BATTLEMENT CREEK FIRE - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

BATTLEMENT CREEK FIRE

Description:

At the time of the accident the weather in Rifle was 93 F, dew point 55 (RH 28%), winds NE at 4 ... An underground nuclear detonation. A 43 kiloton bomb, 8,426 ... – PowerPoint PPT presentation

Number of Views:1527
Avg rating:3.0/5.0
Slides: 37
Provided by: adm81
Category:

less

Transcript and Presenter's Notes

Title: BATTLEMENT CREEK FIRE


1
BATTLEMENT CREEK FIRE
  • USDI, Bureau of Land Management
  • Grand Junction District
  • Glenwood Springs Resource Area
  • July 17, 1976

2
(No Transcript)
3
FUELS
  • Primary fuel type was Gamble oak
  • A severe frost on 14 June had killed a high
    percentage of the leaves

4
(No Transcript)
5
WEATHER
  • No weather observations were taken on the fire
  • The closest weather station was Rifle, 12
    miles to the ENE
  • At the time of the accident the weather in
    Rifle was 93 F, dew point 55 (RH 28), winds NE
    at 4

6
FROM THE ACCIDENT REPORT
  • At the time of the accident, the atmosphere was
    unstable, normal up-slope winds were occurring,
    winds aloft were generally light SW and ranged
    from 5-15 m.p.h. from 6,600 feet to 31,000 feet
    m.s.l.

7
FROM THE ACCIDENT REPORT
  • Observers on the fire at the time of the
    accident reported high winds at ground level
    25-35 m.p.h. and above.

8
TOPOGRAPHY
  • West Aspect
  • Elevation 8550
  • Slopes ranged from 10-75

9
ORIGIN
  • 11 July 1600 HRS, Fire reported
  • Contained at ½ acre by Grand Valley VFD
  • 12-14 July Fire monitored by Grand Valley VFD
  • 15 July Fire escapes
  • 16 July Fire has grown in size to over 500
    acres, B-26 air tanker crashes with one fatality

10
FIRE PERIMETER, 17 JULY
11
(No Transcript)
12
Project Rulison
  • 1969
  • An underground nuclear detonation
  • A 43 kiloton bomb, 8,426 foot deep
  • To investigate the possibility of using nuclear
    explosions to extract natural gas from low grade
    deposits
  • Marginally successful in causing the gas to
    collect in the cavity and fissures produced by
    the bomb
  • The gas was too radioactive to be sold
    commercially
  • The site was threatened by the fire

13
7/17 ASSIGNMENTS
lower
upper
  • Happy Jack Hotshots were assigned to burnout
    the line starting from point A to point D

B-26 Accident x
14
7/17 ASSIGNMENTS
lower
upper
  • Happy Jack Hotshots were assigned to burnout
    the line starting from point A to point D

B-26 Accident x
15
7/17 ASSIGNMENTS
lower
  • Mormon Lake Hotshots were assigned to improve
    and burnout the line starting from point E to
    point G

upper
16
7/17 ASSIGNMENTS
lower
  • Mormon Lake Hotshots were assigned to improve
    and burnout the line starting from point E to
    point G

upper
17
  • Mormon Lake Hotshots
  • Happy Jack Hotshots

18
(No Transcript)
19
(No Transcript)
20
FROM THE ACCIDENT REPORT
  • Apparently, neither crew knew of the specific
    location or assignment of the other.

21
(No Transcript)
22
(No Transcript)
23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
Mormon Lake Hotshots, 1976
30
(No Transcript)
31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
(No Transcript)
35
  • Apparently, neither crew knew of the specific
    location or assignment of the other.

36
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com