Title: TOC Overview
1The TOC Centre of Australia
Resource Optimisation Using Critical Chain Buffer
Management in the Multi Project
Environment Presented by David V Hodes
Tel 02 9293
2844 Mobile
0409 789 034
Fax 02 9315 5891
E-Mail david_at_tocca.com.au
www.tocca.com.au
2The TOC Centre of Australia Product Suite
3Critical Chain Projects
4Some Critical Chain Results
- The first time out, we took 26 days out of a
71-day hypermarket re-fit, a 37 increase in
capacity - Matador Refrigeration
- The industry standard to get the plant up and
running to 90 capacity is about 46 months. The
plant was recently completed and is up to 90
production in 13 months - Harris Semiconductor
- We succeeded in dropping our average turnaround
time per aircraft visit from three months to two
weeks - Israel Aircraft Industries
- We originally scheduled to take 13 months to
deliver and the team did it in six months - Honeywell DAS
5The Idea Factory
The Idea
6The Cash Flow Of An Idea
7When Ideas Become Projects
- They are late
- They are over budget
- They frequently change in scope
- Standish Group (www.standishgroup.com )
- 30 of projects canceled before finished
- 75 of completed projects are late
- Average cost overruns are 189
- Average time overruns are 222
8What About The Measures?
- Show me how you measure me, and Ill show you
how I perform. Measure me in an illogical way,
and dont be surprised if I behave illogically - Dr Eli Goldratt
- Is the goal task conformance or project
performance?
9Global Versus Local Optima
- What we want to do is
- Finish projects on time
- Finish projects on budget
- Finish projects on scope
- Shorten project lead times
- Finish more projects
- What we do is
- Manage to finish tasks on time
- Measure resources on utilisation
- Micromanage task flow
- Detailed risk analyses
- Detailed specifications
10Uncertainty Is At The Heart Of The Problem
- Vendor performance is unreliable
- Required tasks are not fully known
- Time to complete any given task varies
- Delivery of needed tools, equipment, and material
is uncertain - Resource availability cannot be guaranteed
11The Issue of Duration Risk
10 probability
50 probability
95 probability
BC is not necessarily 2xAB
Task Duration
12How Risk Relates To How We Are Measured
When we put safety into each task
- Projects seem to be longer than necessary
- Parkinsons Law work expands to fill the time
available - Tasks seldom finish early
- Student syndrome prevails 2/3 of work done
in last 1/3 of time
Activity
Task start
Task end
13The Effect Of Multi-tasking
14Unlevelled Schedule
15Load to Capacity of C
16Critical Chain
- The definition of the Critical Chain is the
longest set of dependent steps, taking task
precedence and resource contention into account.
17Identify Critical Chain
- Load levelled (finite capacity)
- Critical Chain identified
18Managing The Critical Chain
- Shrink the times to 50 probability of completion
aggregate protection in the feeding and project
buffers
19Types Of Buffers
- Project buffer
- Placed before the customer, to protect our
commitment to the customer (the external
constraint) - Feeding buffer
- Placed at each point where non-critical tasks
join the critical chain, to protect against
precedence conflicts on non-critical tasks
20CC, Fb and Pb
- Project buffer task 13
- Feeding buffers tasks 3 and 8
21Critical Ratio
work to completion time to completion (workbuffer
)
22Scenario 1
- Status date represented by red line (8am Sunday
4th November) - Purple bars represent projected start and finish
times - Project buffer (Pb) penetrated
- Feeding buffer (Fb) task 8 penetrated
- Resource buffer (Rb) tasks 5 and10 scheduled
against expected start - Task 4 most critical to work on, as a delay here
causes immediate Pb penetration
23But How Do We Manage The Complex, Multi-Project
Environment?
Project Pipeline
24The Classic Multi-Project
25Classic Multi-Project Statistics
26TOC Critical Chain, Drum and Buffer Management
27TOC Statistics
28Test Results
29So Whats the Choice?
- You manage the constraint
- Or the constraint manages you