The Concept of Incremental Costs

1 / 25
About This Presentation
Title:

The Concept of Incremental Costs

Description:

The Concept of. Incremental Costs. Typical GEF Projects ... (Costs/ emissions during the project life cycle) ... Inseparability of global and domestic benefits ... – PowerPoint PPT presentation

Number of Views:760
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: The Concept of Incremental Costs


1
The Concept of Incremental Costs
2
Typical GEF Projects for Climate Change
  • 1. Energy Efficiency (Operational Prog. 5)
  • Industrial Boilers
  • Agricultural Pump-Sets
  • 2. RETs (Operational Prog. 6)
  • Wind Power, Small Hydro, Biomass Power etc.
  • 3. Low GHG Emitting Technologies (Operational
    Prog. 7)
  • PV for Grid Power
  • Fuel Cells for Mass Transport Vehicles

3
Example Climate Change
  • (Costs/ emissions during the project life cycle)
  • Baseline Coal-fired power station with
    Conventional Boiler (33 efficiency)
  • Cost Rs. 1000 Crore, Carbon 15 million tons
  • Alternative Coal Plant with Super Critical
    Boiler delivering the same electricity
  • Cost Rs. 1100 Crore, Carbon 13.5 million Tons
  • Incremental Cost Rs. 100 Crore
  • N.B. There is an incremental cost but no
    incremental component.

4
Incremental Cost Matrix
IC of mitigation Rs. 100 Crore / 1.5 MtC Rs.
667/ tC
5
Key Elements
  • Additional net costs (not benefits)
  • Always relative to some baseline course of action
  • Costs incurred as a result of redesigning an
    activity, or selecting an alternative activity
  • That alternative can be additional to or
    substitute for the baseline plan

6
Key Elements ..2
  • When
  • the baseline plan is designed to achieve only
    national benefits and
  • redesigning or selecting an alternative techn is
    made to meet a global environmental objective,
  • then
  • the incremental cost is that of achieving the
    resulting global environmental benefits

7
Alternate Baselines
  • Assuming the current trend will continue
    current-mix of techn. is projected to continue
  • ex dependence on kerosene (lighting) or
    fuelwood
  • Consider alternatives (fossil fuels) and project
    Least-cost-mix
  • ex Diesel system (for electricity) or LPG (for
    cooking)
  • Consider no-project scenario situation for the
    project period
  • Marginal cost of technology should be considered

8
Alternative Scenario
  • Select technology (RET or Energy Efficiency)
  • or
  • Select alternate institutional arrangement or
    policy initiative
  • Which provides the same level or scale of benefit
    as the Baseline Scenario (MWh or GJ)
  • Leads to reduction in GHG emission or emissions
    are fully avoided
  • Alternate technology or alternate institutions
    will involve addition cost

9
Example Climate ChangeBiomass Gasifier Based
Power Generation for an Island
  • Baseline A Village is getting electricity from a
    diesel generator of capacity 1 MW
  • Capacity 1 MW
  • Electricity generation 5000 MWh / yr
  • Alternate Scenario Energy-forest and Biomass
    Gasifier
  • Capacity 1 MW
  • Electricity generation 5000 MWh / yr

10
Incremental Cost-Matrix
IC of mitigation Rs. 5 crore / 20000 tC Rs.
250/ tC
11
Example Biological Diversity
  • Identified Ecosystem
  • Priority under Convention on Bio Diversity
  • Threat
  • Cause of Threat is (say) Industrial Pollution
  • Solution is Removal of Cause
  • (Incremental) Cost
  • Extra cost of same industrial activity with
    pollution abated

12
  • Example Continued
  • Domestic Benefits
  • Some fish breeding grounds in the polluted
    wetland
  • Some tourism
  • But, suppose
  • Incremental CostgtgtIncremental Domestic
    Benefit
  • Grant IC

13
  • Example Continued
  • Baseline Development of the industry sector
  • Alternative Continued development, same output,
    but remove the threat
  • Incremental Cost The extra cost of achieving the
    same baseline development
  • IC Cost of A - Cost of B

14
Issues
  • Selection of baseline and its justification
  • Selection of Alternate technology / Scenario
    stating it will not spread if no project
    implemented
  • Adoption of technology or Institutional
    arrangement involves IC which is not provided by
    Govt. / Banks
  • - Risk associated with Alternate Scenario
  • If any additional benefit it will be deducted
    from IC estimation
  • Use appropriate discount rate and estimate life
    cycle cost
  • Sourcing of baseline finance domestically

15
Baseline Course of Action
  • The baseline course of action is what would
    normally occur in the project area in the absence
    of the proposed project.

16
Incremental Cost Approach for Climate Change
Projects
  • If the project falls under OP5 or OP6
  • The life-cycle costs of win-win Energy
    Efficiency and RET alternatives lt baseline costs
  • Incremental costs barrier removal costs
  • If the project falls under OP7
  • The barrier is the cost of the technology itself.
  • Incremental costs alternative technology costs
    - baseline costs

17
Misunderstandings
  • Incrementalism No radical efforts possible
  • Inseparability of global and domestic benefits
  • Impossibility of monetizing environmental
    benefits
  • Small transfers of resources
  • Complex

18
Implementation
  • Issues
  • Conflict of interest (country, co-financiers)
  • Length of communication chain
  • Unpopularity (strategic flaws, difficult concept)
  • Sensitivity of estimates

19
Reaching Agreement on Incremental Cost
  • Choosing the Eligible Objective
  • Negotiating a Reasonable Baseline
  • Estimating the Cost and Ensuring the Equivalence
    of the Proposed Alternative
  • Comparing the Cost Streams
  • Discounting the Future Costs
  • Agree on incremental cost

20
(No Transcript)
21
Incremental Cost Approach for Climate Change
Projects
  • If the project falls under OP5 or OP6
  • The life-cycle costs of win-win efficiency and
    renewable alternatives lt baseline costs
  • Incremental costs barrier-removal costs

22
Incremental Cost Approach for Climate Change
Projects
  • If the project falls under OP7
  • The barrier is the cost of the technology itself.
  • Incremental costs alternative technology costs
    - baseline costs

23
The utility of the incremental cost approach
  • Summary of Approach

24
HISTORY
  • Cost Accounting
  • Incremental cash flow analysis
  • Project Economics
  • Incremental benefits gt incremental costs
  • Global Environment
  • London Amendments to Montreal Protocol (1990)
  • FCCC CBD GEF
  • Here to stay

25
MOTIVATIONS
  • Complementarity
  • Make a difference
  • Relieve the added burden on project hosts
  • Obtain replenishment
  • Project Selection
  • Developmental expenditure
  • Global environment protection
Write a Comment
User Comments (0)