Title: Critical Chain
1Critical Chain
2PMBOK Definition
- Critical chain
- Schedule network analysis technique that modifies
the schedule to account for limited resources. - Both deterministic and probabilistic techniques
- Build schedule based on non-conservative
estimates for activity durations - Focus is on managing buffer activity durations
instead of slack
3Why do projects fail?
- Goldratts answer
- Parkinsons law work fills the time available
why make added effort to complete a task today
that isnt due until tomorrow. - Self-protection if finish early then will be
given less time next time - Dropped baton early finish may not lead to an
early start of the next activity if people arent
ready to start (or dont received the signal to
start) - Excessive multitasking
- Resource bottlenecks
- Student syndrome delay the start of tasks until
you absolutely have to
4(No Transcript)
5(No Transcript)
6(No Transcript)
7(No Transcript)
8(No Transcript)
9(No Transcript)
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14(No Transcript)
15What is a critical chain?
- Two types of dependencies
- Technical or task dependency
- Resource dependency
- Critical chain is the longest string (or chain)
of dependencies - Critical chain is the resource-constrained
critical path
16Critical chain process
- Aggressively estimate activities with 50/50
chance of completion - Find the critical chain
- Add project buffer at the end of the project.
- Add feeder buffers where non-critical paths merge
with the critical chain - Add resource buffers
- Schedule non-critical activities at their latest
start
17Two types of Resource Buffers
- Resource Time buffer to ensure that the critical
resource is on-call and available when needed - Resource Bottleneck buffer just before any
activities that require the project bottleneck.
18Air Control ProjectCritical Path Network
8-2
19Air Control Project Gantt Chart
8-3
20Air-control project - Resources
Rob
Carly
Ryan
Lauren
Connor
Ryan
Dawn
Kevin
Issues?
21Air Control ProjectSchedule With Resources
Limited
8-5
22Air Control ProjectSchedule With Resources
Limited
8-6
23Air Control ProjectCritical Chain Network
8-8
Aggressively estimate activities with 50/50
chance of completion
24Air Control ProjectCritical Chain Network
8-8
Find the critical chain
25Air Control ProjectCritical Chain Network
8-8
Add project buffer at the end of the project.
26Air Control ProjectCritical Chain Network
8-8
- Add feeder buffers where non-critical paths merge
with the critical chain
27Air Control ProjectCritical Chain Network
8-8
28Air Control ProjectCritical Chain Gantt Chart
8-10
- Schedule non-critical activities at their latest
start