Title: LGS Project Meeting


1
LGS Project Meeting
  • December 21, 2006
  • Agenda
  • SWIFT update - A. Bouchez
  • Laser facility status - A. Bouchez
  • AO bench plans - J. Roberts
  • LGS user interface - J. Roberts
  • FlexCam A method for sensing non-common path
    pointing errors on PalAO - K. Wallace

2
SWIFT Optical Design
http//www.astro.caltech.edu/oir/swift/
3
SWIFT Mechanical Design
4
SWIFT mounting to AO bench
  • SWIFT optical bench mounts ot AO bench using 3
    permanently located conical mounting points.
    Clamp mechanism is captive to SWIFT bench.
  • Mounting scheme for PHARO FM3 still unresolved.

5
SWIFT handling cart
  • Allows work on instrument with optics up and
    mounting to AO bench on AO spit and at on
    telescope (Cass ring at 155º).
  • Now provides 1 cm fine position and tilt
    adjustment using mechanism below.

6
Review panel recommendations
  • Arrival at Palomar should be delayed 2-3 months
    (to May-June 2008) to allow more thorough
    integration and testing.
  • I T schedule needs to be more clearly defined.
  • More resources should be devoted to software
    development.
  • Operational modes and calibrations need to be
    defined.

7
SWIFT tasks for Palomar and AO group
  • Clarify mass limit. SWIFT currently estimated to
    be 220 kg cables. Determine if AO bench can
    support weight.
  • Provide non-common path flexure data to SWIFT
    team. Determine if we can mitigate before SWIFT
    arrival.
  • Plan mounting scheme and purchase of new science
    dichroic.
  • Determine strategy regarding SWIFT shutter.
  • Layout AO relay ( PHARO) to provide focus at new
    location.
  • Recoat relay optics (OAPs and flats).
  • Design new mounting scheme for PHARO FM3.
  • Implement required changes to AO stimulus.
  • Build new enclosure.
  • Consider implications of SWIFT on NGS/LGS
    acquisition software and procedures.

8
AO 5-year plan
9
Laser facility status
  • Laser is in good shape for January observing run.
  • Power and wavefront quality
  • Replace both laser heads with Mach-3 design (Jan.
    10-17)
  • Replace sum-frequency and intra-cavity crystals.
  • Document laser optical design.
  • Characterize delivered wavefront quality.
  • Characterize bandwidth and pulse shape.
  • Reliability and automation
  • Improved cleanliness (clean-room enclosure, clean
    optics).
  • Improved temperature control of bench
    (insulation, etalon control).
  • Phased implementation of LGS computer
  • Temperature display and control.
  • Frequency dither loop control.
  • Power display and logging.
  • Image display and logging.
  • Program delay generator.
  • Operations
  • Document operations procedures

10
AO Bench Opto-mechanics
  • Current plans for January/February
  • Dichroic
  • Separate reflecting spot and dichroic
    capabilities into 2 optics
  • Use a motorized stage to switch between the two
    optics
  • LOWFS
  • Testing to determine the cause of the observed
    loss of light in the LOWFS path
  • Future Plans
  • Re-layout LOWFS and acqusition camera in order to
    put the LOWFS directly in the beam path and
    remove the pick off requirement

11
New Dichroic Layout
  • Dichroic
  • Separate reflecting spot and dichroic
    capabilities into 2 optics
  • Use a motorized stage to switch between the two
    optics
  • LOWFS
  • Testing to determine the cause of the observed
    loss of light in the LOWFS path

12
AO Software
  • Build for January includes bug fixes and
    previously tested code only
  • aodr bug fix for recording BTO data
  • Ability to turn off late message warnings in aodr
    (now the default)
  • Remove debug print in aocp when doing a restore
  • AO software version switching
  • New user interface to be implemented for February
    run
  • Includes NGS improvements and new mode structure
    for LGS

13
New LGS User Interface
GUI Functionality
  • Full document located at http//www.oir.caltech.ed
    u/twiki_oir/bin/view.cgi/Palomar/PalmLGS/WebHome
  • under Technical Reference (until theres an AO
    software page)