Title: Section Objectives
1- Section Objectives
- After completing this section, you should be able
to - 1. Describe the conditions under which MRP is
most appropriate. - 2. Describe the inputs, outputs and nature of
MRP processing. - 3. Explain how requirements in a master schedule
are translated into material requirements for
lower level items. - 4. Discuss possible uses of safety stock and
safety time. - 5. Explain how an MRP system is useful in
capacity requirements planning. - 6. Outline benefits and difficulties of MRP.
- 7. Describe MRP II and how it relates to MRP.
2- MRP Whazzit
- a computer-based information system designed to
handle ordering and scheduling of of
dependent-demand inventories (i.e. raw materials,
component parts and subassemblies). - MRP Inputs
- Master Production Schedule (MPS) Based on
customers orders and demand forecasts, the MPS
details exactly what end products must be
manufactured or assembled, when they must be
manufactured and what quantities are needed. - Bill of Materials File (BOM) Specifies amount
of raw materials, components and subassemblies
needed to manufacture or assemble the end
product. Tells both the requirements and when
they will be needed. - Inventory Status File Maintains inventory
records so that the company may subtract the
amount on hand from the gross requirements, thus
identifying net requirements at any time. - MRP Program Explodes end product demand into
gross requirements for individual parts and other
materials. Then the program calculates net
requirements based on the inventory status file
and places orders for the inputs necessary to the
production / assembly process.
3MRP Inputs
MRP Processing
MRP Outputs
Changes
Order releases
Master production schedule
Orders Forecast
Design Changes
Receipts Withdrawals
Planned-order schedules
Primary Reports
Exception reports
MRP Computer Program
Bill-of- materials file
Planning reports
Performance- control reports
Secondary Reports
Inventory status file
Inventory transaction
4- MRP Outputs
- Outputs and Reports Records and information
related to - (i) quantities the company should order and when
- (ii) any need to expedite or reschedule arrival
dates or needed product quantities - (iii) cancelled need for product
- (iv) MRP system status
5Master Schedule
A master schedule for end item X
Week Number
Item X
1
2
3
4
5
6
7
8
Quantity
100
150
Planning horizon for cumulative lead time
Assembly
Subassembly
Fabrication
Procurement
1
2
3
4
5
6
7
8
9
10
6 Bill of Materials File
Level
X
0
B
C
1
(2)
D
E
E
F
2
(3)
(2)
(2)
E
(4)
3
Product structure tree for end item X
7- Using the information presented in the product
structure tree - a. Determine the quantities of B, C, D, E and F
needed to assemble one X. - b. Determine the quantities of these components
necessary to assemble 200 Xs. - Solution to a b
- Quantity Quantity
- to make to make
- Component 1 X 200 X
- B.....2 Bs per X 2 400
- D.....3 Ds per B 2 Bs per X 6
1200 - E.....1 E per B 2 Bs per X 2 400
- E.....4 Es per D 3 Ds per B 2 Bs per X
24 4800 - C.....1 C per X 1 200
- E.....2 Es per C 1C per X 2 400
- F.....2 Fs per C 1 C per X 2 400
8- Inventory Records File
- Stores information on the status of each item by
time period. Includes - 1. Gross Requirements. The total expected
demand for an item or raw material during each
time period. - 2. Scheduled Receipts. Open orders scheduled to
arrive from vendors or elsewhere. - Projected on Hand. Expected amount of inventory
that will be on hand at the beginning of each
time period. - scheduled receipts available from last
period. - 4. Supplier. The name(s) and address(es) of the
items supplier(s). - 5. Lead Time. The average length of time, in
days or weeks, between placing and receiving an
order from the supplier. - 6. Lot Size. Standard order size. This may be
determined by techniques such as lot-for-lot
ordering, EOQ, part period balancing, etc.
9MRP Processing
- MRP processing involves taking end item
requirements and exploding them into
time-phased requirements for assemblies, parts
and raw materials.
Procurement of RM D
Order point
Fabrication of part E
Subassembly A
Procurement of RM F
Final assembly and inspection
Procurement of part C
Subassembly B
Procurement of RM I
Fabrication of part G
1
2
3
4
5
6
7
8
9
10
11
Week number
Available for delivery
10MRP Processing
1
2
3
4
5
6
7
8
Week number
Item
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order receipts
Planned-order releases
11- MRP Processing Problem Illustration
- A firm that produces wood shutters and bookcases
has received two orders for shutters one for 100
shutters and one for 150 shutters. The 100-unit
order is due at the start of week 4 of the
current schedule, and the 150-unit order is due
for delivery at the start of week 8. - Each shutter consists of four slated wood
sections and two frames. The wood sections are
made by the firm, and fabrication takes one week.
The frames are ordered, and lead time is two
weeks. There is a scheduled receipt of 70 wood
sections in week 1 (i.e. at the beginning of week
1). - Determine the size and timing of planned-order
releases necessary to meet delivery requirements
under each of the following conditions - 1. Lot-for-lot ordering (i.e. order size equal
to net requirements). - 2. Lot-size ordering with a lot size of 320
units for frames and 70 units for wood
sections.
12- MRP Processing Problem Solution - Lot-for-Lot
Ordering
1. Develop a Master Schedule
Week number
1
2
3
4
5
6
7
8
Quantity
100
150
2. Develop a Product Tree Structure
Shutter
Frames (2)
Wood sections (4)
3. Develop an Assembly Time Chart
Make wood sections
Make wood sections
Assemble shutters
Assemble shutters
Procure frames
Procure frames
1
2
3
4
5
6
7
8
13Week number
1
2
3
4
5
6
7
8
4. Master schedule for shutters
100
150
Gross requirements
Shutters LT 1 week
100
150
Scheduled receipts
Projected on hand
Net requirements
100
150
Planned-order receipts
100
150
Planned-order releases
100
150
times 2
times 2
Frames LT 2 week
Gross requirements
200
300
Scheduled receipts
Projected on hand
Net requirements
200
300
Planned-order receipts
200
300
Planned-order releases
200
300
14Week number
1
2
3
4
5
6
7
8
4. Master schedule for shutters
100
150
Gross requirements
Shutters LT 1 week
100
150
Scheduled receipts
Projected on hand
Net requirements
100
150
Planned-order receipts
100
150
Planned-order releases
100
150
times 4
times 4
Wood sections LT 1 week
Gross requirements
400
600
Scheduled receipts
70
Projected on hand
70
70
70
Net requirements
330
600
Planned-order receipts
330
600
Planned-order releases
330
600
15- MRP Processing Problem Solution - Lot Size
Ordering
1. Develop a Master Schedule
Week number
1
2
3
4
5
6
7
8
Quantity
100
150
2. Develop a Product Tree Structure
Shutter
Frames (2)
Wood sections (4)
3. Develop an Assembly Time Chart
Make wood sections
Make wood sections
Assemble shutters
Assemble shutters
Procure frames
Procure frames
1
2
3
4
5
6
7
8
16Week number
1
2
3
4
5
6
7
8
4. Master schedule for shutters
100
150
Gross requirements
Shutters LT 1 week
100
150
Scheduled receipts
Projected on hand
Net requirements
100
150
Planned-order receipts
100
150
Planned-order releases
100
150
times 2
times 2
Frames LT 2 week Lot size 320
Gross requirements
200
300
Scheduled receipts
Projected on hand
120
120
120
120
140
Net requirements
200
180
Planned-order receipts
320
320
Planned-order releases
320
320
17Week number
1
2
3
4
5
6
7
8
4. Master schedule for shutters
100
150
Gross requirements
Shutters LT 1 week
100
150
Scheduled receipts
Projected on hand
Net requirements
100
150
Planned-order receipts
100
150
Planned-order releases
100
150
times 4
times 4
Wood sections LT 1 week Lot size 70
Gross requirements
400
600
Scheduled receipts
70
Projected on hand
70
70
70
20
20
20
20
50
Net requirements
330
580
Planned-order receipts
350
630
Planned-order releases
350
630
18- MRP Outputs
- Primary Reports
- Planned orders - amount and timing of future
orders - Order releases - authorize the execution of
planned orders - Changes to planned orders - changes of due dates
and/or order quantities - Secondary Reports
- Performance-control reports - measure deviation
from plans, including missed deliveries and
stockouts. Provide information that can be used
to assess cost performance. - Planning reports - include purchase commitments
and other data that can be used to assess future
material requirements. Useful in forecasting
future material requirements. - Exception reports - illustrate major
discrepancies such as late and overdue orders,
excessive scrap rates, reporting errors and
requirements for nonexistent parts.
19- Other MRP Issues
- Safety Stock supposedly, safety stock is not
needed because usage quantities can be projected
once the master schedule has been established.
However, bottleneck operations or ones that
produce varying scrap rates can cause shortages
in downstream operations. - MRP systems deal with these problems in several
ways - 1. Identify activities / operations subject to
variability and determine the extent of the
variability. - 2. When lead times are variable, use concept of
safety time - this results in scheduling orders
for arrival or completion sufficiently ahead of
time to eliminate or reduce the chance of having
to wait for these items. - Lot Sizing choosing a lot size to order or for
production. For independent demand items (i.e.
end items), economic order sizes (EOQ) and
economic run sizes are used. For dependent
demand items, demand tends to be more lumpy and
the planning horizon shorter. There are some
models available to assist in planning - 1. Lot-for lot ordering - order or run size for
a period is set equal to demand for that period.
Problems (1) different order sizes prevent
economies associated with a fixed order size
(e.g. standard containers / standardized
procedures) and (2) new setup for each run. - 2. EOQ models - if demand is uniform, this can
minimize order (setup) and carrying costs.
20- 2. EOQ models (continued) - however, the more
lumpy demand is, the less appropriate such an
approach. - 3. Fixed-period ordering - provides coverage for
some predetermined number of periods, where the
number of periods is determined by judgment and
experience. Consider the following - Using a two-period rule, an order size of
120 units would cover the first two periods. The
next two periods would be covered by an order
size of 81 units. However, the demands in
periods 3 and 5 are so small, it would make sense
to combine them both with the 80 units and order
85 units. - 4. Part period model - balances setup and
holding costs. The term, part period, refers to
holding a part or parts over a number of periods.
The economic part period, EPP, can be computed
as the ratio of setup costs to the cost of
holding a unit for one period. The formula for
computing the EPP is - EPP (Setup cost) / (Unit
holding cost per period)
1
2
3
4
5
Period
70
50
1
80
4
Demand
Cumulative Demand
70
120
121
201
205
21- Capacity Requirements Planning (CRP)
- Process of determining short-range capacity
requirements. The necessary inputs include
planned-order releases for MRP, the current shop
load, routing information and job times. Outputs
include load reports for each work centre.
Using MRP to assist in planning
capacity requirements
Develop a tentative master production schedule
Use MRP to simulate material requirements
Revise tentative master production schedule
Convert material requirements to resource
requirements
No
Shop capacity adequate?
Can capacity be changed?
No
Yes
Yes
Develop a tentative master production schedule
Change capacity
22- Capacity Requirements Planning (CRP)
A hypothetical department load report
Load (units)
Capacity
Now in production
Planned order releases
Expected orders
1
2
3
4
5
6
7
8
9
10
11
12
13
Time period
23- Benefits, Requirements and Limitations of MRP
- Benefits
- Low levels of in-process inventories
- Ability to keep track of material requirements
- Ability to evaluate capacity requirements
generated by the master schedule - A means of allocating production time
- Requirements
- Computer and necessary software
- Accurate and up-to-date
- master schedules
- bills of materials
- inventory records
- Integrity of file data
- Limitations
- Recordkeeping deficiencies
- Resistance of supervisory staff
- Time for education, training and convincing of
employees - often a year or more
24- Manufacturing Resource Planning - MRP II
Market demand
Master production schedule
Finance
Manufacturing
Marketing
MRP
Production plan
Capacity requirements planning
Rough-cut capacity planning
Problems?
Yes
Adjust
master schedule
Problems?
Yes
No
Adjust
No
production plan
Requirements schedule
25Enterprise Resource Planning (ERP)
- An extension of the MRP system to tie in
customers and suppliers - Allows automation and integration of many
business processes - Shares common data bases and business practices
- Produces information in real time
- Coordinates business from supplier evaluation to
customer invoicing
- ERP modules include
- Basic MRP
- Finance
- Human resources
- Supply chain management (SCM)
- Customer relationship management (CRM)
26Enterprise Resource Planning (ERP)
- ERP can be highly customized to meet specific
business requirements - ERP systems can be integrated with
- Warehouse management
- Logistics
- Electronic catalogs
- Quality management
- ERP systems have the potential to
- Reduce transaction costs
- Increase the speed and accuracy of information
- Facilitates a strategic emphasis on JIT systems
and integration
27ERP and MRP
28ERP and MRP
29ERP and MRP
Figure 14.11
30ERP and MRP
31Advantages of ERP Systems
- Provides integration of the supply-chain,
production, and administration - Creates commonality of databases
- Can incorporate improved best processes
- Increases communication and collaboration between
business units and sites - Has an off-the-shelf software database
- May provide a strategic advantage
32Disadvantages of ERP Systems
- Is very expensive to purchase and even more so to
customize - Implementation may require major changes in the
company and its processes - Is so complex that many companies cannot adjust
to it - Involves an ongoing, possibly never ending,
process for implementation - Expertise is limited with ongoing staffing
problems
33SAPs ERP Modules
34 A firm that produces electric golf carts has
just received an order for 200 carts, which are
to be ready for delivery at the start of week 8.
Information concerning the product is given
below Parts List Lead Time Quantity on
Hand Electric golf cart 1 week
0 Top 1 week 40
Base 1 week 20 Top
Supports (4) 1 week 200
Cover 1 week 0 Base
Motor 2 weeks 300
Body 3 weeks 50 Seats
(2) 2 weeks 150 Body
Frame 1 week 35
Controls 1 week 0 Wheel
assemblies (4) 1 week 240
Using this information, do each of the
following a. Construct a product tree. b.
Construct an assembly time chart. c. Develop a
material requirements plan that will provide 200
golf carts by week 8, assuming lot-for-lot orderin
g.
Material Requirements Planning - Additional
Illustration 1
35 Refer to illustration 1. Assume there has
been a change in the quantity and timing of
orders for golf carts, which is apparently due to
unusually mild weather. The revised plan calls
for 100 golf carts at the start of week 6, 100 at
the start of week 8 and 100 at the start of week
9. Parts List Lead Time Quantity on
Hand Electric golf cart 1 week
0 Top 1 week 40
Base 1 week 20 Top
Supports (4) 1 week 200
Cover 1 week 0 Base
Motor 2 weeks 300
Body 3 weeks 50 Seats
(2) 2 weeks 150 Body
Frame 1 week 35
Controls 1 week 0
Wheel assemblies (4) 1 week
240 a. Develop a master schedule for this
revised plan. b. Determine the timing and
quantities for orders for tops and bases. c.
Assume now that due to equipment problems,
capacity for assembling bases is 50 units per
week. Revise your material plan for bases to
reflect this, but still meet delivery dates.
Material Requirements Planning - Additional
Illustration 2