TOC Overview - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

TOC Overview

Description:

Resource Optimisation Using Critical Chain Buffer Management in the Multi ... critical chain, to protect against precedence conflicts on non-critical tasks ... – PowerPoint PPT presentation

Number of Views:78
Avg rating:3.0/5.0
Slides: 30
Provided by: davidv70
Category:

less

Transcript and Presenter's Notes

Title: TOC Overview


1
The TOC Centre of Australia
Resource Optimisation Using Critical Chain Buffer
Management in the Multi Project
Environment Presented by David V Hodes
Tel 02 9293
2844 Mobile
0409 789 034
Fax 02 9315 5891
E-Mail david_at_tocca.com.au
www.tocca.com.au
2
The TOC Centre of Australia Product Suite
3
Critical Chain Projects
4
Some Critical Chain Results
  • The first time out, we took 26 days out of a
    71-day hypermarket re-fit, a 37 increase in
    capacity
  • Matador Refrigeration
  • The industry standard to get the plant up and
    running to 90 capacity is about 46 months. The
    plant was recently completed and is up to 90
    production in 13 months
  • Harris Semiconductor
  • We succeeded in dropping our average turnaround
    time per aircraft visit from three months to two
    weeks
  • Israel Aircraft Industries
  • We originally scheduled to take 13 months to
    deliver and the team did it in six months
  • Honeywell DAS

5
The Idea Factory
The Idea
6
The Cash Flow Of An Idea

7
When Ideas Become Projects
  • They are late
  • They are over budget
  • They frequently change in scope
  • Standish Group (www.standishgroup.com )
  • 30 of projects canceled before finished
  • 75 of completed projects are late
  • Average cost overruns are 189
  • Average time overruns are 222

8
What About The Measures?
  • Show me how you measure me, and Ill show you
    how I perform. Measure me in an illogical way,
    and dont be surprised if I behave illogically
  • Dr Eli Goldratt
  • Is the goal task conformance or project
    performance?

9
Global Versus Local Optima
  • What we want to do is
  • Finish projects on time
  • Finish projects on budget
  • Finish projects on scope
  • Shorten project lead times
  • Finish more projects
  • What we do is
  • Manage to finish tasks on time
  • Measure resources on utilisation
  • Micromanage task flow
  • Detailed risk analyses
  • Detailed specifications

10
Uncertainty Is At The Heart Of The Problem
  • Vendor performance is unreliable
  • Required tasks are not fully known
  • Time to complete any given task varies
  • Delivery of needed tools, equipment, and material
    is uncertain
  • Resource availability cannot be guaranteed

11
The Issue of Duration Risk
10 probability
50 probability
95 probability
BC is not necessarily 2xAB
Task Duration
12
How Risk Relates To How We Are Measured
When we put safety into each task
  • Projects seem to be longer than necessary
  • Parkinsons Law work expands to fill the time
    available
  • Tasks seldom finish early
  • Student syndrome prevails 2/3 of work done
    in last 1/3 of time

Activity
Task start
Task end
13
The Effect Of Multi-tasking
14
Unlevelled Schedule
15
Load to Capacity of C
16
Critical Chain
  • The definition of the Critical Chain is the
    longest set of dependent steps, taking task
    precedence and resource contention into account.

17
Identify Critical Chain
  • Load levelled (finite capacity)
  • Critical Chain identified

18
Managing The Critical Chain
  • Shrink the times to 50 probability of completion
    aggregate protection in the feeding and project
    buffers

19
Types Of Buffers
  • Project buffer
  • Placed before the customer, to protect our
    commitment to the customer (the external
    constraint)
  • Feeding buffer
  • Placed at each point where non-critical tasks
    join the critical chain, to protect against
    precedence conflicts on non-critical tasks

20
CC, Fb and Pb
  • Project buffer task 13
  • Feeding buffers tasks 3 and 8

21
Critical Ratio
work to completion time to completion (workbuffer
)
  • Critical Ratio

22
Scenario 1
  • Status date represented by red line (8am Sunday
    4th November)
  • Purple bars represent projected start and finish
    times
  • Project buffer (Pb) penetrated
  • Feeding buffer (Fb) task 8 penetrated
  • Resource buffer (Rb) tasks 5 and10 scheduled
    against expected start
  • Task 4 most critical to work on, as a delay here
    causes immediate Pb penetration

23
But How Do We Manage The Complex, Multi-Project
Environment?
  • Analyse
  • Resource
  • Decide

Project Pipeline
24
The Classic Multi-Project
25
Classic Multi-Project Statistics
26
TOC Critical Chain, Drum and Buffer Management
27
TOC Statistics
28
Test Results
29
So Whats the Choice?
  • You manage the constraint
  • Or the constraint manages you
Write a Comment
User Comments (0)
About PowerShow.com