Title: Valhall Redevelopment Project VRD Contractor Engagement Road Shows
1Valhall Redevelopment Project (VRD)Contractor
Engagement Road Shows
2Contents
- BP Norge Introduction
- VRD Project Introduction
- VRD Project Contracting Strategy
- Wood Group Overview
- Achilles Joint Qualification System
3BP Norge Introduction
4Key facts about the BP Group
- 103 000 employees in more than 100 countries
- Production 4,1 million boe/d) per 2005 (2Q 05)
- Group turn over 285,059 million
- Reserves replacement ratio over 100 every year
since 1994 - Many new developments across the world
2004
5Key facts about BP in Norway
- 552 employees
- Production 84000 boe/d , BP net
- Turn over NOK. 7.3 billion ( 1.2 billion)
- Profit NOK. 1.3 billion ( 0,2 billion)
Oslo
Stavanger
- 56 staff
- Turn over NOK 226 million
All figures by end of 2004
6Around NOK 25 billion to beinvested in Norway
7Our interests offshore Norway
- Partner in 18 licenses
- Operator of 12 of these
- Producing fields operated by BP Ula,Tambar,
Valhall,Hod - Partner in the Draugen field
core areas
8BP operated fields
Valhall
Hod
Tambar
Ula
9VRD Project HSE QDag Løfsgaard
loefsgd_at_bp.com 47 52 01 40 90
10VRD Q HSEGoals
- No injuries
- Risk of injuries and major accidents are
controlled and minimized in all phases of the
Project - A best possible working environment minimizing
platform personnel exposure to working
environment risks - Minimum discharges to air and sea during normal
operation
11VRD Q HSEWhat do we look for?
- Clear expectations set to everyone involved at
all levels of the organization - Focus on technical integrity and quality in all
phases of the Project - Implemented systems for hazard identification and
risk management - Willingness to share information about incidents
- Lessons learned form incidents are actively used
to improve performance - A culture where safety interventions are valued
12VRD Q HSEHigh Level Requirements
- General
- Norwegian regulations and Norsok are minimum
requirements - HSE
- Strong focus on HSE Performance
- Openness to HSE initiatives from BP
- HSE Evaluation of Contractors (Norsok S-006)
- Quality
- Quality Assurance Systems according to ISO 9001
13VRD Project TechnicalDag Løfsgaard
loefsgd_at_bp.com 47 52 01 40 90
14Valhall Subsidence
5.3m subsidence Air Gap!
15Valhall Redevelopment VRD
16VRD Selected Concept New Production Hotel (PH)
New Facility Design Life 40 years Hotel 150
single bed cabins Oil production capacity 150
mbopd Gas handling capacity 5 million
Sm³/day Total liquid capacity 250 mbpd (oil
water) Design (Dry) Weight 11,000 tonnes
(topsides process/utility) 1,700 tonnes
(hotel module) 5,000 tonnes
(jacket) Power from Shore 292
km DC cable from Southern Norway Oil
Export Provision for future offshore
loading/EOR
17VRD Topsides Equipment Primary Attributes
- Large single train Oil Gas processing system
- process conditions are well understood (20 years
operation) - NGL recovery export
- Solids recovery, processing injection
- Utility systems
- No Drilling Unit or Offshore Power Generation
- Utilisation of retained equipment on IP/WP
- - produced water clean up - water injection
system - - air compressors - seawater treatment
- - gas metering
18VRD - Install a power from shore solution
- System to deliver
- 78 MW on the platform to allow delivery of 150mbd
/ 175mmscf/d capacity, offshore loading and EOR - Main Components
- Onshore Power Supply connect to national power
grid - HVDC Converter stations onshore and offshore
ABB supply - HVDC Power cable (plus Fiber Optic Cable)
Nexans supply - Platform HVDC converter station module
fabrication contractor - TBD
19VRD Fabrication Strategy
- Complete skid design before fabrication begins
- Skid based methodology 30 to 50 skids
- High proportion of bulks in skids, from a common
source - Skids may range in size from 5 tonnes to 800
tonnes - Main fabricator erects steel integrates skids
- All facilities will meet or exceed NORSOK
standards
20VRD Topsides Execution Methodology
-
- What exactly is a Skidor Pre-Assembled Unit
(PAU)?
21Test Separator Skid Skid Base
22Test Separator Skid Test Separator Installed
23Test Separator Skid Upper Level and Heater
Installed
24Test Separator Skid Grating and Pipe Supports
Installed
25Test Separator Skid Piping Installed
26Test Separator Skid Instrument/Electrical
Installed
27Test Separator Skid Complete
28Topsides Execution Methodology
-
- How is the deck constructed and the Skids
integrated?
29Cellar Deck
Cellar Deck Pancake
30Cellar Deck with Single Skid Added
31Cellar Deck with Multiple Skids Added
32Completed Deck with Power Module LQ
Power Module
Bridges to/from IP
33VRD Contracting StrategyGraeme Hall
hallgr_at_bp.com 47 52 01 33 70
34VRD Design and Execute Strategy
- Template design and skid package build philosophy
imported from GoM. - Strategy used successfully on BP Clair.
- Design engineering in one place.
- Designs to 100 AFC status.
- Fabricators and suppliers focus on build, test
and deliver.
35VRD Contract Strategy 1
- Safe, intelligent, maintenance free and remotely
operated facility - FEED contract with optional Engineering
Procurement and Construction Management (EPcma)
services. - Control and Power from Shore providers integrated
into FEED team - Contract for control/SAS system awarded in
parallel to the FEED contract - Engineering contract includes procurement of
critical equipment, integration with existing
facilities and provision of construction
management services - Procurement of critical equipment will be to BP
standards and Company provided to fabricators
36VRD Contract Strategy 2
- Fabrication contracts will be awarded for
- Jacket
- Process Utility Skid Packages
- Deck including installation and hook-up of skids
- Living Quarters
- PFS Module
- Separate contracts for
- Brown-field modifications to existing facilities
- Offshore installation of jacket, topsides and
living quarters - Tie-in of subsea pipelines
- BP will be manage commissioning and start up
activities with resources provided by onshore
deck fabricator engineering contractor - More than 130 contracts in total
- ITTs issued from Houston Stavanger
37How to become a supplier to BP Norway
- Identify and connect with customer (BP end user)
- Registered in Achilles as approved supplier with
updated info - HSE - Self assesment (NORSOK S-006)
- Products/Services
- Contact details
- Meet minimum HSEQ Req.
- HSEQ System and Processes
- HSE Performance
- HSE matters for allocation of work!
We will not find you if your capabilities are not
registered!
38What we look for in a supplier
- Leadership in HSE
. - Documented Track Record of Capabilities
- The right Products / Services
- Life Cycle Costs 40 year field life
- Execution Ability
- Quality and delivery of vendor data
- Desired Attributes
- Better use of technology
- Improved Ops Efficiency
- Value Creation
- Innovative, Creative, Proactive
- Willing to Share Ideas
39Valhall Redevelopment Prelim Schedule
40Wood Group PresentationGordon Stirling
41Achilles Joint Qualification SystemAtle Gjertsen
atle.gjertsen_at_achilles.com 47 51 71 86 66
42Who and Where?
- www.bp.no
- .
- Ewan Drummond Project Director
- Chris Ruthven Topsides Manager
- Terje Iversen Operations Manager
- Graeme Hall Project Services Manager
- Simon Bateson Snr Supply Chain Analyst
- Judith Emms Snr Supply Chain Analyst
- Mark Frary Mustang Procurement Manager
- Gloria Thorarensen Project Administration
- Gorden Stirling Wood Group
- Atle Gjertsen Achilles
- Heather Jack
- Terje Aasen