Title: Procurement and manpower for service installation


1
Procurement and manpower for service installation
  • Services readiness dates
  • Planning for type ii/iii
  • Fibre installation dates
  • PS installation plan
  • Readout installation plan covered by Janet
  • PS and ROD mapping

2
Where to find information?
  • Installation WP document https//edms.cern.ch/docu
    ment/499680/1
  • Tuesday mornings, CRM (control room management)
    meetings https//edms.cern.ch/document/526887/1
  • (Pamela Ferrari, Sandra Ciocio attend for ID).
  • Any installation in racks in US(A)15 should be
    discussed here
  • Wednesday mornings ID/TC installation meeting
    https//edms.cern.ch/document/462288/1
  • Numerous ID representatives
  • Focussing on services installation so far.
  • New schedule v.7.09 talks by Miikka Kotamaki in
    the last TMB http//agenda.cern.ch/fullAgenda.php?
    idaa055703
  • Schedule is now under scrutiny
  • Safety course
  • Level 4 course mentioned in the bulletin is for
    LHC machine experts only not for work in ATLAS
  • Safety course in English is now available every
    day in Building 55

3
Timescales for services - NEW
  • Type IV installation complete on US side. USA
    just starting. Will drop to lower priority when
    type II/II cable installation begins.
  • 2 November barrel calorimeter moves to z0
    (this is an additional delay since the last TMB)
  • Sequence in a sector is
  • Tubes, fibres, heater cables, SCT cables, (Muon
    chambers),
  • TRT cables, pixel cables

4
Organisation for type II/III services
  • New organisational effort to work out detailed
    installation strategy
  • Management team being established
  • Nicolas Massol (TC - coordinator), Sigi Wenig
  • Marek Stodulski (leaving), Jack Fowler (part
    time), Stefan Valker, Hans Danielsson
  • Technical follow up from Marco Olcese (based in
    Genova and commuting to CERN from Nov 05)
  • Installation teams
  • Cables at PPB/F1 Need experienced people from
    the subsystems to make connections at PPB/F1
  • Cables over cryostat flange 8 people from Prague
  • Cables from tile gaps outwards TC installation
    team of Russians (already in place)
  • Tubes on flange current installation team
  • Design work on flange should not be the
    bottleneck plan to finish by end of the year

5
List of SCT cables in sector 3
  • To be extracted from services inventory by Sigi
    Wenig

6
Planning for type II/III power cables
  • Type II/III service installation is supposed to
    start on 15th December in sector 3
  • Company are at present making double length
    harnesses with type II cable and connectors on
    both ends. Saverio will work on QA.
  • We need cable trays to be in place to measure
    lengths of type II/III harnesses with trial
    cables
  • Company will then take 2-3 weeks to make
    harnesses
  • We must supply tables of lengths, connectors (not
    yet delivered to CERN), labels (final scheme
    being worked out)
  • Include a few spares for instant replacements
    (and maybe even try to install a few?????)

7
(dummy) PPB1 and PPF1
  • PPB1 mechanics and dPPB1 boards seem to be under
    control
  • Test of dPPB1 prototype was made in the pit
  • A few pieces (clamps) need to be remade
  • PPF1 mechanics - needs some attention
  • Agreed in Engineering meeting in NIKHEF to
    redesign the cable clamp to avoid deforming
    cables
  • The clamp is supported from the cryostat and is
    sufficient to locate the type II cable in the
    correct position
  • The mechanics to support the dPPF1 PCBs is NOT
    available (either not yet made or in use at
    Liverpool/NIKHEF)
  • dPPF1 boards should be fabricated on time need
    to find a way to support them

8
Fibres
  • First fibres to be installed 15 December
  • Boxes of data fibres should have been delivered
    yesterday to Bat 188-1-001
  • Space there to sort out all boxes, get fibres in
    sequence for installation, do inventory
  • Tony strongly resists any testing to avoid
    spoiling the heavy duty rigging we paid for
  • Need to verify that we understand
    connectivity/labels in enough detail.
  • FSI fibre drums are still in Bat 226. Urgently
    need a person to take charge of planning
  • Where to cut them to length?
  • Are all the steps for pulling/stripping/splicing
    sufficiently understood
  • Make labels

9
Mapping
  • A lot of discussion recently about power supply
    mapping
  • DCS and other experts are fully informed of the
    results of the mapping some implications for
    interlock complexity.
  • Barrel crates not mixed with end cap crates
  • Some end cap crates mix EC-A and EC-C but
    cooling circuits (quadrants) collected in the
    same crate

10
Cables between racks in US(A)15
  • We are collecting a list of services needed
    between racks in US and USA15
  • These must be put into the cable DB and given to
    Sergei Malyukov to book slots in cable trays and
    find out lengths
  • Marco Olcese does not want to add them to the ID
    services inventory

11
Conclusions
  • Dates for installation of first type II/III
    cables are known
  • Urgent need to identify skilled people to do
    connections at PP1 without depleting SR1 team
  • Logistics of type II/III power cables will be
    interesting
  • Need to improve plans for dPPF1 for power cables
  • Planning for fibres (especially FSI) needs to be
    improved
  • Have to go through the list of other cables and
    verify that all is going to be in time