UNENE 32 S1 - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

UNENE 32 S1

Description:

... a fuse was blown and the pile tripped allowing all the remaining shut-off rods (5) to drop in. ... step in going from a trip free condition to seven rods in ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 32
Provided by: DanMe8
Category:
Tags: unene | tripped

less

Transcript and Presenter's Notes

Title: UNENE 32 S1


1
Chapter 3 -- Case Studies Lecture 2Accident
Histories - Future Lessons
  • Louis Slotin USA
  • NRX Canada
  • SL-1 USA
  • Other reactivity-initiated events Japan
  • Close call - ZPR-3 USA

2
Why Study Old Accidents?
  • Typical Failure Trend for a New TechnologyRef.
    K.O. Ott and J.F. Marchaterre (1981)
  • Accidents are usually highly complex
  • Most designs obey single failure rule
  • High component of human factors
  • Lessons learned for future designs
  • Humility

3
A Learning Experience?? Ref. Meneley (1982)
Three Mile Island Accident
UFM - unidentified failure mode IFM - Identified
failure mode
New UFM?
Failures per Unit-Year
UFM
Metal Fatigue, or Mental Fatigue?
IFM
Year
Present Time
4
Subcritical Initial State(e.g. ref. Slotin
experiment, NRX, SL-1, JCO, etc.)
5
Characteristics of a Subcritical Reactor
  • It is sleeping -- i.e. innocent, cool, inactive
  • Detectors are insensitive, and indications of a
    near-to-critical state are not very obvious
  • It is VERY dangerous if it is nearly critical
  • This is the reason for the guaranteed shutdown
    state
  • This is the reason for discouraging fuelling
    during shutdown
  • This is the reason for requiring poised safety
    systems during shutdown conditions

6
The Louis Slotin Experiment
  • At Los Alamos, they called it tickling the
    dragons tail.
  • Louis (from Winnipeg) had done this experiment
    many times before.
  • On May 21, 1946 he made a small mistake -- a
    screwdriver slipped
  • Things went wrong -- and he died nine days later.
  • SEE THE DEMONSTRATION
  • This provides LESSON 2 in reactor safety - what
    is it?
  • Technical lesson - maintain control at all times
    --and backups are good.
  • Human lesson - we are at least half of the
    problem.

7
Re-Enactment of Slotin Experiment
8
National Research Experimental -- NRXFirst
critical July 22, 1947
9
NRX Elevation View Channel X-Section
10
The NRX AccidentChalk River, Ontario, December
12, 1952
  • A reactivity accident occurred during reactor
    startup
  • What went wrong, and why? Compare different
    accounts.
  • What can we learn?
  • What lessons from this event are still
    remembered in todays safety procedures?

11
NRX Accident Sequence -1
12
NRX Accident Sequence - 2
13
NRX Accident Sequence - 3
14
NRX Accident Sequence - 4
  • Cooling flow to experimental rods reduced one
    was air cooled
  • Rods raised earlier in error did not drop when
    error was corrected
  • Reactivity reached 6 mk. positive due to
    removal of safeguard
  • bank power reached 100kW in 20 sec. and 17 MW
    at 30 sec.
  • Voiding of low-flow channels suddenly added
    another 2.5 mk
  • Moderator dump started at 45 sec.
  • Peak power 80-90 MW at 49 sec. Rapidly
    decreased to low level
  • at 70 sec.

15
NRX Human Errors
16
NRX Human Errors (Continued)
17
NRX -- Consequence
  • Several fuel channels damaged
  • Some fuel melting
  • Heavy contamination in the building
  • No worker injuries
  • No significant public dose
  • Calandria removed, buried, replaced
  • After refurbishment, NRX operated until April 08,
    1994

18
NRX -- Lessons Learned
  • Safeguard bank -- to be poised (ready to
    operate) at all times
  • Loss of confidence in rods
  • Large clearances, simple design, fail-safe
  • Separation of control safety systems
  • Eventually, redundant shutdown systems

19
The SL-1 AccidentNational Reactor Testing
Station, Idaho, January 3, 1961
  • Reactivity accident from subcritical conditions.
    Reactor was intended to supply electricity and
    space heating for remote US Army bases, at a
    thermal power of 3 MW.
  • Peak thermal power during transient was 10,000
    MW, energy release was 130 MW.s.
  • First indication of trouble came from personnel
    gamma monitors, 1.5 km
  • Three operators were killed by the explosion
  • What went wrong, and why? What can we learn?
    What do we remember about the accident?

20
SL-1 General LayoutUS Army developed this
concept electricity and heating at remote sites
Why not use the USN reactor design?
Reactor
Operator
21
SL-1Elevation View
22
SL-1 Core PlanCore was 90 cm square, 35 cm high
23
SL-1 Accident Chronology
24
SL-1 Lessons Learned
  • Single rod rule
  • Limits on rod withdrawal speed
  • Inherent fast feedback required in reactors where
    rapid positive insertion is possible
  • Human factors / maintenance

25
JCO Uranium Processing Plant, Tokai,
JapanSeptember 30, 1999
  • Information at ltwww.inea.org.brgt - Newsletter
    Publications - Consequences and Causes.
  • Workers were preparing batches of uranyl nitrate
    solution in a tank, and grossly exceeded the
    amount of uranium allowed in the tank at one
    time.
  • The tank solution went super-critical. One
    worker died.
  • Investigate this accident

26
JCO Processes
Operations became progressively more lax over a
period of years. Criticality was reached in the
precipitation tank - overloaded. Rapid pulse
followed by slow reaction - for 20
hours Criticality terminated by draining cooling
water jacket, to reduce neutron reflection Total
fissions 2.5 x 10E18, or 100 MWsec
27
JCO Accident Causes ad Remedies
  • Direct cause - addition of Uranyl nitrate in the
    amount of 16.6 kg into a tank not designed to
    prevent criticality
  • Contributors (in brief)
  • Inappropriate procedure-batch was too large
  • Operators performed operations exceeding batch
    limit of 2.4 kgU
  • Tech management failed to provide or enforce
    proper procedures
  • Company did not enforce special control measures
    in this (rare) operation
  • Licensing did not review the operations in detail
    - as necessary in criticality cases
  • Safety regulations did not specify periodic
    inspection of operations
  • Recommendations of this review mainly
    concentrated on strenthening of the regulations,
    enforcement, and training.

28
Eight Antinomies(Conclusions of the Chairman,
JCO Accident Investigation Committee)
  • If safety increases, efficiency decreases
  • If regulations are reinforced, creativity is
    lost
  • If surveillance is reinforced, spirit declines
  • If manuals are introduced, self-management is
    lost
  • If fool-proof measures are implemented, the level
    of skills decreases
  • If responsibilities are centered on a key person,
    the group loses concentricity
  • If responsibilities are too strict, cover-ups
    result
  • If information disclosure is promoted, situation
    becomes too conservative.

29
Central Finding and ConclusionJCO Committee
Chairman
  • AUTHORITY AND RESPONSIBILITY WERE NOT PROPERLY
    ASSIGNED
  • CLEAR ALLOCATION OF AUTHORITY AND CORRESPONDING
    RESPONSIBILITY WITHIN MANAGEMENT STRUCTURES IS
    ESSENTIAL TO ACHIEVEMENT OF SAFE OPERATIONS OF
    THE NUCLEAR INDUSTRY

30
Memory Aid for Safety Managers The Organization
Tree -- from Masao Nozawa
  • If you work near the trunk of the tree you must
    be strong -- flexible, but not too flexible.
  • If you work near the trunk of the tree you must
    be aware of the organizations roots and the
    sources of its strength and needs of the whole
    tree.
  • If your job is to support the tree as staff you
    must accept this as a service role.
  • If you work part way up the tree you must be
    aware of your duty to support the branches above
    and to carry out the policies given from below
  • If you work near the top of the tree you must be
    aware of your duty to to grow, and of your
    inter-dependence with those below you in the tree.

31
Close Call -- Zero Power Reactor 3National
Reactor Testing Station, Idaho, 1964
  • Critical assembly experiments for US fast reactor
    program
  • One-half of ZPR 3 slid on a horizontal track, to
    ensure that it remained subcritical during
    loading. Criticality was achieved by moving two
    halves of reactor together slowly, then
    withdrawing safety rods
  • Shutdown via fast-acting rods (poised during
    loading).
  • Independent shutdown action via large scram
    motor mounted on the movable track.
  • Motor was 3-phase, and it was powered from site
    power lines -- these were long. Many other
    intermittent loads on these lines. Phase
    reversal was a common transient condition.
  • If phase-reversal had occurred coincident with a
    scram demand, the reactor halves would have
    been slammed TOGETHER rather than being
    separated.
  • Had that happened this lecture would have been
    presented by someone else. What was the combined
    probability?
Write a Comment
User Comments (0)
About PowerShow.com