Title: Rich Halvey
1 2- LSEs, transmission providers, generation
developers, state regulators can make more
informed decisions about - Costs of renewable power
- Optimum transmission needed to move renewable
power to consumers - Potential partners in developing transmission to
access renewable areas and - Where renewable energy developers can site their
facilities to ensure access to the transmission
system and minimize environmental impacts.
3- Outside of the CA ISO and AB, there is no
mechanism in the Western Interconnection to force
unwilling parties to pay for new transmission. - LSE fuel choices will ultimately determine what
transmission gets built. - LSE resource planners (and regulators) often
operate in stovepipes and may miss opportunities
for inter-company collaboration. - Inter-company collaboration is important because
transmission is a lumpy investment with large
economies of scale. One LSE may not need all the
capacity created by transmission to a REZ.
4- Promotes a regional view of renewables
development blunting potential balkanization of
the renewables markets. This is particular
important for development of renewables that are
distant from load centers. - Paves way for interstate collaboration on
- Permitting of multi-state transmission
- Allocating and recovering cost of new
transmission. - Could provide an informational foundation for new
approaches to interconnection and transmission
service queuing problems.
5- Highly integrated grid
- Excellent and diverse renewable resources
- State-by-state REZ initiatives
- Other Western Interconnection actions important
to the WREZ work
6(No Transcript)
7- Identification of WREZs
- Technical analysis
- Stakeholder ground truthing
- Conceptual transmission from WREZs
- Coordinated procurement for renewables (beyond
current budget period) - Institutional options to facilitate interstate
transmission for renewables (beyond current
budget period)
8Organization of REZ Project
Steering Committee (Governors, PUC Commissioners,
Premiers, Federal ex-officio members)
Technical Committee (states, provinces, work
group chairs)
NREL technical support
LBNL Technical Support
Zone Identification/Technical Analysis
Generation/ Transmission Modeling
Environment, Land Use and Permitting
Ad Hoc Work Group?
9Technical Committee
Resource zone identification work group
Environment, land use permitting work group
Generation/ transmission modeling work group
Economic assumptions in supply curves
Areas to be excluded and minimum elements an area
must have to be considered
Areas of concern
Mitigation measures and cost
Conceptual transmission plans
Model for LSE evaluation of interest in REZs
Area requiring close collaboration
10- Technical work
- Technology characterization resource assessment
application of filters, supply curves
delineation of WREZ boundaries - Transparency/communication Maximum stakeholder
input to identifying WREZs - Web based GIS
- Easy electronic stakeholder input
- Iterations between technical work (e.g.,
technical contractor work, stakeholder input, and
WREZ technical committee/work groups) - Build on/supplement individual state REZ work
11- Identify areas for consideration, based on
resource potential and transmission
requirements. We would exclude known areas where
development would be disallowed (e.g., national
parks, urban areas, unacceptable terrain). By
default, this would also define which areas are
not going to be analyzed for REZ potential. This
does not mean only the REZs will be developed,
but that only certain areas will meet the
criteria to be a REZ.
12- Based on the criteria, NREL would produce a base
resource map. - The Identification/Analysis Work Group and the
Environment and Lands Work Group would then meet
separately and jointly to determine which areas
within the areas for consideration should be
excluded and which areas would become the
candidate study zones. The work groups have to
agree on the study zones.
13- The study zones would be refined based on
exclusionary criteria (e.g., wildlife, species,
water) - Supply curves would only be developed for the
study zones. Supply curves could include
information regarding mitigation activities. - Based on the supply curve work, propose REZs.
The work groups would sign off on these. - The Technical Committee would approve final REZ
maps.
14- Areas for Consideration - areas to be
included/excluded and minimum factors to qualify
for further study - Candidate Study Zone - based on the application
of additional exclusionary factors and
transmission requirements - Proposed REZ - proposed REZs for public review in
September - Final REZ - Phase 1 findings
15- LSE fuel choice is prime determinant
- After identification of REZs, LSE need tools to
- Prioritize REZ options
- Compare with other options
- Identify synergies with other LSEs
- Integrate with existing sub-regional and WECC
transmission expansion planning processes
16- Elements not defined
- Phase 2 modeling tool can provide foundation for
coordinated procurement - Increasing LSE competition for renewables could
be beneficial or unconstructive
17- Elements not defined
- Build on existing efforts
- WGA Transmission Permitting Protocol
- NTTG
- Infrastructure Authority coordination on HPX
18- May 28-29 kick-off meeting Salt Lake City
- July 11 Technical Committee finalizes work plan
and schedule - Late August - workshop to review candidate study
areas, identification criteria (renewable
potential and environmental) - November 1- identify developable renewable energy
zones - December 30 - supply curves and mitigation
strategies developed - Jan 3 - Draft report sent to Technical Committee
- Jan 30 -Technical Committee meeting to consider
draft report - Feb 1 28 public comment and outreach
- March 13 - revised draft report
- March 31 - Technical Committee meets to finalize
report - April 16 - final report to Steering Committee
- May 1, 2009 Steering Committee meets to approve
report - May 1, Launch of Phase 2 (transmission from
zones)