Title: UNENE 32 S1
1Chapter 3 -- Case Studies Lecture 2Accident
Histories - Future Lessons
- Louis Slotin USA
- NRX Canada
- SL-1 USA
- Other reactivity-initiated events Japan
- Close call - ZPR-3 USA
2Why Study Old Accidents?
- Typical Failure Trend for a New TechnologyRef.
K.O. Ott and J.F. Marchaterre (1981)
- Accidents are usually highly complex
- Most designs obey single failure rule
- High component of human factors
- Lessons learned for future designs
- Humility
3A Learning Experience?? Ref. Meneley (1982)
Three Mile Island Accident
UFM - unidentified failure mode IFM - Identified
failure mode
New UFM?
Failures per Unit-Year
UFM
Metal Fatigue, or Mental Fatigue?
IFM
Year
Present Time
4Subcritical Initial State(e.g. ref. Slotin
experiment, NRX, SL-1, JCO, etc.)
5Characteristics of a Subcritical Reactor
- It is sleeping -- i.e. innocent, cool, inactive
- Detectors are insensitive, and indications of a
near-to-critical state are not very obvious - It is VERY dangerous if it is nearly critical
- This is the reason for the guaranteed shutdown
state - This is the reason for discouraging fuelling
during shutdown - This is the reason for requiring poised safety
systems during shutdown conditions
6The Louis Slotin Experiment
- At Los Alamos, they called it tickling the
dragons tail. - Louis (from Winnipeg) had done this experiment
many times before. - On May 21, 1946 he made a small mistake -- a
screwdriver slipped - Things went wrong -- and he died nine days later.
- SEE THE DEMONSTRATION
- This provides LESSON 2 in reactor safety - what
is it? - Technical lesson - maintain control at all times
--and backups are good. - Human lesson - we are at least half of the
problem.
7Re-Enactment of Slotin Experiment
8National Research Experimental -- NRXFirst
critical July 22, 1947
9NRX Elevation View Channel X-Section
10The NRX AccidentChalk River, Ontario, December
12, 1952
- A reactivity accident occurred during reactor
startup - What went wrong, and why? Compare different
accounts. - What can we learn?
- What lessons from this event are still
remembered in todays safety procedures?
11NRX Accident Sequence -1
12NRX Accident Sequence - 2
13NRX Accident Sequence - 3
14NRX Accident Sequence - 4
- Cooling flow to experimental rods reduced one
was air cooled - Rods raised earlier in error did not drop when
error was corrected - Reactivity reached 6 mk. positive due to
removal of safeguard - bank power reached 100kW in 20 sec. and 17 MW
at 30 sec. - Voiding of low-flow channels suddenly added
another 2.5 mk - Moderator dump started at 45 sec.
- Peak power 80-90 MW at 49 sec. Rapidly
decreased to low level - at 70 sec.
15NRX Human Errors
16NRX Human Errors (Continued)
17NRX -- Consequence
- Several fuel channels damaged
- Some fuel melting
- Heavy contamination in the building
- No worker injuries
- No significant public dose
- Calandria removed, buried, replaced
- After refurbishment, NRX operated until April 08,
1994
18NRX -- Lessons Learned
- Safeguard bank -- to be poised (ready to
operate) at all times - Loss of confidence in rods
- Large clearances, simple design, fail-safe
- Separation of control safety systems
- Eventually, redundant shutdown systems
19The SL-1 AccidentNational Reactor Testing
Station, Idaho, January 3, 1961
- Reactivity accident from subcritical conditions.
Reactor was intended to supply electricity and
space heating for remote US Army bases, at a
thermal power of 3 MW. - Peak thermal power during transient was 10,000
MW, energy release was 130 MW.s. - First indication of trouble came from personnel
gamma monitors, 1.5 km - Three operators were killed by the explosion
- What went wrong, and why? What can we learn?
What do we remember about the accident?
20SL-1 General LayoutUS Army developed this
concept electricity and heating at remote sites
Why not use the USN reactor design?
Reactor
Operator
21SL-1Elevation View
22SL-1 Core PlanCore was 90 cm square, 35 cm high
23SL-1 Accident Chronology
24SL-1 Lessons Learned
- Single rod rule
- Limits on rod withdrawal speed
- Inherent fast feedback required in reactors where
rapid positive insertion is possible - Human factors / maintenance
25JCO Uranium Processing Plant, Tokai,
JapanSeptember 30, 1999
- Information at ltwww.inea.org.brgt - Newsletter
Publications - Consequences and Causes. - Workers were preparing batches of uranyl nitrate
solution in a tank, and grossly exceeded the
amount of uranium allowed in the tank at one
time. - The tank solution went super-critical. One
worker died. - Investigate this accident
26JCO Processes
Operations became progressively more lax over a
period of years. Criticality was reached in the
precipitation tank - overloaded. Rapid pulse
followed by slow reaction - for 20
hours Criticality terminated by draining cooling
water jacket, to reduce neutron reflection Total
fissions 2.5 x 10E18, or 100 MWsec
27JCO Accident Causes ad Remedies
- Direct cause - addition of Uranyl nitrate in the
amount of 16.6 kg into a tank not designed to
prevent criticality - Contributors (in brief)
- Inappropriate procedure-batch was too large
- Operators performed operations exceeding batch
limit of 2.4 kgU - Tech management failed to provide or enforce
proper procedures - Company did not enforce special control measures
in this (rare) operation - Licensing did not review the operations in detail
- as necessary in criticality cases - Safety regulations did not specify periodic
inspection of operations - Recommendations of this review mainly
concentrated on strenthening of the regulations,
enforcement, and training.
28Eight Antinomies(Conclusions of the Chairman,
JCO Accident Investigation Committee)
- If safety increases, efficiency decreases
- If regulations are reinforced, creativity is
lost - If surveillance is reinforced, spirit declines
- If manuals are introduced, self-management is
lost - If fool-proof measures are implemented, the level
of skills decreases - If responsibilities are centered on a key person,
the group loses concentricity - If responsibilities are too strict, cover-ups
result - If information disclosure is promoted, situation
becomes too conservative.
29Central Finding and ConclusionJCO Committee
Chairman
- AUTHORITY AND RESPONSIBILITY WERE NOT PROPERLY
ASSIGNED -
- CLEAR ALLOCATION OF AUTHORITY AND CORRESPONDING
RESPONSIBILITY WITHIN MANAGEMENT STRUCTURES IS
ESSENTIAL TO ACHIEVEMENT OF SAFE OPERATIONS OF
THE NUCLEAR INDUSTRY
30Memory Aid for Safety Managers The Organization
Tree -- from Masao Nozawa
- If you work near the trunk of the tree you must
be strong -- flexible, but not too flexible. - If you work near the trunk of the tree you must
be aware of the organizations roots and the
sources of its strength and needs of the whole
tree. - If your job is to support the tree as staff you
must accept this as a service role. - If you work part way up the tree you must be
aware of your duty to support the branches above
and to carry out the policies given from below - If you work near the top of the tree you must be
aware of your duty to to grow, and of your
inter-dependence with those below you in the tree.
31Close Call -- Zero Power Reactor 3National
Reactor Testing Station, Idaho, 1964
- Critical assembly experiments for US fast reactor
program - One-half of ZPR 3 slid on a horizontal track, to
ensure that it remained subcritical during
loading. Criticality was achieved by moving two
halves of reactor together slowly, then
withdrawing safety rods - Shutdown via fast-acting rods (poised during
loading). - Independent shutdown action via large scram
motor mounted on the movable track. - Motor was 3-phase, and it was powered from site
power lines -- these were long. Many other
intermittent loads on these lines. Phase
reversal was a common transient condition. - If phase-reversal had occurred coincident with a
scram demand, the reactor halves would have
been slammed TOGETHER rather than being
separated. - Had that happened this lecture would have been
presented by someone else. What was the combined
probability?