Title: EU EXTERNAL AID
1EU EXTERNAL AID
Raul Mateus Paula
EFCA - 21th March 2002
2This presentation underlines
- The key objectives of the Relex Reform
- The division of the responsibilities
- EuropeAid organization
- Project cycle phases (Financial phase.
Implementation phase.) - Futures developments
3The Key Objectives of the Relex Reform
The key objectives of the Relex Reform
- Make significant improvements in the quality and
efficiency of project management - Substantially reduce the time taken to implement
projects - Ensure robust and efficient management procedures
- Improve the impact and visibility of the Aid
4The division of the responsabilities
Division of Responsibilities
- EuropeAid is responsible for the project cycle
from identification through implementation - DG Relex and DG Dev are responsible for the
pluri-annual programming
Mettre en oeuvre lensemble des instruments d
5EuropeAid organization
The six stages of the Project Cycle Today
6Project cycle phases
Project cycle phases
- Programming
- Analyse situation to identify problems which
development co-operation could address - Identification
- Identify project ideas and screen them for
further study - Formulation
- Develop relevant project ideas into operational
project plans - Financing
- Commission decides to fund project and agrees
arrangements with beneficiary country - Implementation
- Mobilise and execute project
- Evaluation
- Assess project achievements and identify lessons
7Financing phase
Project cycle phases
8Implementation phase
Project cycle phases
- Award contract(s) to implement projects
- fair competition
- transparency
- Manage execution of projects
9Procurement rules applicable to EC external aid
Project cycle phases
- Specific rules for projects in the interest of
beneficiary countries - Directives and WTO rules if the projects are in
the interest of - the Commission or
- both the Commission and beneficiary countries
10Public procurement Directives
Project cycle phases
- Apply to public procurement by Member States and
the Commission itself - Govern
- choice of award procedure
- rules on publicity
- candidates allowed to tender
- selection and award criteria
11EC external aid contracts
Project cycle phases
- Commission for and on behalf of the Government
of a beneficiary country - Title IX of the existing Financial Regulation
provisions applicable to external aid - Commission must comply with the basic principles
adhered to by the Union in the field of public
contracts, particularly for the Directives
Committee of Independent Experts
12Manual of Instructions
Project cycle phases
- Adopted by the Commission on 10/11/99 after 3
years of consultations with the market and
representatives of the EU Member States - negotiated with Member States
- warmly welcomed by consultancy organisations
- commended by Transparency International
13Impact of Manual of Instructions
Project cycle phases
- Before
- 46 different contract procedures between the EC
external aid programmes - different Web sites with different presentations
and information content - After
- 8 contract procedures for all EC external aid
programmes - unique Web site
14EuropeAid Web site
Project cycle phases
- Allows consultants to search procurement notices
by programme and type of contract - Contract forecasts, procurement notices, Calls
for Proposals, shortlist notices and contract
award notices all published - Initially 200,000 hits per month, now 800,000
hits per month, making it the most heavily
consulted Web site on the entire Europa server
15(No Transcript)
16(No Transcript)
17(No Transcript)
18(No Transcript)
19Practical Guide to EC external aid contracts
Project cycle phases
- Incorporates full text of Manual of Instructions
- Provides operational detail necessary to
implement Manual of Instructions - Annexes include standard tender dossiers,
contracts, publication templates, Guidelines for
Grant Applications and templates for letter to
candidates and tenderers
20Contract award procedures - Service contracts
Project cycle phases
- ? 200,000
- International restricted tender procedure
- lt 200,000 but gt 5,000
- 1 Framework Contract
- 2 Simplified procedure
- ? 5,000
- Single tender
21Contract award procedures - Supply contracts
Project cycle phases
- ? 150,000
- International open tender procedure
- lt 150,000 but ? 30,000
- Local open tender procedure
- lt 30,000 but gt 5,000
- Simplified procedure
- ? 5,000
- Single tender
22Contract award procedures - Works contracts
Project cycle phases
- ? 5,000,000
- 1 International open tender procedure
- 2 International restricted tender procedure (in
exceptional cases) - lt 5,000,000 but ? 300,000
- Local open tender procedure
- lt 300,000 but gt 5,000
- Simplified procedure
- ? 5,000
- Single tender
23International tender procedure - Service contract
Project cycle phases
- Publish procurement notice
- Candidates submit applications
- Shortlist panel applies selection criteria
- Tender dossier sent to short-listed candidates
- Tenderers prepare and submit tenders
- Evaluation Committee examines tenders
- Award contract
24International tender procedure - Supply or works
contract
Project cycle phases
- Publish procurement notice
- Tender dossier sent to interested tenderers
- Tenderers prepare and submit tenders
- Evaluation Committee examines tenders
- Award contract
25Project cycle of a 2-year service contract
Project cycle phases
26Grants
How to award grants
- Programming
- Publicity
- Call for Proposals
- Transparency and impartiality
- Standard guidelines and forms
- Evaluation procedure
- Record keeping
27Grants
Award procedures
- Local Call for Proposals
- If one or more of the 4 conditions are not
satisfied - Direct Award
- Exceptional procedure to be used only in four
specific cases - objective of the grant programme
- special legal or technical characteristics
- running cost grants
- unforeseeable events (urgency)
- International Call for Proposals
- If 4 conditions are all satisfied
- programme budget is at least 2,000,000
- minimum grant is at least 100,000
- applications from other countries are likely
- programme is not restricted to national
applicants
28Grants
Evaluation procedure
- Receipt and opening
- Administrative compliance
- Eligibility
- Evaluation of technical quality
- Recommendations
- Approval of final list
Signature of the contract
- Standard contract
- Derogations must all be individually endorsed
by the EC - No derogations global endorsement by the EC
- Modifications addendum
29Futures developments
Futures developments
- Application to EDF
- Standard financing decision financing agreement
- EC external aid Finance Guide Update
- Update of the Practical Guide
- CRIS Appel doffre
- Extensive Devolution