Title: Proposed Key Agenda Topics


1
Proposed Key Agenda Topics
Discussion Options for Managing AOCs
Environmental Clearinghouse Topic Briefing on
Permitting for OTIA III Bridge Projects
  • Water Quality Committee Meeting
  • February 3, 2004

2
Environmental Clearinghouse
  • Major Component of My Job/Performance Standards
  • To Date, Consolidating Information on
  • Laws/Rules/Policies/Guidance/BMPs/BMP Design
    Manuals
  • Developing/Posting this Information On-line (see
    hand-out)
  • Visit Compliance Guide on the Environmental
    Services website
  • http//aocweb.org/em
  • Options for Managing this Information

3
Environmental Clearinghouse Options
  • Web-based decision-making tree like TurboTax
  • Take info. in on-line create a decision-making
    tree
  • Design based on perspective of road dept.
    employee
  • E.g., If ditch cleaning, what do I need to do
    if anything to comply?
  • User prompted by a question w/ several reply
    choices
  • Replies take you key information or application,
    guidance etc.
  • Create an Information Management System (EMS)
  • Environmental Management System
  • Decision-making tree like TurboTax database aid
    in compliance decisions automate completion of
    permit applications reports
  • GIS of county road system w/ environmental
    constraints to target BMP application
  • GPS/PDA for automating monitoring requirements
  • Tracking/database of staff environmental training

4
Permitting of OTIA III Bridges
  • In a Nutshell
  • If feasible, design for compliance with SPGP
  • Using ODOTs Bridge GA RGP is not an Option
  • However, can use ODOTs planning current
    contract work to date to save time/money on
    county permitting
  • No ODOT Wetland Mitigation Sites/Banks to Tap
    Into

5
Permitting OTIA III Bridges (continued)
  • If feasible, Design for Compliance w/ SPGP
  • Requires context sensitive design
  • Have to comply with SLOPES II
  • Key in on Section 2.2.3
  • Terms/Conditions 2.r and 2.t. i(1)(b) and
    7.a.b.c.
  • www.nwr.noaa.gov/1publcat/bo/2003/200300850_slopes
    _07-08-2003.pdf
  • ESA Section 7 Consultation already done
    programmatically
  • ODOTs Bridge GA/RGP Not an Option
  • Designed for specific ODOT bridge projects.
  • However, ODOTs work could serve as a foundation
    for a future programmatic GA/GRP
  • ODOT is reluctant to assume liability of county
    projects

6
Permitting OTIA III Bridges (continued)
  • Using ODOTs Planning/Contract Work to date
  • When Possible, Use ODOTs BA to save /reduce
    permitting issues
  • This will reduce the number of ecological effects
    to consider
  • Reduce the ecological effects to negotiate w/
    Services
  • Reduce the level of contractor support needed
  • ODOT Bridge GA (Jan./Feb. 2004) and Bridge RGP
    (March 2004)
  • ODOTs Contractor is Negotiating Performance
    Standards
  • These are agreed upon terms/conditions
  • Stds. integrate regulatory programs/requirements
  • These include SLOPES II terms/conditions
  • If counties use these when possible, it will
    reduce consultation time
  • Parametrix will develop a performance standard
    guide for agencies
  • ODOTs Bridge Program Management Firm
  • OACES may want to meet w/ ODOT management
  • Request that P.M. Firm train Co. Project Managers

7
Permitting OTIA III Bridges (continued)
  • No ODOT Wetland Mitigation Sites To Tap Into
  • ODOT doesnt want to get into the land mgt.
    business
  • ODOT is developing a framework/approach for
    replacing wetland ecological functions lost
  • This is a tool not a place where you can do
    mitigation
  • Establishes key ecological functions for region
  • Goal is to establish function-based mitigation
    standards
  • This will avoid the current ratio approach to
    mitigation
  • Oregon R-F statute allows for this but ratio
    approach is currently used
  • Once tested/approved, other agencies can use
    approach
  • Listing of mitigation banks will be included in
    Permitting Template for county road programs

8
Permitting Guide for Bridge Projects
  • Draft Guide for Navigating the Permitting OTIA
    III Bridge Projects
  • For Draft in Development, see
  • http//www.aocweb.org/em
  • Click on Compliance Guide Site Link
  • Click on Wetlands/Streamsides Link

9
SPGP Update
  • Goal for SPGP Issuance is April 1 this year
  • DSL/Corps pushing Services to wrap-up the Section
    7 Consultation
  • Issuance date will likely be too late for 2004
    work window