Title: Business Continuity Program Disaster Recovery Program Update
1Business Continuity Program/Disaster Recovery
Program Update
- Statewide BCP Project
- SDC Disaster Recovery Plan Service Contract
Project - eBRP Project
Contributors CNIC BCP Team
CNIC Disaster Recovery Task Force State
Data Center
February 2007
2Background Multiple Projects within a BCP/DR
Program
3Background - Projects
- 1) Statewide BCP Initiative
- This initiative was launched in March 2006 with
the implementation of the Statewide BCP Policy.
It is managed by the DAS Enterprise BCP office
and provides guidelines and direction for State
agencies in their plan development. - 2) eBRP Toolkit Project
- In Fall 2006, the eBRP Toolkit was selected for
the storage and publication of BCP and DR plans
for state agencies. This project manages Phase 1
of the implementation, training and utilization
of the toolkit by 12 state agencies. Subsequent
phases will include the inclusion of additional
agencies and testing. - 3) BCP Tabletop Test Project
- At the conclusion of the eBRP Toolkit Project,
this project will manage BCP tabletop tests for
12 state agencies.
4Background - Projects
- 4) SDC Recovery Service Contract Project
- This project establishes a disaster recovery
service contract for applications and systems
hosted at the SDC. -
- 5) SDC/Agency DR Test Project
- This project executes disaster recovery tests per
the DR awarded service contract for systems
hosted at the SDC. - 6) Agency DR Test Projects
- This project executes disaster recovery tests per
the DR awarded service contract for agency
systems. - 7) Ongoing BCP/DR Plan Maintenance
- Business Continuity Plans and Disaster Recovery
Plans will be maintained and routinely tested by
each agency through their established
maintenance programs.
5 6Statewide BCP Initiative Objectives
- Designation of BCP Coordinators and Sponsors.
- Identification of critical business functions.
- Developed, tested, and maintained BCP.
- Complete DR plans for the IT infrastructure that
support the critical business functions. - Implementation of BCP maintenance programs.
- Established awareness and training programs to
create organizational awareness.
7Ultimate Goal
- All Agencies will have developed, maintained, and
tested plans by June 2009 to restore and recover
their business operations in the event of a
disaster.
8Phased Approached Proposed Planning Goals
- The Enterprise BCP Office has recommended that
agencies develop their BCP utilizing a phased
approach - This will focus agencies to work on those most
critical business functions - Four Phases are recommended
- Phase 1 CBF that must be restored within 2 days
- Phase 2 CBF that must be restored within 1 week
- Phase 3 CBF that must be restored within 2
weeks - Phase 4 CBF that must be restored within 1
month
9Statewide BCP Initiative Tracking the Progress
- The Enterprise BCP Program will use a Scorecard
to track the progress of the implementation of
the Statewide BCP Policy. - The Scorecard will use the standard Green
Yellow Red Status indicators - Agencies that have met the planning goals will
receive a GREEN Status - those that have partially met the goals will
receive a YELLOW status and - those who have not met the goal in any form will
receive a RED Status.
10Statewide BCP Initiative The Scorecard
11- SDC Disaster Recovery Plan Service Contract
Project
12SDC Disaster Recovery Plan Contract Project
Overview
- The CNIC CIOs formed a CNIC Disaster Recovery
taskforce to examine and propose DR solutions for
systems and services managed by the State Data
Center. - The current Sungard DR service contract was
extended through October 2007, while requirements
for a new RFP and service contract can be
gathered and awarded.
13SDC Disaster Recovery Plan Contract Project
Objectives
- Gather requirements for critical business
functions and applications supported by SDC
managed systems. - Issue an RFP for recovery service contract
pricing. - Analyze pricing and select recovery options and a
recovery vendor. - Issue a recovery service contract that
- will be executed with the SDC for SDC managed
systems and services - may be executed by CNIC agencies for out-of-scope
systems and services - The DR component of this project will be tracked
and managed by the use of a Scorecard which
includes the DR tasks and milestones. - IT data gathered to support the acquisition of
the DR service contract will be used to load SDC
and Agency instances of eBRP.
14Recovery Time Objective (RTO)
SDC Disaster Recovery
The Recovery Time Objective (RTO) is the least
amount of time required by a business function
and/or application to recover critical services,
measured from time of disruption to resumption of
critical business operations. As a part of the
BIA, SunGard classified the RTOs for the critical
functions identified by the State of Oregon
agencies. The graph below denotes the number of
functions that have an RTO of less than 1 day
(blue) and between 1-2 days (burgundy).
14
15SDC Disaster Recovery
Recovery Point Objective (RPO)
Data
The Recovery Point Objective (RPO) is the amount
of data that each business function is willing to
lose if a disruption occurs. As a part of the
BIA, SunGard classified the RPOs for the critical
functions identified by the State of Oregon
agencies. The graph below denotes the number of
functions that have an RPO of less than 1 day
(blue) and between 1-2 days (burgundy).
15
16 SDC Disaster Recovery
16
17SDC Disaster Recovery Plan Service Project
Scorecard
Note The scorecard reflects phases for a) DR
Plan Development, b) DR RFP and Service Contract,
and c) Subsequent DR Planning and Tests.
18How Much of a Robust DR Capability is Needed?
When compared against Agencys consensus on
existing risk..
Recovery Windows
Recovery Point
Recovery Time
18
19 20eBRP Toolkit Project Overview
- This project supports the Statewide BCP Policy
by implementing the eBRP Toolkit software within
the 12 CNIC agencies. - The eBRP Toolkit bridges the gap between business
and IT. This project encompasses two distinctive
components, the development and maintenance of
agency BCP and DR plans. - The software will allow state agencies to manage
business continuity planning (BCP) and disaster
recovery (DR) planning. The resulting plans
published through the software will be used
during an event to manage recovery strategies. - All 12 Agencies are expected to support and
maintain the eBRP Toolkit by dedicating the
resources necessary for the development of their
business continuity plans and disaster recovery
data within the tool. The implementation team
consists of a minimum of a BCP and DR
administrator from each agency.
21eBRP Toolkit Project Objectives
- Implementation of toolkit to the 12 CNIC
agencies. - Build disaster recovery strategies and plans that
are aligned with critical business functions and
support agency business continuity plan
development. - Data will be loaded and maintained by each of the
agencies into their own eBRP instance, using data
entry and toolkit import processes. - Each agency will determine the extent of data
loaded based on their individual BCP
requirements. - The 12 CNIC agencies will participate in the
development and use of common terms and codes to
support the long term goals of the statewide BCP
initiative.
22eBRP Toolkit Project Bridging the Gap
23eBRP Toolkit Project Logistics
- All location data must be entered.
- All technology data must be entered.
- To populate the other sections of the Toolkit,
each Agency will use their top 6 Critical
Business Functions (CBF). - New milestones have been established.
- To successfully meet the new milestones
identified on the WBS, the complete location and
technology data must be entered into the Toolkit
as well as the information pertaining to the 6
CBFs. - If an Agency has less than 6 CBF they will be
required to input the data of those CBF they have
identified.
24eBRP Toolkit Project - WBS
25eBRP Project - Project Support Toolkit Training
- Basic Training 1 September 2006 (Plan
Development) - Basic Training 2 November 2006 (Basic Entry
Organization Data) - IT Training January 17th 18th 2007
- Basic Training 3 TBD 2007 (Process
Development) - Toolkit Assistance for individual help, the
Enterprise BCP Office, Enterprise Application
Services (EAS), and the SDC are available to
assist BCP and DR Administrators as needed. Call
the Enterprise BCP Office to request help
503-373-1067.