Project Planning and Estimation - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Project Planning and Estimation

Description:

Web engineering projects often adopt the Agile process model ... For small software projects, one person can analyze requirements, perform design, ... – PowerPoint PPT presentation

Number of Views:461
Avg rating:3.0/5.0
Slides: 33
Provided by: AdamM98
Category:

less

Transcript and Presenter's Notes

Title: Project Planning and Estimation


1
Project Planning and Estimation
  • Chapters 23, 24
  • Software Engineering A Practitioners Approach
  • Roger S. Pressman

2
Project Planning
  • When need for software has already been
    established stakeholders are on-board coding is
    ready to begin
  • What project planning spans five major
    activitiesestimation, scheduling, risk analysis,
    quality management planning, and change
    management planning
  • Who software project managers, with information
    from stakeholders and engineers

3
Estimation
  • Planning requires estimation early-on, even
    though it is likely this commitment will be
    proven wrong
  • Some degree of uncertainty is unavoidable when
    predicting into the future
  • Solid techniques and concrete procedures help
    reduce the inaccuracy of estimates

4
Process-based estimation
  • Most commonly-used technique for project
    estimation
  • Project is broken down into a relatively small
    set of tasks and the effort required to
    accomplish each task is estimated
  • Begins with a delineation of software functions
    obtained from the project scope

5
Process-based estimation
  • A series of framework activities must be
    performed for each function
  • Representative framework activities
  • Customer communication
  • Planning / risk analysis
  • Engineering
  • Construction / release
  • Functions and activities may be shown together as
    a table

6
Process-based estimation table
7
Process-based estimation
  • Once functions and activities are melded, the
    planner estimates the effort (person-months)
    required to accomplish each activity per function
  • Average labor rates are then applied to the
    estimated efforts (may vary per task)
  • Cost and effort for each function and activity
    (row and column totals) are computed as the last
    step

8
Estimation with use-cases
  • Use-cases provide insight into software scope and
    requirements
  • However, developing an estimation approach with
    use-cases is problematic
  • There is no standard form for use-cases
  • They represent an external view (the users view)
    of the software, and vary in levels of
    abstraction
  • Use-cases do not address the complexity of a
    feature
  • Use-cases do not describe complex interactions
    between many functions and features

9
Estimation with use-cases
  • One persons use-case could require months of
    effort, another just a day or two
  • Estimation using use-cases has been investigated,
    but no proven method has emerged to date.
  • Smith suggests a method for using use-cases, but
    in a strict, hierarchical manner

10
Use-case estimation
  • A structural hierarchy is described for the
    project
  • Any level of the hierarchy can be described by no
    more than 10 use-cases
  • Each of the use-cases would encompass no more
    than 30 distinct scenarios

11
Use-case estimation
  • Use-cases for a large system are described at a
    much higher level of abstraction then use-cases
    for individual sub-systems
  • Before use-cases can be used
  • The level within the structural hierarchy is
    established
  • Average length (in pages) of each use-case is
    determined
  • The type of software (business, scientific, etc)
    is defined
  • Rough architecture for the system is considered

12
Use-case estimation
  • Once those characteristics are established,
    empirical data can be used to determine estimated
    LOC or FP per each use-case for each level of the
    hierarchy
  • Historical data are then used to calculate the
    effort required to develop the system

13
Sample use-case estimation
  • LOC N LOCavg (Sa/Sh - 1) (Pa/Ph - 1)
    LOCadjust
  • N actual number of use-cases
  • LOCavg historical average LOC per use-case
    for this type of system
  • Sa actual scenarios per use-case
  • Sh average scenarios per use-case for this
    type of system
  • Pa actual pages per use-case
  • Ph average pages per use-case for this
    type of system
  • LOCadjust represents an adjustment based on n
    percent of LOC where n is defined locally and
    represents the difference between this project
    and average projects

14
Reconciling estimates
  • The various estimation methods encountered result
    in multiple estimates which must be reconciled
  • The goal of a reconciliation process is to
    produce a single estimate of effort, project
    duration, or cost
  • Complicated methods might not yield a more
    accurate estimate, particularly when developers
    can incorporate their own intuition into the
    estimate. -- Philip Johnson, et al.

15
Reconciling estimates
  • Widely divergent estimates can often be traced to
    one of two causes
  • The scope of the project is not adequately
    understood or has been misinterpreted by the
    planner
  • Productivity data used for problem-based
    estimation is inappropriate for the application,
    obsolete, or has been misapplied.
  • The planner must determine the cause of the
    divergence to reconcile the estimates

16
Estimation for Agile projects
  • Requirements for an agile project are defined as
    a set of user scenarios (e.g., stories in
    Extreme Programming)
  • It is possible to develop an estimation approach
    that is informal, but reasonable disciplined for
    each software increment
  • This approach uses a decomposition method with
    the following steps

17
Estimation for Agile projects
  • Each user scenario is considered separately for
    estimation purposes
  • The scenario is decomposed into the set of
    functions and engineering tasks required to
    develop them
  • Each task is estimated separately, based on
    historical data, an empirical model, or
    experience
  • Estimates for each task are summed to obtain an
    estimate for the scenario

18
Estimation for Agile projects
  • 5. The effort estimates for all scenarios are
    summed for a given increment to obtain the
    increment estimate
  • Because the project duration of an increment is
    short (3-6 weeks), the estimation approach serves
    two purposes
  • Ensure that the number of scenarios conforms to
    available resources
  • Establish a basis for allocating effort as the
    increment is developed

19
Estimation for web engineering projects
  • Web engineering projects often adopt the Agile
    process model
  • Along with the Agile estimation approach, a
    modified function point (FP) measure can be used
    to develop an estimate for a web application
  • Roetzheim suggests the following information
    domain values when adopting function points

20
Web application domain values
  • Inputs are each input screen or form, each
    maintenance screen, and each tab (if that design
    metaphor is used anywhere)
  • Outputs are each static web page, each dynamic
    page (script), and each report (whether web-based
    or administrative)
  • Tables are each logical table in the database, or
    each XML object or collection of XML attributes
    (if XML is used for storage)

21
Web application domain values
  • Interfaces retain their definition as logical
    files (for example, unique record formats) into
    our out-of-the-system boundaries
  • Queries are each externally published or use a
    message-oriented interface. A typical example is
    DCOM or COM external references
  • Function points computed with these values are a
    reasonable indicator of volume for a web
    application

22
Web application estimation
  • Mendes suggests that the volume of a web
    application is best determined by collecting
    measures associated with the application called
    predictor variables
  • These include
  • Application level page, media, and function
    count
  • Page level page, linking, and graphic complexity
  • Media level media size, duration
  • Functional characteristics code length, reused
    code length

23
Software project scheduling
  • Creating a network of software engineering tasks
    enabling you to get the job done on time
  • Responsibility is assigned for each task,
    progress is tracked, and the network is adapted
    to changes in the process as they occur

24
Software project scheduling
  • I love deadlines. I like the whooshing sound
    they make as they fly by.
  • Douglas Adams

25
Relationship between people and effort
  • For small software projects, one person can
    analyze requirements, perform design, generate
    code, and conduct tests
  • As the projects grow in size, more people most
    become involved
  • As this happens, more and more time is spent
    managing the interaction and communication among
    the people involved

26
Relationship between people and effort
  • Common myth still believed by many software
    managers If we fall behind schedule we can
    always add more programmers to catch up.
  • Smiths law Adding more people to a late
    software project always makes it later.

27
Relationship between people and effort
  • People added to the project must learn the
    system, and the people who can teach them are the
    people currently producing code
  • In addition to learning time, more people means
    more communication paths and increasing the
    complexity of communication throughout the
    project

28
Elasticity of project schedules
  • Empirical data and analysis has demonstrated that
    project schedules are elastic
  • It is possible to compress a desired project
    completion date to some degree by adding
    resources
  • Conversely, removing resources can extend a
    completion date

29
Putnum-Norden-Rayleigh Curve
  • The PNR Curve provides an indication of the
    relationship between effort applied and delivery
    time for a software project
  • There is a highly non-linear relationship between
    chronological time to complete a project and
    human effort applied

30
Putnum-Norden-Rayleigh Curve
  • The number of delivered lines of code L is
    related to effort and development time by the
    equation L P E1/3t4/3
  • E is development effort in person-months
  • P is a productivity parameter that reflects that
    result in high quality (typically 2,000-12,000)
  • t is the project duration in calendar months

31
Putnum-Norden-Rayleigh Curve
  • Rearranged to solve for development effort E
    L3/(P3t3)
  • E is effort expended (in person-years) over the
    entire project life-cycle
  • L is lines of code (source statements)
  • P is a productivity parameter that reflects that
    result in high quality (typically 2,000-12,000)
  • t is the development time in years

32
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com