Title: LLU Update
1LLU Update 3rd December 2008 Peter Boyle
Openreach makes every effort to ensure the
information in this report is accurate at the
time of compilation, however, Openreach does not
represent that it is complete and Communications
Providers should check with Openreach for the
latest available information. Openreach reserves
the right to modify delivery criteria and
delivery dates.
2PSTN Non Served Premises - NSP
Openreach makes every effort to ensure the
information in this report is accurate at the
time of compilation, however, Openreach does not
represent that it is complete and Communications
Providers should check with Openreach for the
latest available information. Openreach reserves
the right to modify delivery criteria and
delivery dates.
3Current Issues
- No lead time is given for PSTN NSP or its
equivalent WLR3 NSP - Line Plant Availability dates can be changed at
short notice (often on the day quoted) - Openreach use own contractors, infrequent updates
in a timely manner - No escalation chain in place during an order or
after civils have been completed no SLA for
PSTN delivery - No quality audit after civils have been completed
- No formal reporting process in place when orders
have been delayed
4Proposed Initiatives
- No lead time is given for PSTN NSP or its
equivalent WLR3 NSP - The existing SLA is that Openreach aims to
provide a Gateway reference number within 3
working hours for at least 99 of valid orders
placed within the order placement capacity of the
Gateway during a calendar month. - If a field Site survey is required, Openreach
aims to complete within 4 Working Days from the
date the order is Processed. Openreach planners
will utilise provided contact numbers in order to
arrange joint meets as required. Site details and
plans can be exchanged at this stage as EMP
cannot accept attachments on orders - After planning is completed the LPAD is delivered
to the customer usually within 24hrs or at an
agreed time during the joint meet
5 Proposed Initiatives
- Line Plant Availability dates can be changed at
short notice (often on the day quoted) - On large scale NSP roll outs, Openreach has
trialled the concept of a Contract Liaison
Manager who engages with our contractors and is a
single point of contact for the Openreach SMC.
The concept has proved beneficial and will apply
on all new contracts - This has resulted in more accurate updates to the
SMC and reduced calls between Openreach, its CP
and end user - With the introduction of a single point of
contact in the field, future lead times can be
better provided and also be more timely - Communication currently limited to the London
area but will be briefed nationally as best
practice is established and larger scale schemes
come on line Manchester Congestion Charging etc
6Proposed Initiatives
- Openreach use own contractors, infrequent updates
in a timely manner - The implementation of a Contract Liaison Manager
has resolved this issue as the SMC now has a
single point of contact for issues and updates - No escalation chain in place during an order or
after civils have been completed no SLA for
PSTN delivery - If Openreach fail to pass on an update regarding
delay to the LPAD then an escalation can be
raised via the DSO - Where delays are due to MBORC then a new LPAD
will apply - Where HS is an issue (trip hazard etc) Openreach
has a maximum two hour limit to respond. Where
work is of a reinstatement nature, the current
lead time for all utilities is six months
7 Proposed Initiatives
- No quality audit after civils have been completed
- The Contract Liaison Manager has eliminated the
practice of a snagging list by CPs as the SMC
are able to maintain control over outstanding
work and also bring to light any HS issues - No formal reporting process in place when orders
have been delayed - Formal reports can be requested by a CP where
Openreach has failed a commitment. To request a
report the CP can utilise the current complaints
portal on www.openreach.co.uk and this provides
an audit trail when required as well as providing
documentation which can be shared with your end
user
8 www.openreach.co.uk...................
9 www.openreach.co.uk...................
10 Currently Available
- LLU NSP can also be ordered direct from Openreach
- Please speak to your Customer Business Manager
for more details. NSP can be ordered via the
Service Products arena with an initial survey
required.
11LLU SFI Improvement
Openreach makes every effort to ensure the
information in this report is accurate at the
time of compilation, however, Openreach does not
represent that it is complete and Communications
Providers should check with Openreach for the
latest available information. Openreach reserves
the right to modify delivery criteria and
delivery dates.
12SFI Update
- Workshop held with Field Operations on 2nd Dec to
review field procedures and identify best
practice. - Specific areas of improvement identified are in
- Testing procedures Work has already started to
simplify "Hawk Pair Quality Testing" which we are
looking to utilise for SFI - Co-op calls
- Task Closure
- Clear codes
- Quality of notes
- The 2 hour limit
- Objective is to provide an enhanced and more
consistent customer experience.
13Other initiatives that impact SFI
- Frames Direct Trial for ADSL
- Fames Direct Product trial scheduled to start in
25 exchanges in London area, January 2009. - Frames engineers will carry out sync tests at the
frame using testers compatible with ADSL2 - Frames engineers will also be equipped with
attenuators that can simulate a long line so
testing sensitivity of CP equipment to weaker
signal strengths
14SDSL / Missed Appointments / Engineer Contact
Openreach makes every effort to ensure the
information in this report is accurate at the
time of compilation, however, Openreach does not
represent that it is complete and Communications
Providers should check with Openreach for the
latest available information. Openreach reserves
the right to modify delivery criteria and
delivery dates.
15SDSL / SMC Workshop
- SDSL customer / SMC workshop provisionally
arranged - Date - Thursday 8th January 2009.
- Venue - 1 Sovereign Street, Leeds LS1 4BT
- Agenda Items
- End to end repair process walkthrough.
- Router types / testing scenarios (CP Driven)
- Current workaround for SDSL .is it working?
- Can we do anything different?
- Visit SMC to view live faults on system
- Enquiries regarding the workshop should be
directed to mark.withero_at_openreach.co.uk
16Missed Appointments Progress Update
- End date for SMC Appointment Trial for LLU Repair
is Friday 28th November. - RCA during SMC trial has identified a small
number of failings in Field Engineering/ Work
Allocation Team Process and Procedures. - Data from Trial will be used to support the
Change Request submitted to align Work Allocation
Team Process for WLR and LLU Repair. - Report on trial to be compiled during December.
17Engineer Contact Progress Update
- The following systems have fields for alternative
contact details that should be used by CPs at
Order/Fault Entry. - EMP Provision for LLU
- EMP Repair for LLU
- WLR3 Provision
- WLR3 Repair
- eCo Repair (WLR2)
- If CPs have issues with engineers not responding
to requests on Engineering Notes or not using the
alternative contact details to be raised with
individual Service Managers.
18Engineer Contact Progress Update
- The following systems do not have fields for
alternative contact details that can be used by
CPs at Order/Fault Entry. - SPG WLR2 Provision
- No plans for system changes or developments for
WLR2. - Current working practice for some CPs is to add
the contact details in the Non Engineering Notes
which leads to delays in the issuing of the
order. In the majority of cases these notes are
duplicates of the details already submitted in
the Engineering Notes. - Issues with engineers not responding to requests
on Engineering Notes or not using the alternative
contact details to be raised with individual
Service Managers.