekeeping reality and
sciencekeeping first cut estimate, (first cut
bottoms up telemetry estimate showed 4.1 kbps
with margin) - Impact relook at comm hardware (see next trade)
14Trade Studies Completed
- End-to-End Data Architecture
- Old Baseline 30 cm HGA, 5 W X-band SSPA, DSN 8
hours/2days, inter S/C comm over laser link - New Baseline 30 cm HGA, 25W Ka TWTA (TBD), DSN
8 hours/2days, inter S/C comm over laser link
using spread spectrum on carrier - Rationale Meet telemetry allocation. Inter SC
comm required to support ranging and clock tone
transfer. No extra hardware. - Impact Software to support spread spectrum mod
and demod. - Dynamics Parameters
- Old Baseline Multiple sets of simulation
parameters with no CM. - New Baseline Database of parameters agreed to
by lead dynamicists at both Astrium and NASA. - Rationale All simulation should reference a
common baseline. - Impact Parameter database kept under CM by MSE
(Tupper).
15Work In-Progress
- Orbits
- Old Baseline NASA and ESA trajectories based on
different launch dates with different delta-Vs - Recommended New Baseline Select delta-V that
envelopes all launch dates - Rationale Provide flexibility to launch any day
of the year - Impact Operations orbits will either lead or
trail Earth depending on launch date. - Getting-To-Orbit
- Old Baseline Solar electric propulsion, Delta
IV Med (4,2) (4045 kg capability) - Recommended New Baseline Chemical (Dual-Mode)
propulsion, Atlas V 531 (5185 kg capability) - Rationale Chemical propulsion less risk due to
less complexity and lower cost. Atlas family has
more steps due to strap-on options. - Impact Will stay on intermediate launch
vehicle. Further LV options to be considered
after further mass and delta-V reduction studies.
16Work In-Progress
- PAA Actuator
- Old Baseline No PAA
- Rejected option rotating wedges (Risley
prisms), periodic operation. - Recommended New Baseline 1 DOF actuator, TNO
Design (Ti-6Al-4V integral structure with piezo
actuation and front face centered cross blade
flexure). Continuous operation. - Rationale the strap down concept do not allow
to use the PM to steer the incoming laser beam on
the science photodiode - Impact Addition of actuator, delta mass on
optical bench of 75g, additional noise due to
actuator in the measurement path - Pointing (TA) Mechanism
- Old Baseline 2-stage linear actuator with pivot
bearings (FTR) - Options 2 lever tiller with OTS linear
actuators, rotary piezo stepper motors. - Recommended New Baseline TBD
- Rationale TBD
- Impact TBD
17Work In-Progress
- Wave Front Error Impact
- Old Baseline far-field effect budgeted to 8
nrad/rtHz, 30 nrad offset, periodic calibration
(TBD), flat spot centering. - Rejected Options continuous dither, bright spot
(not flat spot) centering, no on-ground
correction. - Recommended New Baseline periodic calibration
(2 weeks), flat spot centering, near field
pointing (phase center moment arm) budgeted, near
and far field effects cancelled on ground - Rationale flat spot centering results in only 2
loss of power, pointing knowledge is 2-40 times
better than pointing error - Impact send down quadrant info from front
science phasemeters, two tone dithering during
calibrations to pick out near and farfield
effect, PAA pointing noise directly degrades
pointing knowledge - Telescope
- Old Baseline Dall-Kirkham 40 cm (up from 30 cm
in FTR), optical assy articulation - Rejected options Off axis, Three mirror
anistigmat, in-field pointing (/- 1.5 deg),
telescope only pointing. - Recommended New Baseline Cassegrain 40 cm,
optical assy articulation - Rationale Cassegrain is least complex but still
allows for placement of pupils at PAA steering
mirror and at quad science photodetector.
Potential for larger FOV to support option of
through telescope natural star tracking (TBD). - Impact Additional reflective or transmissive
optics required between secondary and first
beamsplitter
18Trade Studies In-Progress
- Redundancy Philosophy
- Old Baseline No credible single point failure
shall degrade the mission below the minimum
mission performance. - Rejected Options A single failure cannot degrade
the mission below the minimum mission success
criteria (assuming two arm LISA is still a
success). - Recommended New Baseline No credible single
point failure shall degrade the mission below the
full science requirements. LISA system must be
one failure tolerant (fail safe). - Rationale Such a philosophy is appropriate for
the scale of the LISA mission. - Impact Design has to implement full redundancy.
Failures must be detected before extant
capability is damaged. Waivers are required for
credible single point failures which are
prohibitively expensive to make redundant and
whose failure would degrade but not end the
mission. - The GRS may require such a waiver since there is
no redundant GRS and its loss still allows two
arm science operations).
19Trade Study (Dec 05- Feb 06)
- The 2 million km arm Study
- ESA and NASA quick-look to find significant
mass/complexity/risk/cost reductions - Goal to maintain full science performance
- Evaluate cost payoff of slight relaxation at 5
mHz requirement point - Reduce Arm Length to 2 million km
- Cruise deltaV reduced from 1000 m/s to under
700 m/s, 500 kg savings, opens monoprop option
again - Use PM forcing on sensitive axis (1x10-9 m/s2)
to buck out earth induced perturbation - Max doppler reduced from 15 to 1 MHz
- Triangle breathing angle reduced from 1.5 deg to
0.15 deg - Eliminate optical assy articulation
- Removes large structural stage, large mechanism
and launch locks - Replaced with in-field pointing (perhaps
periodically) - Phasemeter bandwidth reduced from 50 Mhz to 3 Mhz
- Laser power reduced from 1 W to just meet
requirements (300 mW?) - Reduce electronics box count (combine functions)
- Payload mass, power, and size savings
- SC diameter reduction from 2.7m to 2.0 m
- Average thruster force reduced from 9 to 5
micronewtons - Bus mass savings due to size reduction and
smaller payload
20Short Arms (full science)
21Short Arms (missing 2 points)
22Future Trade Studies
- Trade Studies due Feb 06
- Spacecraft Mass Reduction
- Acquisition
- No Vacuum
- Optical Bench Layout
- Arm Locking Details
- Trade Studies due April 06
- Thermal Interfaces
- Grounding/Power Distribution
- Frequency Plan
- Avionics Arch
- Flight SW Arch
- Magnetic Zones/PM mag reqs
- Ranging/Clock
- DRS Cal
- Critical Alignments
23Timeline for Chemical Transfer
24Optimal Chemical Transfer
25Structural Baseline
- Sciencecraft mass estimate down to 550 kg
(including 30 percent margin) - Analyzed several spacecraft/prop module
configurations - Electric (SEP) and Chemical Prop Module Versions
- Chem Prop Module looks promising with spaceframe
construction - Outer cylinder of prop module is the main load up
the launch path - Spacecraft not required to carry full launch
stack - Spacecraft designed for 40cm telescope
- Y-tube opening housed inside of tuna can,
providing thermal protection from sunlight and
contamination shielding during launch and cruise
phase. - Develop spacecraft to prop module and PM to PM
separation systems - Only six separation systems are required (3 PM to
PM and 3 S/C to PM) - Eliminate release mechanisms on top deck
26LISA Spacecraft Configuration
- Volume and mass are design drivers!!
- Coordinated electronics boxes in solid model with
agreed to mass/power budget - Currently 35 electronic boxes are housed inside
of the Sciencecraft - Redundancy philosophy needs to be worked (combine
functions) - Placement of electronics boxes need to address
self gravity, thermal, magnetics (adopt zone
philosophy) - Consider requirements carefully!
VIEW Top of structure with Solar Array and Top
Panel removed
27Top Hat/Redundant Thruster Clusters
- Current design puts redundancy in cluster (there
are only 3 clusters, not 6 as shown)
28Welcome to crowded LISAapolis
29Telescope to Bench Options
Astrium MAR (Oct 05) design
Astrium lightweight (Dec 05) design
NASA Large FOV (Nov 05) design
30Laser Subsystem Configuration
- Old Baseline
- 2 2 laser subsystems (everything out to fiber
to bench) - Switching to backup laser was by TBD fiber
positioner mechanism - Under evaluation
- 3 laser units modulators to provide redundancy
- A single box serving the three laser heads and
amplifiers - A single box serving the three modulators
electronics - A single box for switching the lasers
(switchyard) - A single box for the electronics needed for the
cavity and power stabilization of each laser - Total mass of system unchanged at 29 kg
31LIMAS Functions Overview
GRS
3 phase msrmts Laser freq. GRS tilt GRS
position Clock msrmnt Range msrmt Comm
message (all to ground)
Phase/range/clock/comm/GRS
In from distant Sc/C
Phase Measurement
InterSc/C comm demod signal
Laser phase lock signal (inc. armlocking)
S/C Bus
Frequency distribution
LIMAS Avionics
Inter-Sc/C Comm message Ground
commands Acquisition commands
Laser Freq. offset Clock tone Ranging
tone InterSc/C comm signal
laser
Out to distant Sc/C