LLU Update - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

LLU Update

Description:

Openreach makes every effort to ensure the information in this report is ... limited to the London area but will be briefed nationally as best practice ... – PowerPoint PPT presentation

Number of Views:124
Avg rating:3.0/5.0
Slides: 19
Provided by: rossdi
Category:
Tags: llu | briefed | update

less

Transcript and Presenter's Notes

Title: LLU Update


1
LLU Update 3rd December 2008 Peter Boyle
Openreach makes every effort to ensure the
information in this report is accurate at the
time of compilation, however, Openreach does not
represent that it is complete and Communications
Providers should check with Openreach for the
latest available information. Openreach reserves
the right to modify delivery criteria and
delivery dates.
2
PSTN Non Served Premises - NSP
Openreach makes every effort to ensure the
information in this report is accurate at the
time of compilation, however, Openreach does not
represent that it is complete and Communications
Providers should check with Openreach for the
latest available information. Openreach reserves
the right to modify delivery criteria and
delivery dates.
3
Current Issues
  • No lead time is given for PSTN NSP or its
    equivalent WLR3 NSP
  • Line Plant Availability dates can be changed at
    short notice (often on the day quoted)
  • Openreach use own contractors, infrequent updates
    in a timely manner
  • No escalation chain in place during an order or
    after civils have been completed no SLA for
    PSTN delivery
  • No quality audit after civils have been completed
  • No formal reporting process in place when orders
    have been delayed

4
Proposed Initiatives
  • No lead time is given for PSTN NSP or its
    equivalent WLR3 NSP
  • The existing SLA is that Openreach aims to
    provide a Gateway reference number within 3
    working hours for at least 99 of valid orders
    placed within the order placement capacity of the
    Gateway during a calendar month.
  • If a field Site survey is required, Openreach
    aims to complete within 4 Working Days from the
    date the order is Processed. Openreach planners
    will utilise provided contact numbers in order to
    arrange joint meets as required. Site details and
    plans can be exchanged at this stage as EMP
    cannot accept attachments on orders
  • After planning is completed the LPAD is delivered
    to the customer usually within 24hrs or at an
    agreed time during the joint meet

5
Proposed Initiatives
  • Line Plant Availability dates can be changed at
    short notice (often on the day quoted)
  • On large scale NSP roll outs, Openreach has
    trialled the concept of a Contract Liaison
    Manager who engages with our contractors and is a
    single point of contact for the Openreach SMC.
    The concept has proved beneficial and will apply
    on all new contracts
  • This has resulted in more accurate updates to the
    SMC and reduced calls between Openreach, its CP
    and end user
  • With the introduction of a single point of
    contact in the field, future lead times can be
    better provided and also be more timely
  • Communication currently limited to the London
    area but will be briefed nationally as best
    practice is established and larger scale schemes
    come on line Manchester Congestion Charging etc

6
Proposed Initiatives
  • Openreach use own contractors, infrequent updates
    in a timely manner
  • The implementation of a Contract Liaison Manager
    has resolved this issue as the SMC now has a
    single point of contact for issues and updates
  • No escalation chain in place during an order or
    after civils have been completed no SLA for
    PSTN delivery
  • If Openreach fail to pass on an update regarding
    delay to the LPAD then an escalation can be
    raised via the DSO
  • Where delays are due to MBORC then a new LPAD
    will apply
  • Where HS is an issue (trip hazard etc) Openreach
    has a maximum two hour limit to respond. Where
    work is of a reinstatement nature, the current
    lead time for all utilities is six months

7
Proposed Initiatives
  • No quality audit after civils have been completed
  • The Contract Liaison Manager has eliminated the
    practice of a snagging list by CPs as the SMC
    are able to maintain control over outstanding
    work and also bring to light any HS issues
  • No formal reporting process in place when orders
    have been delayed
  • Formal reports can be requested by a CP where
    Openreach has failed a commitment. To request a
    report the CP can utilise the current complaints
    portal on www.openreach.co.uk and this provides
    an audit trail when required as well as providing
    documentation which can be shared with your end
    user

8
www.openreach.co.uk...................
9
www.openreach.co.uk...................
10
Currently Available
  • LLU NSP can also be ordered direct from Openreach
  • Please speak to your Customer Business Manager
    for more details. NSP can be ordered via the
    Service Products arena with an initial survey
    required.

11
LLU SFI Improvement
Openreach makes every effort to ensure the
information in this report is accurate at the
time of compilation, however, Openreach does not
represent that it is complete and Communications
Providers should check with Openreach for the
latest available information. Openreach reserves
the right to modify delivery criteria and
delivery dates.
12
SFI Update
  • Workshop held with Field Operations on 2nd Dec to
    review field procedures and identify best
    practice.
  • Specific areas of improvement identified are in
  • Testing procedures Work has already started to
    simplify "Hawk Pair Quality Testing" which we are
    looking to utilise for SFI
  • Co-op calls
  • Task Closure
  • Clear codes
  • Quality of notes
  • The 2 hour limit
  • Objective is to provide an enhanced and more
    consistent customer experience.

13
Other initiatives that impact SFI
  • Frames Direct Trial for ADSL
  • Fames Direct Product trial scheduled to start in
    25 exchanges in London area, January 2009.
  • Frames engineers will carry out sync tests at the
    frame using testers compatible with ADSL2
  • Frames engineers will also be equipped with
    attenuators that can simulate a long line so
    testing sensitivity of CP equipment to weaker
    signal strengths

14
SDSL / Missed Appointments / Engineer Contact
Openreach makes every effort to ensure the
information in this report is accurate at the
time of compilation, however, Openreach does not
represent that it is complete and Communications
Providers should check with Openreach for the
latest available information. Openreach reserves
the right to modify delivery criteria and
delivery dates.
15
SDSL / SMC Workshop
  • SDSL customer / SMC workshop provisionally
    arranged
  • Date - Thursday 8th January 2009.
  • Venue - 1 Sovereign Street, Leeds LS1 4BT
  • Agenda Items
  • End to end repair process walkthrough.
  • Router types / testing scenarios (CP Driven)
  • Current workaround for SDSL .is it working?
  • Can we do anything different?
  • Visit SMC to view live faults on system
  • Enquiries regarding the workshop should be
    directed to mark.withero_at_openreach.co.uk

16
Missed Appointments Progress Update
  • End date for SMC Appointment Trial for LLU Repair
    is Friday 28th November.
  • RCA during SMC trial has identified a small
    number of failings in Field Engineering/ Work
    Allocation Team Process and Procedures.
  • Data from Trial will be used to support the
    Change Request submitted to align Work Allocation
    Team Process for WLR and LLU Repair.
  • Report on trial to be compiled during December.

17
Engineer Contact Progress Update
  • The following systems have fields for alternative
    contact details that should be used by CPs at
    Order/Fault Entry.
  • EMP Provision for LLU
  • EMP Repair for LLU
  • WLR3 Provision
  • WLR3 Repair
  • eCo Repair (WLR2)
  • If CPs have issues with engineers not responding
    to requests on Engineering Notes or not using the
    alternative contact details to be raised with
    individual Service Managers.

18
Engineer Contact Progress Update
  • The following systems do not have fields for
    alternative contact details that can be used by
    CPs at Order/Fault Entry.
  • SPG WLR2 Provision
  • No plans for system changes or developments for
    WLR2.
  • Current working practice for some CPs is to add
    the contact details in the Non Engineering Notes
    which leads to delays in the issuing of the
    order. In the majority of cases these notes are
    duplicates of the details already submitted in
    the Engineering Notes.
  • Issues with engineers not responding to requests
    on Engineering Notes or not using the alternative
    contact details to be raised with individual
    Service Managers.
Write a Comment
User Comments (0)
About PowerShow.com