EE590 Transmission Planning Projects and Cost Allocation - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

EE590 Transmission Planning Projects and Cost Allocation

Description:

... beyond the 10-year simulation time frame based on an extrapolation of the market ... Example of Benefit Calculation for Single Year (cont. ... – PowerPoint PPT presentation

Number of Views:88
Avg rating:3.0/5.0
Slides: 42
Provided by: rco57
Category:

less

Transcript and Presenter's Notes

Title: EE590 Transmission Planning Projects and Cost Allocation


1
EE590Transmission Planning Projects and Cost
Allocation
  • Ming NI
  • Economic Studies, Midwest ISO

2
Transmission Planning Projects
  • Reliability Projects
  • Identified either in the periodically
    performed Baseline Reliability Study, or in
    Facilities Studies associated with the request
    processes for new transmission access.
  • Baseline Reliability Projects Network upgrades
    identified in the base case as required to ensure
    that the Transmission System is in compliance
    with applicable reliability standards.
  • Transmission Access Projects
  • Generation Interconnection Projects
  • Transmission Delivery Service Projects

3
Transmission Planning Projects
  • Economic Project (Regionally Beneficial Projects)
  • Bring economic benefits to the region. Need
    to pass the Benefit/Cost test.

4
Why Cost Sharing
  • FERC Order 890 issued in early 2007
  • Require compliance with nine principles
  • Coordination
  • Openness
  • Transparency
  • Information Exchange
  • Comparability
  • Dispute Resolution
  • Regional Participation
  • Economic Planning Studies, and
  • Cost Allocation

5
MISO Reliability ProjectCost Allocation(RECB I)
6
RECB I Principles
  • Load growth driven projects in one zone (utility)
    can benefit users in another
  • Lower voltage projects have more localized
    benefits than higher voltage - especially within
    a large geographic area RTO
  • Higher voltage projects have at least some effect
    on all grid users but large geographic area of
    RTO must be considered
  • New generator driven transmission projects are
    in-part caused by the generator, but in-part
    benefit more than just the generator or his
    customer
  • New transmission for specified transmission
    service use (point to point requests) can be
    targeted to the requesting customer

7
BRP Project Cost Allocation
  • BRP Allocation mechanism
  • 345 kV and above
  • 20 of cost Postage Stamped across footprint
  • 80 allocated to specific zones based on relative
    impact of project on zones
  • Measure of impact is sum of Line Outage
    Distribution Factor (LODF)Line Length on all
    other lines (branches) in MTEP model
  • Below 345 kV and above 100 kV
  • 100 allocated to specific zones based on
    relative impact of project on zones
  • Measure of impact is sum of Line Outage
    Distribution Factor (LODF)Line Length on all
    other lines (branches) in MTEP model

8
TAP Project Cost Allocation
  • Generator Interconnection Projects
  • 50 allocated to Interconnection Customer
  • 50 allocated to zones by same mechanism as BRP
  • Point-to-point Transmission Service Projects are
    directly assigned to requesting customer

9
MISO Economic ProjectIdentification and Cost
Allocation(RECB II)
10
Qualifying Tests
  • Project Cost gt 5 million
  • And project voltage is gt 345 kV
  • And the project is not exclusively a Baseline
    Reliability Project or a New Transmission Access
    Project
  • If a project is both a BRP and a RBP, allocated
    as RBP

11
Benefit Metric
  • Benefit Metric is calculated on region level
    (MISO East, Central and West Region).
  • For each hour, calculate the regions Load Cost
    Saving, and regions Adjusted Production Cost
    Saving.
  • Regions Load Cost Saving is the change in load
    energy payment (Load Load LMP)
  • Regions Adjusted Production Cost Saving is the
    change of Regions Adjusted Production Cost,
    which equals
  • Regions Production Cost (fuel costs, variable
    OM costs and emissions costs)
  • Regions Purchase Region Load Weighted LMP
    (if it purchase at that hour)
  • - Regions Sale Region Generation Weighted LMP
    (if it sales at that hour)
  • Regions Annual Benefit 70 Regions Annual
    Adjusted Production Cost Saving 30 Regions
    Annual Load Cost Saving

12
Study Year
  • MISO Tariff Language
  • minimum of 10 years of benefits with a maximum
    20 year horizon model
  • For a project with ISD of 2011, we will run
    PROMOD for the in service year (2011), 5 years
    after (2016) and 10 years after (2021). For the
    years between, these 3 years, we will use the
    linear interpolation based 3 years values.

13
Benefit/Cost Ratio
  • Present value of MISOs annual benefit (sum of
    regions) for the first 11 years (2011 to 2021 if
    ISD is 2011) of project life compared to present
    value of annual project cost for first 11 years
    of project life
  • The threshold B/C ration increases linearly with
    the time until planned in-service date.

14
(No Transcript)
15
Cost Allocation
  • Twenty percent (20) of the Project Cost of the
    Regionally Beneficial Project shall be allocated
    on a system-wide basis to all Transmission
    Customers and recovered through a system-wide
    rate.
  • Eighty percent (80) of the costs of the
    Regionally Beneficial Projects shall be allocated
    on a sub rgion-wide basis to all Transmission
    Customers in each of the three defined Planning
    Sub Regions. The region with negative total NPV
    benefit will not share any portion of these 80
    cost.
  • Example 1
  • Total NPV Benefit East M100
    Central M200, West M300
  • Then Cost Allocation East 16.67,
    Central 33.33, West 50
  • Example 2
  • Total NPV Benefit East M-100
    Central M200, West M300
  • Then Cost Allocation East 0,
    Central 40, West 60

16
(No Transcript)
17
PJM Reliability ProjectCost Allocation
18
Cost Allocation Method
  • For projects gt 500 kV
  • 100 of project cost is regionally allocated to
    PJM zones based on load-ratio share
  • For projects lt 500 kV
  • Use the DFAX (Distribution Factor) Method

19
Basic Concepts
  • DFAX
  • DFAX (After-shift power flow pre-shift power
    flow) / Total amount of power shifted
  • Total amount of power shifted Modeled
    incremental megawatt transfer to a given Load
    Deliverability Area
  • Pre-shift power flow Megawatt flow over the
    constrained transmission element before the
    incremental megawatt transfer
  • After-shift power flow Megawatt flow over the
    constrained transmission element after the
    incremental megawatt transfer
  • Capacity Emergency Transfer Objective (CETO)
  • Transfer limitation into the LDA.

20
Example
21
Example (Cont)
22
Example (Cont)
23
Example (Cont)
24
Example (Cont)
25
PJM Economic ProjectIdentification and Cost
Allocation
26
Process Overview
  • Annual Benefit Metric
  • Annual Benefit (.7)(?System Production
    Cost)(.3)(?Load Energy Payment)
  • ?System Production Cost is change in system
    generation variable cost (fuel costs, variable
    OM costs and emissions costs) associated with
    total PJM energy production
  • ?Load Energy Payment is change in net load energy
    payment (change in gross load payment minus
    change in transmission right credit)
  • For projects that have costs allocated regionally
    (500 kV and up), the load energy payment for all
    PJM zones is considered
  • For projects that have costs allocated using a
    flow-based methodology (below 500 kV) , the load
    energy payment for only those PJM zones that show
    a decrease in load energy payment is considered

27
Process Overview (cont.)
  • Simulation/Model Details
  • Annual market simulations made with and without
    upgrade for future years 1, 4, 7 and 10 (current
    year (cy), cy3, cy6 and cy9)
  • Annual benefits within the 10-year time frame for
    years which were not simulated interpolated using
    these simulation results
  • Annual benefits for years beyond the 10-year
    simulation time frame based on an extrapolation
    of the market simulation results for years 1, 4,
    7 and 10
  • A higher-level annual market simulation made for
    future year 15 (cy14) to validate the
    extrapolation results and extrapolation of annual
    benefits for years beyond the 10-year simulation
    time frame may be adjusted accordingly

28
Process Overview (cont.)
  • Cost/Benefit Analysis
  • Present value of annual project benefit for first
    15 years of project life compared to present
    value of annual project cost for first 15 years
    of project life
  • Project is considered economic and included in
    RTEP if B/C ratio exceeds 1.251

29
Example of Benefit Calculation for Single Year
Annual Benefit Metric Calculation Benefit
(.7)(153.3M) (.3)(-83.4) 82.3M
(for 500 kV and above) Benefit
(.7)(153.3M) (.3)(784,7) 342.7M
(for below 500 kV)
30
Example of Benefit Calculation for Single Year
(cont.)
Note On a total system basis, Delta Net Load
Payment Delta Gross Gen Revenue and Delta
Congestion Costs Delta FTR Credits therefore
explicit calculation of FTR credits is not
necessary in order to determine Delta Net Load
Payments for entire system.
31
Annual Benefit Extrapolation
32
Annual Benefit / Annual Costs
C/B analysis uses 15 years of project costs and
benefits starting with project in-service year
33
NPV Analysis
  • Present value of annual project benefit for first
    15 years of project life compared to present
    value of annual project cost for first 15 years
    of project life
  • Project is considered economic and included in
    RTEP if B/C ratio exceeds 1.251

B/C Ratio 1,731 / 1,039 1.66 gt 1.25
34
Cost Allocation Method
  • For projects gt 500 kV
  • 100 of project cost is regionally allocated to
    PJM zones based on load-ratio share
  • For projects lt 500 kV
  • Use the DFAX (Distribution Factor) Method

35
Cost Allocation Example
36
Cost Allocation Example (Cont)
37
Cost Allocation Example (Cont)
38
Cost Allocation Example (Cont)
39
Cost Allocation Example (Cont)
40
Cost Allocation Example (Cont)
41
Cost Allocation Example (Cont)
Write a Comment
User Comments (0)
About PowerShow.com