Title: LISA Mission System Engineering Status
1LISA Mission System Engineering Status
- Marcello Sallusti (ESA)
- Colleen McGraw (GSFC)
- Jordan Evans (JPL)
2Agenda
- Technical Organization
- Current Baseline Mission Architecture Parameters
- Latest Results for Sciencecraft Orbits
- Results and Baseline for Initial Acquisition
- Measurement Scheme and Performance
- Telescope Trade-Off and Far-Field Analysis (LOCS
Status)
- DFACS During Science Mode
- LIMAS Status
- Spacecraft Configuration
- Technical Resource Budgets
- Near-Term Trade Studies and Activities
3Technical Organization
- The three Mission Systems Engineering Managers
(MSEMs) have the joint responsibility of leading
and coordinating the overall engineering efforts
across the LISA Project - This involves Systems Engineers and Discipline
Engineers from Astrium (ESAs Mission Formulation
contractor) and NASA organizations (technical
organizations and contractors) - To date, the work has been a combination of
- Parallel work presented between the two agencies
to converge on a baseline (e.g. baseline orbit
definitions, end-to-end data architecture)
- Joint work developed via a consensus approach
(e.g. the IMS architecture via the IMS ITAT)
- Technical Interchange Meetings (TIMs) for focused
topics and Quarterly Meetings for general status
are currently the primary vehicles for
interchange
4Baseline Mission Parameters (1/3)
- Following charts reflect a list of parameters
being referred to as the Baseline Fact Sheet
- It is intended to be used to help track the
current baseline for LISA
- It does not fully characterize a baseline
architecture as it does not include items like
block diagrams
- It provides a common source for some of the
information needed to be shared across the team
for consistency
- The current version is a work in progress
- Does not yet represent the baseline as it is
still in review
- Many holes are identified by the Fact Sheet and
represent areas of future work in defining the
LISA baseline
5Baseline Mission Parameters (2/3)
6Baseline Mission Parameters (3/3)
7Orbit Design Process
- NASA and ESA have independently optimized
candidate operations orbits
- Different optimization processes were used
- ESA uses two phases and a simplified model (only
Earth and that only an approximation)
- NASA included Earth and the other planets with
standard ephemeredes
- Different independent variables were used
- NASA used position and velocity
- ESA used certain classical elements (eccentricity
and argument of periaps) and then position and
velocity
- Different cost functions were used
- NASA used average distance from Earth
- ESA used average of range rates between
spacecraft
- Different constraints were assumed in the design
- NASA included an arm length requirement of 5 GM
1, which is tighter than the separate
requirement that the difference between any two
arm lengths be less than 1 of their sum - NASA included an allowance for delivery error (by
linearly reducing the arm length variance allowed
from 1 at the beginning of the mission to 0.8
at the end of the nominal mission - Although the 5 Gm requirement is in the latest
Mission Requirements Document draft, it should
probably be a requirement only on the initial
state - Final results were qualitatively the same and
quantitatively similar
8Orbit Elements Compared
NASA Baseline 2 Orbits
From Steven Hughes, Memorandum of 2005-05-02.
ESA / Astrium Orbits
9Orbit Characteristics Compared
ESA / Astrium Orbits
NASA Baseline 2 Orbits
8.5 years 3100 days
From Steven Hughes, Memorandum of 2005-05-02.
10LISA - Earth Range
NASA Baseline 2 Orbits
ESA / Astrium Orbits
20 deg 52 Gm 25 deg 65 Gm
8.5 years 3100 days
These results are documented in
LISA-ASU-TN-2001.doc (on PMIS)
LISANewConstraints.pdf (S. Hughes Memo, 5/2/05)
11Acquisition Basics
- Constellation acquisition
- Defined as the process of bringing the three LISA
spacecraft from zero to all six links phased
locked and optimized (ready for science)
- Re-acquisition is a simpler (and faster) process
with much smaller alignment and bias
uncertainties
- Acquisition Process
- Spacecraft star tracker to telescope alignment
calibrated with natural stars
- Command sequences and ephemeri uplinked to all
three spacecraft
- Spacecraft attitude (by star tracker) and point
ahead prescribed
- For each link.autonomous process, but monitored
by ground
- Pointing acquisition (three strategies defocus,
scan, super-CCD)
- Phase acquisition (scan frequency and lock to
incoming)
- Tune up constellation
- Verify inter-SC clock, comm. and ranging
- Phase Gain tuning for laser and offset/arm-lock
loops
- Pointing Brightness and flat-spot search and
optimization
- Engineering Mode checkout, calibrations, and
trial data runs
12The Three Strategies
- Defocus
- Spoil beam to cover uncertainty cone
- 2 mrad beam spoiled 7.5 x (to 15 mrad), 56x
weaker 2 pW
- Receiver fixed stares until integration time
(SNR) good enough
- This sets time required for gyro-mode
stability
- Scan
- Scan over uncertainty cone (continuous or
step/stare)
- Receiver fixed stares until integration time
(SNR) good enough
- This sets scan rate and time required for
gyro-mode stability
- Thru-telescope Star Tracker
- Natural star fixes with visible CCD through LISA
telescopes
- (mv) of 16, for 1 sec integration
- Issue of imaging quality FOV with telescope
prescription
13Issues
- Defocus
- Signal to noise ratio and fiber positioner
mechanism complexity are driving issues
- Can be mitigated by both ends defocus and
co-re-focusing in steps
- Scan
- Pointing stability over scan time is driving
issue
- Can be mitigated with gyro-mode operation of
GRSs
- Scan can always be done, even if another strategy
is chosen as prime
- Thru-telescope star tracker
- FOV of telescope is driving issue
- Requires good alignment knowledge on bench or
searching
- Eliminates requirement to have high performance
SC star trackers
14Acquisition Summary
- An observatory laser acquisition strategy and
control has been developed
- Defocus and scan strategies
- Defocus should be considered the baseline with
the scan strategy as backup
- Requires an order to the sequence
- Uses a Gyro mode for enhanced pointing stability
with the drag-free loop following one of the test
masses
- Star tracker bias estimation/calibration can be
done a priori or with the acquisition algorithm
- A 57-dof Acquisition model has been developed
- SIMULINK for time-domain analysis
- STATEFLOW for switching logic
- Simulation results confirm the feasibility of
both acquisition strategy
- Thru-telescope approach may not be feasible due
to limited FOV and star availability needs
further investigation
- For More Information
- Technical Note Acquisition with Scan and Defocus
Methods (on PMIS, LISA-TN-GSFC-225, 10 Feb 2005)
- On VSDE The Feb 05 TN, presentations, papers,
working files, animations, and the scan and
defocus 57 DOF simulations (in Matlab/Simulink
files)