Title: Generation
1Comprehensive renewal of IC at Loviisa Nuclear
Power Plant
Fortum Power and Heat / Loviisa Power Plant Ulf
Linden
- IAEA Technical Meeting on the Impact of Digital
Instrumentationand Control Technologies on the
Operation and Licensing of Nuclear Power
Plants3-6 November 2008 Beijing, China
2Loviisa 1 and 2
- Reactor 510 MWe PWR (VVER-440 213)
- Plant owner Fortum Power and Heat
- Location Finland, Loviisa, 80 km east of
Helsinki - Commissioning Unit 1 1970 - 1977, Unit 2 1972 -
1980 - High energy availability, short outages
- Originally installed IC systems
- Siemens hardwired solution for operational IC
and ESFAS (Teleperm C, Simatic P) - Russian solution for RPS (SUZ) and Control rod
IC - Renewal 2008
- part of RPS AREVA TXS
- waste water handling systems Siemens T2000
3Load Factors of Loviisa Power Plant 1977-2007
4Renewal of IC - Reasons for Renewal
- The nuclear power units Lo1 and Lo2 were
commissioned in 1977 and 1980. Plant life time
has been extended to at least 50 years. - It is not possible to maintain the original IC
systems to the end of the plant lifetime the
systems are obsolete and problems with spare
parts will increase. - It is hard to get new engineers that have the
knowledge in maintaining and repairing 30 years
old electronic cards - An IC renewal was required. The objective of the
renewal is to ensure that the IC systems will
not limit the safe and economical use of the
plant during the remaining lifetime of plant. - The units are now around the half of their
lifetime. Now it is the right time to make the
renewal while there is still a lot of lifetime
left.
5Milestones passed
6Overall Scope of the Renewal
Control room
Renewed
Automation cabinets (Data acquisition and
logics)
Switchgear
Training simulator
Actuators
Field equipment
7Time schedule
IC renewal time schedule
- STAGE 1 (pilot stage)
- Reactor shutdown, control rod sequence
- control and position indication
- automation systems of waste water handling
Commission
C
F
Lo1
Commission
C
F
Lo2
Commission
STAGE 2 Reactor protection and power
control Emergency diesel generator IC
F
C
Lo1
Commission
C
F
Lo2
Commission
C
F
STAGE 3 IC systems of the primary process
systems, ventilation systems
Lo1
Commission
C
F
Lo2
Commission
C
F
STAGE 4 (option) IC systems of the secondary
process and auxiliary systems
Lo1
Commission
C
F
Lo2
Contract with Supplier FAT Commission
C
F
8Main Principle of the Renewal
- The functions of the old automation remain.
- Single failure tolerance is built into the
automation concept - New cabinets are placed into new buildings that
fulfill all new requirements (seismic req., EMC,
etc.). - Selection of a competent supplier, who has
applicable products of reliable and proven
technology that can be licensed in Finland - Simulators shall be used effectively in the
renewal process.
9New IC buildings
- New buildings have been built for the IC
cabinets. - Due to the new buildings
- installations are easier.
- new requirements are met more easily
- better channel separation
- better EMC characteristics
- better seismic characteristics.
10Control room
- Control room renewal
- Fortum is responsible for
- Functional design of control room and MMI
- Control room verification and validation (VV)
- Fortum will extensively use different kind of
simulators in the design process - Supplier is responsible for implementation
- and integration
- Existing control rooms
- Separate control rooms for both units
- Main control room (MCR
- Auxiliary control room (ACR)
- Ventilation control room (VCR
- Severe accident management (SAM) control room
common for both units
11Loviisa 1 main control room before renewal of
IC for unit 1 stage 1)
12Loviisa 1 Control room stage 1
13Doing IC projects in stagesChallenges
- Doing the project in stages may be more
economical than in one big outage, but - Several stages have to go on in parallel
- More resources are needed
- Are the software and hardware version installed
in the first stage still usable in later stages
or will a long project cause ongoing updates? - There will be several test fields and several
factory acceptance tests is testing only in
small parts enough? - Can people involved commit themselves to be in
the project for so many years? - Persons may change on both the supplier and
purchaser side
14Challenges Critical Path
- Installation and commissioning performed in
outages - Short time for work
- A problem during installation or commissioning
can prolong the outage in an unacceptable way - A delay in one stage can move the schedule for
other stages - Very challenging to do the modifications in the
control room in stages - May need temporary controls during outages for
critical systems and components - Challenging to do the modifications in the
simulator - The training of control room operators must start
6 - 12 months before commissioning,
15Some lessons learned
- Good Requirement Specifications are very
important - tools for tracing requirements needed
- Collection of initial data from an old plant
- huge amount, in which form and in which language
shall it be delivered - can the engineers of today read 30 year old hand
written circuit diagrams - Resources
- most experienced people on the plant needed
- not the only project for the supplier
- Supplier's organisation
- the supplier must have a project organisation on
the site that closely works together with plant
people - Authorities
- national nuclear guidelines must be taken into
account in licensing
16Success factors
- Fortum had a good knowledge of the new system
- Comprehensive training of people, participating
in the testfield, installation and commissioning - Large pre-installations were done before outage
- Simulated assisted testing
- Automation systems must be tested before
installation - Like virtual commissioning, dynamic tests can be
run - Errors from faulty initial data could also be
found
17Summary
- Two Nuclear Power Plant Units
- Four modernization stages/unit between 2008 and
2014 - Two main suppliers
- New IC buildings enable pre-installations
- Installation and commissioning in normal
refueling outages - Modifications made also to the control room and
full scope training simulator - Successful commissioning in 2008 of stage 1.