Process Topsides Piping - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Process Topsides Piping

Description:

150,000 BBl / Day FPSO. Onshore hook up / commissioning of 26 modules. ... Labor supplied was analyzed at 14% less due to integrated teams. ... – PowerPoint PPT presentation

Number of Views:596
Avg rating:3.0/5.0
Slides: 13
Provided by: c4communic
Category:

less

Transcript and Presenter's Notes

Title: Process Topsides Piping


1
(No Transcript)
2
Process Pipeline Markets
Subsea Pipelines
Process Topsides Piping
Inspect, Clean, Dry, Test, Run, Leak Free Every
phase of the project lifecycle
3
Process Services
  • Hydrotesting
  • HP Water Jetting
  • Water / Air flushing
  • Chemical Cleaning
  • Oil Flushing
  • Bolt tensioning / torquing
  • Valve Testing
  • Air / Nitrogen / Vacuum Drying
  • Leak Detection
  • Temporary Fuel Gas
  • Compressor run trials
  • Refrigerant Handling
  • Nitrogen Foam Inerting
  • Piping preservation
  • Pipefreezing

4
BJ PPS Integrated Concept
5
Benefits of Integration
By focusing on the four key project areas, we
will deliver the most cost effective service to
the project
6
Case Study - Schiehallion FPSO
  • 150,000 BBl / Day FPSO
  • Onshore hook up / commissioning of 26 modules.
  • June 1997 - January 1998 - 36 weeks
  • Flushing
  • H.P Jetting
  • Hydrotesting
  • Bolt tensioning / torquing
  • Machining
  • Oil flushing
  • Chemical cleaning
  • PSV Testing
  • Gauge pigging
  • Leak Testing
  • Compressor runs
  • Bolt Preservation
  • 291 Hydrotest packs
  • 250,000 stud bolts torqued / tensioned
  • 62100 manhours completed

7
Schiehallion FPSO
Cross Trained Personnel
Labour Pool
8
Schiehallion FPSO - Key Benefits
  • Contracts to tender / administer reduced from 5
    to 1 (Alliance)
  • 15 ITT/RFQs to 3
  • Leak testing / compressor run trials started at
    45 complete in overall program
  • Less than 0.1 downtime on 62,100 manhours
  • Zero lost-time incidents occurring from injury to
    persons or property.
  • Zero NCRs in internal quality audits.

9
Case Study - Bleoholm FPSO
  • 50 000 BPD oil gas separation
  • 12 000 tonnes topsides process, 27 packages
  • 28 weeks duration
  • 6000 Isometrics, 110 P IDs
  • Hydrotest engineering
  • Hydrotest Planning tracking
  • Flushing
  • H.P Jetting
  • Hydrotesting
  • Bolt tensioning / torquing
  • Leak Testing
  • Compressor runs
  • 690 Hydrotests, 320 flushes, 347 visuals
  • 80,000 manhours completed
  • Maximum P.O.B 85

10
Bleoholm FPSO
Cross Trained Personnel
Labour Pool
11
Bleoholm FPSO - Key Benefits
  • Contracts to tender / administer reduced from 4
    to 1.
  • 12 RFQs to 3
  • Planning tracking identified an 8000 manhour peak
    in time to mobilize the resources required to
    complete inside timeframe.
  • Labor supplied was analyzed at 14 less due to
    integrated teams.
  • We supplied 12,000 manhours to the customer to
    complete his work.
  • Large crew sizes justified 2 full time safety
    reps to interface with construction.

12
Why Use BJ PPS ?
  • Thoroughly understand Precommissioning to
    Mechanical completion Phase of the project
    lifecycle.
  • We know what it will take to complete on time and
    interface with the completions / commissioning
    group
  • targeting the critical path activities
  • executing the services in the chain
  • We have an extensive track record of
    Integrating our management / engineering staff.
  • We are flexible enough and experienced enough to
    take on as much or as little as you may require.