Title: EE590 Transmission Planning Projects and Cost Allocation
1EE590Transmission Planning Projects and Cost
Allocation
- Ming NI
- Economic Studies, Midwest ISO
2Transmission Planning Projects
- Reliability Projects
- Identified either in the periodically
performed Baseline Reliability Study, or in
Facilities Studies associated with the request
processes for new transmission access. - Baseline Reliability Projects Network upgrades
identified in the base case as required to ensure
that the Transmission System is in compliance
with applicable reliability standards. - Transmission Access Projects
- Generation Interconnection Projects
- Transmission Delivery Service Projects
3Transmission Planning Projects
- Economic Project (Regionally Beneficial Projects)
- Bring economic benefits to the region. Need
to pass the Benefit/Cost test.
4Why Cost Sharing
- FERC Order 890 issued in early 2007
- Require compliance with nine principles
- Coordination
- Openness
- Transparency
- Information Exchange
- Comparability
- Dispute Resolution
- Regional Participation
- Economic Planning Studies, and
- Cost Allocation
5MISO Reliability ProjectCost Allocation(RECB I)
6RECB I Principles
- Load growth driven projects in one zone (utility)
can benefit users in another - Lower voltage projects have more localized
benefits than higher voltage - especially within
a large geographic area RTO - Higher voltage projects have at least some effect
on all grid users but large geographic area of
RTO must be considered - New generator driven transmission projects are
in-part caused by the generator, but in-part
benefit more than just the generator or his
customer - New transmission for specified transmission
service use (point to point requests) can be
targeted to the requesting customer
7BRP Project Cost Allocation
- BRP Allocation mechanism
- 345 kV and above
- 20 of cost Postage Stamped across footprint
- 80 allocated to specific zones based on relative
impact of project on zones - Measure of impact is sum of Line Outage
Distribution Factor (LODF)Line Length on all
other lines (branches) in MTEP model - Below 345 kV and above 100 kV
- 100 allocated to specific zones based on
relative impact of project on zones - Measure of impact is sum of Line Outage
Distribution Factor (LODF)Line Length on all
other lines (branches) in MTEP model
8TAP Project Cost Allocation
- Generator Interconnection Projects
- 50 allocated to Interconnection Customer
- 50 allocated to zones by same mechanism as BRP
- Point-to-point Transmission Service Projects are
directly assigned to requesting customer
9MISO Economic ProjectIdentification and Cost
Allocation(RECB II)
10Qualifying Tests
- Project Cost gt 5 million
- And project voltage is gt 345 kV
- And the project is not exclusively a Baseline
Reliability Project or a New Transmission Access
Project - If a project is both a BRP and a RBP, allocated
as RBP
11Benefit Metric
- Benefit Metric is calculated on region level
(MISO East, Central and West Region). - For each hour, calculate the regions Load Cost
Saving, and regions Adjusted Production Cost
Saving. - Regions Load Cost Saving is the change in load
energy payment (Load Load LMP) - Regions Adjusted Production Cost Saving is the
change of Regions Adjusted Production Cost,
which equals - Regions Production Cost (fuel costs, variable
OM costs and emissions costs) - Regions Purchase Region Load Weighted LMP
(if it purchase at that hour) - - Regions Sale Region Generation Weighted LMP
(if it sales at that hour) - Regions Annual Benefit 70 Regions Annual
Adjusted Production Cost Saving 30 Regions
Annual Load Cost Saving
12Study Year
- MISO Tariff Language
- minimum of 10 years of benefits with a maximum
20 year horizon model - For a project with ISD of 2011, we will run
PROMOD for the in service year (2011), 5 years
after (2016) and 10 years after (2021). For the
years between, these 3 years, we will use the
linear interpolation based 3 years values.
13Benefit/Cost Ratio
- Present value of MISOs annual benefit (sum of
regions) for the first 11 years (2011 to 2021 if
ISD is 2011) of project life compared to present
value of annual project cost for first 11 years
of project life - The threshold B/C ration increases linearly with
the time until planned in-service date.
14(No Transcript)
15Cost Allocation
- Twenty percent (20) of the Project Cost of the
Regionally Beneficial Project shall be allocated
on a system-wide basis to all Transmission
Customers and recovered through a system-wide
rate. - Eighty percent (80) of the costs of the
Regionally Beneficial Projects shall be allocated
on a sub rgion-wide basis to all Transmission
Customers in each of the three defined Planning
Sub Regions. The region with negative total NPV
benefit will not share any portion of these 80
cost. - Example 1
- Total NPV Benefit East M100
Central M200, West M300 - Then Cost Allocation East 16.67,
Central 33.33, West 50 - Example 2
- Total NPV Benefit East M-100
Central M200, West M300 - Then Cost Allocation East 0,
Central 40, West 60
16(No Transcript)
17PJM Reliability ProjectCost Allocation
18Cost Allocation Method
- For projects gt 500 kV
- 100 of project cost is regionally allocated to
PJM zones based on load-ratio share - For projects lt 500 kV
- Use the DFAX (Distribution Factor) Method
19Basic Concepts
- DFAX
- DFAX (After-shift power flow pre-shift power
flow) / Total amount of power shifted - Total amount of power shifted Modeled
incremental megawatt transfer to a given Load
Deliverability Area - Pre-shift power flow Megawatt flow over the
constrained transmission element before the
incremental megawatt transfer - After-shift power flow Megawatt flow over the
constrained transmission element after the
incremental megawatt transfer - Capacity Emergency Transfer Objective (CETO)
- Transfer limitation into the LDA.
20Example
21Example (Cont)
22Example (Cont)
23Example (Cont)
24Example (Cont)
25PJM Economic ProjectIdentification and Cost
Allocation
26 Process Overview
- Annual Benefit Metric
- Annual Benefit (.7)(?System Production
Cost)(.3)(?Load Energy Payment) - ?System Production Cost is change in system
generation variable cost (fuel costs, variable
OM costs and emissions costs) associated with
total PJM energy production - ?Load Energy Payment is change in net load energy
payment (change in gross load payment minus
change in transmission right credit) - For projects that have costs allocated regionally
(500 kV and up), the load energy payment for all
PJM zones is considered - For projects that have costs allocated using a
flow-based methodology (below 500 kV) , the load
energy payment for only those PJM zones that show
a decrease in load energy payment is considered
27 Process Overview (cont.)
- Simulation/Model Details
- Annual market simulations made with and without
upgrade for future years 1, 4, 7 and 10 (current
year (cy), cy3, cy6 and cy9) - Annual benefits within the 10-year time frame for
years which were not simulated interpolated using
these simulation results - Annual benefits for years beyond the 10-year
simulation time frame based on an extrapolation
of the market simulation results for years 1, 4,
7 and 10 - A higher-level annual market simulation made for
future year 15 (cy14) to validate the
extrapolation results and extrapolation of annual
benefits for years beyond the 10-year simulation
time frame may be adjusted accordingly
28 Process Overview (cont.)
- Cost/Benefit Analysis
- Present value of annual project benefit for first
15 years of project life compared to present
value of annual project cost for first 15 years
of project life - Project is considered economic and included in
RTEP if B/C ratio exceeds 1.251
29Example of Benefit Calculation for Single Year
Annual Benefit Metric Calculation Benefit
(.7)(153.3M) (.3)(-83.4) 82.3M
(for 500 kV and above) Benefit
(.7)(153.3M) (.3)(784,7) 342.7M
(for below 500 kV)
30Example of Benefit Calculation for Single Year
(cont.)
Note On a total system basis, Delta Net Load
Payment Delta Gross Gen Revenue and Delta
Congestion Costs Delta FTR Credits therefore
explicit calculation of FTR credits is not
necessary in order to determine Delta Net Load
Payments for entire system.
31Annual Benefit Extrapolation
32Annual Benefit / Annual Costs
C/B analysis uses 15 years of project costs and
benefits starting with project in-service year
33 NPV Analysis
- Present value of annual project benefit for first
15 years of project life compared to present
value of annual project cost for first 15 years
of project life - Project is considered economic and included in
RTEP if B/C ratio exceeds 1.251
B/C Ratio 1,731 / 1,039 1.66 gt 1.25
34Cost Allocation Method
- For projects gt 500 kV
- 100 of project cost is regionally allocated to
PJM zones based on load-ratio share - For projects lt 500 kV
- Use the DFAX (Distribution Factor) Method
35Cost Allocation Example
36Cost Allocation Example (Cont)
37Cost Allocation Example (Cont)
38Cost Allocation Example (Cont)
39Cost Allocation Example (Cont)
40Cost Allocation Example (Cont)
41Cost Allocation Example (Cont)