Title: Critical Chain


1
Critical Chain
2
PMBOK Definition
  • Critical chain
  • Schedule network analysis technique that modifies
    the schedule to account for limited resources.
  • Both deterministic and probabilistic techniques
  • Build schedule based on non-conservative
    estimates for activity durations
  • Focus is on managing buffer activity durations
    instead of slack

3
Why do projects fail?
  • Goldratts answer
  • Parkinsons law work fills the time available
    why make added effort to complete a task today
    that isnt due until tomorrow.
  • Self-protection if finish early then will be
    given less time next time
  • Dropped baton early finish may not lead to an
    early start of the next activity if people arent
    ready to start (or dont received the signal to
    start)
  • Excessive multitasking
  • Resource bottlenecks
  • Student syndrome delay the start of tasks until
    you absolutely have to

4
(No Transcript)
5
(No Transcript)
6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
What is a critical chain?
  • Two types of dependencies
  • Technical or task dependency
  • Resource dependency
  • Critical chain is the longest string (or chain)
    of dependencies
  • Critical chain is the resource-constrained
    critical path

16
Critical chain process
  • Aggressively estimate activities with 50/50
    chance of completion
  • Find the critical chain
  • Add project buffer at the end of the project.
  • Add feeder buffers where non-critical paths merge
    with the critical chain
  • Add resource buffers
  • Schedule non-critical activities at their latest
    start

17
Two types of Resource Buffers
  • Resource Time buffer to ensure that the critical
    resource is on-call and available when needed
  • Resource Bottleneck buffer just before any
    activities that require the project bottleneck.

18
Air Control ProjectCritical Path Network
8-2
19
Air Control Project Gantt Chart
8-3
20
Air-control project - Resources
Rob
Carly
Ryan
Lauren
Connor
Ryan
Dawn
Kevin
Issues?
21
Air Control ProjectSchedule With Resources
Limited
8-5
22
Air Control ProjectSchedule With Resources
Limited
8-6
23
Air Control ProjectCritical Chain Network
8-8
Aggressively estimate activities with 50/50
chance of completion
24
Air Control ProjectCritical Chain Network
8-8
Find the critical chain
25
Air Control ProjectCritical Chain Network
8-8
Add project buffer at the end of the project.
26
Air Control ProjectCritical Chain Network
8-8
  • Add feeder buffers where non-critical paths merge
    with the critical chain

27
Air Control ProjectCritical Chain Network
8-8
28
Air Control ProjectCritical Chain Gantt Chart
8-10
  • Schedule non-critical activities at their latest
    start