Title: ETH Zurich


1
CGSE Status
  • Outline
  • 0. Remarks (2)
  • 1. Problems on valve boxes, crystat, simulator
    and transfer lines
  • 2. Repairs
  • 3. Modifications
  • 4. Schedule
  • 5. Manpower

2
CGSE Problems
  • 1. Welds
  • 90 of welds are not acceptable for cryogenic
    application
  • Root Porosity (due to lack of Argon TIG)
  • Lack of penetration
  • Combination of the two
  • 2. Design Errors
  • Lack of compensators in G-He valve box and
    Cryostat
  • Vapour cooled shield (parallel instead of coil)
  • 3. Burning of cryogenic valves in L-He valve box

3
(No Transcript)
4
(No Transcript)
5
(No Transcript)
6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
CGSE Repairs at CERN
  • After two meetings in the Central Workshop with
    engineers and expert Welders, it was decided that
    the operation of the CGSE in its state is too
    risky
  • Repair of transfer lines in B112 (ex LHC)
  • 2 expert welders from Central Workshop
  • Repair of valve boxes, cryostat and simulator in
    B180 (ex ATLAS Toroid)
  • 2 expert welders and 1 pipe fitter from STMBA, a
    firm that was used by LHC cryogenics for the
    repair of QRL and valve boxes

11
B 180
12
B180
13
B112
14
B112
15
Modifications
  • Add filter into L-He valve box to remove
    particles from entering the Simulator (Magnet)
    during cool down to 80 K
  • Remove HX1 from cryostat
  • Replace HX2 by Heating Tapes
  • Install new vapour cooled shield into L-He valve
    box

16
Modifications
17
Schedule
  • 1. L-He valve Box 15/09/2008
  • 2. G-He valve box  middle 08/2008
  • 3. Cryostat end 08/2008
  • 4. Simulator end 07/2008
  • 5. Transfer Lines end 08/2008
  • 6. Compressor assembly end 08/2008
  • 7. Leak Tests from end 07 09/2008
  • Installation of CGSE will start beginning of
    September
  • Pumping and leak testing until end of September
  • Cool-down of Simulator can start at the beginning
    of October

18
Manpower Plan
  • Control System Yang 2 students 15/08
  • The 2 students stay until Xmas, Shudong Xu
  • CGSE repair, installation tests Huang and Xu
    from 25/08 until cool down is terminated, Vassily
    Plyaskin (replaces me when I am absent), Ken
    Bollweg, Johan Bremer LHC/CR (consultancy) and
    myself help from AMS technicians.
  • Working group on process control All mentioned
    above Mike Capell and Alexei Lebedev others
    (CERN)
  • Repair Team 4 expert welders 1 pipe fitter
    engineering help from Central Workshop.
  • Jobs still to be done Organize pumps leak
    detectors