Title: Motagua Bridge Project


1
(No Transcript)
2
Motagua Bridge Project
  • Design Selection Construction Process
  • Presented by James Ritter

Bridge over the Rio Grande Motagua near La
Garrucha, Guatemala
3
Motagua Bridge Project
  • Design Selection and Construction Process
  • Project Background
  • Design
  • Alternatives
  • Selection Methodology
  • Construction Process
  • Unique Construction Elements
  • Construction Overview
  • Questions

4
Project Background
  • Project Description
  • Design and construction of a vehicle bridge over
    the Rio Motagua
  • Key Project Partners
  • PAVA Local Guatemalan Non-Profit
  • Marquette University College of Engineering
  • Southminster Presbyterian Church Waukesha, WI
  • Wisconsin Professional Partners Chapter of
    EWB-USA

5
Project Background
  • Project Location
  • On the Rio Grande Motagua near La Garrucha,
    Guatemala

6
Project Background
  • Existing Conditions
  • Confluence of the Rio Motagua and Rio Cujil
  • Exposed bedrock

7
Project Background
  • Existing Conditions
  • The existing bridge construction
  • Historical and sentimental value

8
Design Alternatives
  • Steel Girder Design
  • Five wide flange structural steel girders
  • Located at existing structure
  • Two Span Concrete T-Beam
  • Four concrete girders
  • Located approximately 100 upstream
  • Single-Span Concrete T-Beam
  • Five concrete girders
  • Located at existing structure or directly
    upstream

9
Selection Methodology
  • Steel Girder Design (Located at existing
    structure)
  • Pros
  • Less shoring
  • Shorter construction schedule
  • Cons
  • Extensive demolition of existing structure
  • Unknowns of utilizing portions of the existing
    abutments
  • Sentimental and historical value
  • Beam size
  • Cost
  • Need for hoisting equipment
  • Alternative discarded as impractical cost
    prohibitive

10
Selection Methodology
  • Concrete T-Beam Alternatives
  • Both two span and single span alternatives
    required
  • Extensive formwork and shoring towers
  • Large volumes of concrete to be poured
  • Longer construction schedule
  • Relatively equal cost estimates
  • Similar construction schedules

11
Selection Methodology
  • Two Span Concrete T-Beam Design
  • (Located approximately 100 upstream of existing
    structure)
  • Cons
  • Requires construction of a permanent pier in the
    riverbed
  • Additional formwork and excavation for pier
  • Unknown conditions of riverbed
  • Concerns regarding potential for scour
  • Possibility of changing hydraulic conditions
  • Alternative was eliminated based on concerns
    regarding permanent pier construction.

12
Selection Methodology
  • Selected Design
  • Single-Span Concrete T-Beam
  • (Located directly upstream of existing structure)
  • Lowest Cost
  • No Permanent Pier
  • No Demolition
  • Preserve Existing Structure
  • Hydraulic Conditions Will Remain Unchanged

13
Selection Methodology
  • Selected Design

14
Construction Process
  • Unique Construction Elements
  • Bedrock Excavation
  • Temporary Pier Construction
  • Falsework Trusses

15
Unique Construction Elements
  • Bedrock Excavation

16
Unique Construction Elements
  • Temporary Pier Construction

17
Unique Construction Elements
  • Temporary Pier Construction

18
Unique Construction Elements
  • Falsework Trusses

19
Unique Construction Elements
  • Falsework Trusses

20
Construction Overview
  • Advanced Site Preparation
  • Bedrock excavation
  • Construction of Primary Bridge Structure
  • Two groups of volunteers working with the local
    community
  • 16 days of construction over a three week time
    period
  • Construct footings, abutments, temporary pier
    truss false work structure, beams, and bridge
    deck
  • Finishing Construction
  • Local mason and local community construct wing
    walls and railings, and remove the false work

21
Construction Overview
  • Pre-Construction

22
Construction Overview
  • Pier Island Construction

23
Construction Overview
  • Footing Construction

24
Construction Overview
  • Abutment Pier Construction

25
Construction Overview
  • False Work Construction

26
Construction Overview
  • Beam Construction

27
Construction Overview
  • Deck Construction

28
Construction Overview
  • Deck Construction

29
Construction Overview
  • Finished Bridge

30
Q A
Project Recognition
  • Finalist for the ASCE Outstanding Civil
    Engineering Achievement award.
  • Honors the project that best illustrates superior
    civil engineering skills and represents a
    significant contribution to civil engineering
    progress and society.
  • First university student design project and first
    non-profit organization to receive this national
    nomination.

31
Q A
Q A
  • Questions?

Completed Bridge Painted in Guatemalas National