Title: The Past, Present, and Future of CQC in FDOT
1Contractor Quality Control
- The Past, Present, and Future of CQC in FDOT
- Presented by Kevin Price and David Sadler at 2008
FTBA/FDOT Construction Conference
2Topics
- Past Deployment of CQC (QC2000)
- Origin in FDOT, areas of work covered, personnel
qualifications, risks, outcomes, lessons learned,
Specifications, QC Plans/Manuals - Present Deployment of CQC
- Projects, findings, lessons learned,
Specifications, QC Plans/Manuals, personnel - Future Deployment of CQC
- Continued use, areas of work being considered,
Specifications, QC Plans/Manuals, personnel
3Topics continued
- Role s and Responsibilities of the
- Contractor
- QC Manager
- QC Plans/Manuals
- Recent Specification Changes
- Section 6
- Section 105
4Past Origin of CQC in FDOT
- When Greg Xanders was State Construction
Engineer, he initiated the program for FDOT where
contractors would perform their own quality
control. - This effort began at a time in which the sitting
Governor directed all state agencies to reduce
staff by 25 and also at a time when FDOTs
construction program was burgeoning.
5Past Origin of CQC in FDOT
- The program began in 1998 with projects being
piloted in several Districts for contractors,
consultants, and FDOT to gain experience in the
process of having Contractors perform QC sampling
and testing with FDOT performing Verification
sampling and testing. -
6Past Origin of CQC in FDOT
- FDOT fully implemented the CQC program on all
its construction projects let after July 1, 2002. - Authority to use Contractor test results was
given by the FHWA via its Technical Advisory
T6120.3 under the conditions that FDOT had in
place a system of performing verification testing
of the Contractors QC results.
7Past Origin of CQC in FDOT
- Technical Advisory T6120.3 required states to
ensure that contractors and owners had trained,
qualified staff to perform sampling and testing. - To satisfy the training and qualification
requirements, FDOT initiated the Construction
Training Qualification Program (CTQP).
8Past Areas of Work
- Areas covered under the CQC umbrella
- Asphalt Mix
- Portland Cement Concrete (Structural)
- Earthwork
- Cementitious Materials
- Timber
- Steel and Miscellaneous Metals
- Galvanized Metal Products
- Prestressed and/or Precast Concrete Items
- Drainage Products
9Past Risks, Outcomes and Lessons
- Psychological
- adjustments
- needed
10Past Risks, Outcomes and Lessons
- Outcome of the piloted projects was that FDOT
revised its developmental specifications based
on what it learned and adopted them as standard
specifications. - A lesson learned was that there were some
contractors manipulating the test results of
samples to avoid penalty or plant shut down.
11Past Risks, Outcomes and Lessons
- Because of the findings that a few of the
contractors were manipulating results, FDOT took
actions such as suspension of qualifications of
personnel involved, disallowing bidding of
projects for a period of time, payment of
restitution for damages. - FDOT also gained confidence that its processes
were capable of discovering these actions.
12Past Overall Outcome
- Overall, found that the CQC program was
successful and FDOT had means of handling
performance issues. - This is the case because FDOT has in place
safeguards to verify and validate Contractor
provided QC test results. Also, because FDOT has
maintained separation between QC and QA.
13Past Overall Outcome
- The verification of Contractors QC testing
results should be viewed, not as a lack of trust
of those results, but as a means of ensuring that
the taxpayers money is being spent appropriately. - Trust but verify.
14Past QC Plans and Manuals
- QC Plans FDOT worked with industry to develop a
boilerplate document as a framework upon which
contractor could build its plan. - QC Manual FDOT encouraged contractors to
develop a QC Manual that would be adopted
statewide and allow contractors to make reference
to the manual in its QC Plan, thus shortening the
plan.
15Past QC Plans and Manuals
-
- While it is not possible to determine from the
contractors QC Plan whether the level of
construction quality will be acceptable, it is
possible to verify that the contractor, as an
organization, has addressed the basic elements of
its quality process.
16Present
- As stated previously, FDOT implemented CQC on
all projects beginning with July 2002 lettings. - FDOT continues to monitor these projects for
compliance with specifications and procedures.
17Present National CQC Perspective
- Nationally, there are approximately 35 states
that have some level of Contractor Quality
Control. - FDOT has the most work areas covered by CQC.
- There are two of the 35 states that are going
back to self-performing sampling and testing.
18Present - Findings
-
- FDOT is still finding most contractors in
compliance with specifications but occasionally
have also found examples of contractors
manipulating test results. In these cases, FDOT
has exercised its options as appropriate to the
offense.
19Present Lessons Learned
- Roving Verification Technicians
- Still having areas of training needs
- Still personnel (FDOT, Contractors, and
Consultants) that have not embraced the CQC
program havent fully made the psychological
adjustment.
20Present - Specifications
- The one constant with the specifications has been
Change. - Changes due to many reasons
- industry recommendations
- owner needs
- technology changes
- research results
- owner reassessments (R2)
21Present QC Plans
- FDOT still has requirement for QC Plans.
- Seeing two common occurrences with QCPs
- FDOT looking for too much in plans
- Contractor including too little in plans
- The QC Plan is the document outlining the
Contractors process for delivering the level of
quality defined in the contract.
22Present QC Manuals
- Still have option for Contractor QC Manual.
- Presently, there are six contractors that have
submitted and received approval of their QC
Manual. - FDOT sees a value in the QC Manuals that has not
been fully recognized yet.
23Present Personnel
- CTQP qualifications still required
- CTQP providers have been expanded
- CTQP QC Manager course rewritten for 2007
24Contractors Quality Control Plan
25QC Plan Definition
- Federal Highway Administration Defines
- A contractor quality control plan (CQCP) is the
documentation of the contractors process for
delivering the level of construction quality
required by the contract.
26QC Plan Definition continued
- CQCP is where the contractor outlines what they
are going to do to control quality where
applicable. - CQCP can be a living breathing document that
changes during a single contract or it may not
change through multiple contracts. - Contractors will use the same plan for all the
ongoing projects. - Consistency of the contractors staff and
operations from project to project.
27Contractors Quality Control Plan
- No requirement for format.
- Requirements for content found in 105
- Materials found in 6-8
- Draft plans found at FTBA and ACAF websites
- Can be amended by a letter
- Recommend that long term projects have the CQCP
updated to reflect mix design changes and TIN
numbers
28QC Plan Materials
- Certain materials must be produced with an
approved quality control program - HMA
- Structural Concrete
- Earthwork
- Cementitious materials
- Timber
- Steel and Misc metals
- Galvanized Metal products
- Prestressed/Precast concrete products
29Specification consolidation
- Sections 6 and 105 have been recently combined to
consolidate the Quality Control requirements - To read the entire specification go to
- http//www.dot.state.fl.us/specificationsoffice/Hi
storyJuly2008WorkBook/1050000.impl.pdf
30Producers of
- Flexible and Concrete pipe
- Prestressed/Precast Concrete products
- Incidental Precast/Prestressed Concrete Products
- Portland Cement Concrete
- Structural Steel and Miscellaneous Metal
Components - Shall meet the requirements of the materials
manual in addition to the specifications
(105-3.2)
31Contractors
- 105-3.8 Contractors Quality Control Plan Have
an approved Quality Control Plan meeting the
requirements of this Section for the
transportation, storage, placement, and other
related construction operations required by the
Contract Documents. - Different location, same statement. Current CQC
plans should be valid providing that the
applicable materials are addressed.
32QCP Submittal
- State Materials Office
- Producers of cementitious materials, steel and
miscellaneous metals, galvanized metal products,
and aggregates must submit their proposed Quality
Control Plan to the State Materials Office for
review and acceptance.
33QCP Submittal continued
- District Materials Office
- Producers of hot mix asphalt, Portland cement
concrete (Structural), earthwork, timber,
prestressed and/or precast concrete products and
drainage products must submit their proposed
Quality Control Plan to the local District
Materials Office for acceptance. - Producers located outside the State must contact
the State Materials Office for address
information of the District Materials Office
responsible for the review of the proposed
Quality Control Program.
34QCP Submittal continued
- CQC Plans are submitted at the project level
- FDOT allowed 21 days to respond
- Specifications still require CQC plans to be
submitted 21 days after award - Needs revising - If changed, when should it be
submitted? - FDOT has seven days to review and respond to all
revisions, including revisions due to plan
suspensions.
35Quality Control Plan Content
- Your plan should address how your firm will
produce a product that meets the specifications. - Generalities are acceptable
- Multiple suppliers are acceptable providing that
they are all approved - Typical courses of action when a problem does
arise - Standard individualized information not found in
the contract like rolling patterns
36Quality Control Plan Content
- Should address how you are going to handle
unspecified situations with regard to materials
acceptance. - Should address your methods of meeting the
specifications. - Should address common situations that may arise
during the construction of an item and how the
contractor chooses to handle it - Should identify technical staff by TIN for
applicable items
37Quality Control Plan Content
- Does not need to state the obvious
- Should not restate the specifications
- Not required to have each and every supplier
listed upon initial submittal. - There is no required format only required
content - No limitations Suppliers primary, back up, Back
up,
38Contractor Quality Control Manager
39Responsibilities
- Ensure that materials produced for acceptance are
in substantial compliance with the contract. - Ensure technical staff are qualified
- Implement QC plan
- Paperwork
40Responsibilities
- Mediator between the department and the
contractor - Specification interpreter
- Educator/Trainer
- Documentation administrator
41Contractors responsibilities
- ensure that the material suppliers are approved
- Acquire certification documents
- Coordinate scheduling and delivery
- Ensure project compliance
42Requirements
- A responsible position with the contractor
- Able to make changes to bring materials to
acceptable limits - Execute the monthly statement of compliance
- Provide test or inspection reports to the
department - Does not report to field staff
- Must speak and understand English
43General
- May be a subcontractor
- Entire Quality control division may be
subcontracted - Requirements/responsibilities do not change
44CQC Future
45Future
- FDOT intends to continue its use of CQC
- FDOT will continue to evaluate the performance in
the areas of work covered by CQC and look for
ways to improve with industry input - If appropriate, other areas of work will be
included under CQC none on the horizon at this
time
46Future
- Changes in the specifications from method to
performance specs - Revisit the boilerplate QC plan
- Work on process for expediting QC Plan
changes/revisions - Certification requirements review
47Questions??
48Common Comments/Questions
- What is the value added by CQC?
- The value gained by the FDOT with CQC is
49Common Comments/Questions
- You guys know what you want, so why make the
contractor do the documentation. - Response the value gained by having the
contractor perform the sampling/testing and
reporting is cradle to grave responsibility and
accountability.
50Common Comments/Questions
- QC Plans wheres the value here?
- Value to the Department is assurance that the
contractor has accounted for and planned its work
in compliance with specifications
51Common Comments/Questions
- Before a specification is changed, the question,
Will this add cost or will this add value? - This is done before specification changes. A
determination is made to assess the cost impacts.
52Common Comments/Questions
- Should have clear specifications with guidelines.