Optimisation
  • ARODG Seminars
  • Glasgow London
  • February 2007

2
Content
  • Outline of concept
  • What Does Optimisation Address
  • Optimisation Issues
  • Possible options
  • Process Going Forward

3
Optimisation - Concept
  • Maximise use of GB Transmission System
  • Facilitate Competition
  • Due regard to potential increased constraint
    costs
  • Economic coordinated GB Transmission System
  • Solution within existing framework

4
Optimisation Addresses
  • Resolving referred Offers
  • Confirmation of contracted background
  • Review of required reinforcements
  • Delaying works for consents (where relevant)
  • Scheduling of works
  • Backfilling any spaces
  • Moving Users forward
  • Moving Users backwards

5
Optimisation Issues
  • User Consent mismatch with contract
  • Increase in small generation
  • GB System Demand lower than Scottish Peak demand
  • Lack of space ahead of reinforcements
  • Limited Users withdrawing/reducing
  • Users uncertain over potential to move forward
  • 2016 Offers
  • Optimum method to move users onto different works
  • NGET Licence Condition C8 back of queue
    uncertainty
  • Limited market information published
  • Uncertainty over TEC trading, capacity delaying

6
Optimisation Options
  • Restricting Users moving backwards
  • No limit
  • Within backstop date
  • 6 months
  • Moving Users Forward
  • Managed based approach (sequential allocation)
  • Market based approach (willingness to pay)
  • Limiting changes to amount consented (or applied
    for)
  • Removing TEC/Capacity if not meeting milestones
  • More information published

7
Optimisation Going forward
  • Open Letter February
  • Review Code/Framework implications
  • Discussions with Authority
  • Responses Seminar March
  • Earliest spaces identified - May