Specifications for Bid Submission - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Specifications for Bid Submission

Description:

This Presentation Is Not For You If: ... You are unconcerned with liability. You like doing things multiple times. You are unconcerned with system performance. ... – PowerPoint PPT presentation

Number of Views:55
Avg rating:3.0/5.0
Slides: 33
Provided by: jeremy122
Category:

less

Transcript and Presenter's Notes

Title: Specifications for Bid Submission


1
Specifications for Bid Submission
  • Jeremy D. Ruck, Senior Engineer
  • D.L. Markley Associates, Inc.
  • 2104 West Moss Ave.
  • Peoria, IL 61604
  • (309) 673-7511
  • jdr_at_dlmarkley.com

2
This Presentation Is Not For You If
  • You have an unlimited budget
  • You are unconcerned with liability.
  • You like doing things multiple times.
  • You are unconcerned with system performance.
  • You are convinced that everybody else has your
    best interests in mind.
  • Failure is an option.

3
For the Rest of Us
  • Living within a budget is mandatory.
  • Mitigation of liability is crucial.
  • Once is enough.
  • System performance is vital.
  • We are responsible for facility technical
    operations.
  • Failure is not an option.

4
When to Use Specifications
  • Significant capital involved.
  • Substantial technical changes are to be made to a
    facility.
  • Outside vendors, crews, and / or personnel are
    involved in the work.
  • Work involving operational continuity of a
    facility is involved.
  • Project is sent out for bid.
  • Hazardous materials are involved.
  • Concerns exist.

5
Significant Capital Involved
  • A Substantial Portion of Your Equipment Budget is
    to be Spent.
  • A Special Project.
  • May Be Overkill for Specific Purchases Where
    Desired Item is Already Researched or Known.
  • Useful for High-Ticket Items where Multiple
    Vendors are Comparable.
  • Probably not Necessary for Replacement Parts.

6
Substantial Technical Changes
  • One-Stop Shopping System Integrator.
  • Replacement of Tower(s).
  • Replacement of Antenna(s).
  • Replacement of RF System(s).
  • Studio / Facility Construction and/or
    Re-Construction.
  • Any other Technical Change which is out of the
    Ordinary.

7
Outside Vendors / Personnel
  • Tower Crews.
  • Construction Crews.
  • Architects.
  • Consultants.
  • Contractors / Trades.
  • Other Technical Personnel.
  • Typically your Consulting Engineer falls Outside
    of this Category.

8
Operational Continuity
  • Replacement of Tower(s).
  • Replacement of Antenna(s).
  • Replacement of RF System(s).
  • New Tower Construction.
  • New Antenna Construction.
  • New Site Construction.
  • Utility Work.
  • Any other Situation Where the Ability to
    Broadcast is Affected or Hampered.

9
Projects out for Bid
  • May Involve Unfamiliar Suppliers.
  • May Involve Unfamiliar Contractors.
  • May Involve Well-Known Suppliers and/or
    Contractors.
  • Usually is Related to an Important Project.
  • Clearly Details Project Information, Goals, and
    Expectations.
  • Levels Vendor Playing Field.
  • Provides Compliance Mechanism.

10
Hazardous Materials
  • Shift Regulatory Compliance to Contractor.
  • Mitigate Liability of Licensee/Owner.
  • Mitigate YOUR Liability.
  • Promote Safety for All Involved with Project.
  • Reduce Potential Environmental Impact.

11
Existence of Concerns
  • When any Concern Exists which may Potentially
    Affect any Area of Personnel Safety.
  • When any Concern Exists which may Potentially
    Affect the Environment.
  • When any Concern Exists which may Potentially
    Affect the Continuity, Operation, and Liability
    of the Licensee, Station, or Personnel.

12
Applicable Wisdom
  • There are very honest people who do not think
    that they have had a bargain unless they have
    cheated a merchant. Anatole France.
  • Arguments of convenience lack integrity and
    inevitably trip you up. Donald Rumsfeld.
  • Specifications involve three parties. One of
    them is a cheat, and were not sure about the
    other. Don Markley.

13
Elements of Good Specifications
14
Elements of Good Specs
  • Provide Instructions to Bidders
  • List General Conditions.
  • Contractual Financial Conditions.
  • Scope of Work.
  • Individual Sections for Each Major Aspect of the
    Project.
  • Appropriate Drawings and Definitions.

15
Instructions to Bidders
  • Provide General Instructions.
  • State Required Bidder Qualifications.
  • Describe Examination Procedures.
  • Notes Concerning Bid Forms.
  • Dates for Bid Submission.
  • Bid Modification Procedures.
  • Bid Opening Information.
  • Award of Contract.

16
General Conditions
  • Project Related Definitions. - Specific
    definitions for all important terms used in
    specifications.
  • Preliminary Matters. - These are matters to be
    addressed before work begins. This includes
    further information about award process,
    contracts, insurance considerations,
    sub-contractor qualifications, and any other
    items relevant to the specific project requiring
    clarification.

17
General Conditions
  • Specific Tabulation of Bonds Required. Includes
    any bid, performance, and contract bonds.
  • Specific Tabulation of Insurance Requirements.
    Details concerning the amount of coverage
    required, and lists co-insured requirements for
    project.
  • Responsibilities of the Contractor, Engineer, and
    Owner.

18
General Conditions
  • Change Order Procedure.
  • Warranties, Tests, and Remediation of Defects.
  • Provisions for Default of Contract.
  • Publicity Concerns.
  • Equal Employment Opportunity Concerns.
  • Workplace Hazards, Safety, and Training.
  • Other General Items.

19
Financial Considerations
  • Contract Issuance. Procedures for awarding a
    contract and initial financial issues including
    bond submission and proof of insurance.
  • Subsequent Payments. Describes schedule of
    payments including initial payments, recurring
    payments, and final payment.
  • Release of Bonds and Security Payments.

20
Scope of Work
  • General Information Concerning the Scope of the
    Project.
  • Re-iteration of Regulatory Compliance
    Requirement. Caution that any act by the
    contractor which causes loss of zoning, funding,
    or permits will forfeit bonds.
  • Relevance of Bid Exceptions. Exceptions
    pertinent to financial considerations and scope
    of work are not permitted.

21
Scope of Work
  • Acceptability of Equipment. Typically only new
    equipment is acceptable.
  • Schedule of Work. Detail start and finish times
    of the project.
  • Liquidated Damages. Damages incurred by
    contractor for failure to complete on time. This
    may be crucial for new construction to meet
    permit requirements.

22
Individual Sections
  • Specify Pertinent Portion of Project.
  • Specify Site Location. A physical address as
    well as geographic coordinates are sufficient.
  • Site Preparation Requirements. Including
    clearing, grading, surveying, etc.
  • Equipment Requirements. Here we need to be
    specific but still retain generality.

23
Specificity/Generality Example
  • Three self-supporting towers identical in nature
    of a height of 167.4 feet above base insulator.
    Towers to comply with EIA/TIA-222-F or its
    successor, whichever is more current at time of
    bid preparation.
  • Three self-supporting towers identical in nature
    of a height of 167.4 feet. Face width at base to
    be 15 feet. Towers to comply with EIA/TIA-222-F
    or most current successor. A450 bolts to be used
    between sections. Base piers to be 3 feet
    square. Depth of base piers not to exceed 8 feet.

24
Individual Sections
  • Specific Installation Requirements. Layout
    specific concerns. AM arrays will have to be
    constructed differently than a non-AM tower for
    example. This portion should also require the
    contractor to provide all necessary items even if
    not specifically stated in specifications.

25
Individual Sections
  • Structural Requirements. Once again be specific
    yet general. Allow the contractor latitude such
    that you do not accept liability. Require
    compliance with applicable certifications and
    request documentation of said compliance.
  • Specify General Obstruction Marking Scheme. Red
    lights and paint, strobes, etc.

26
Individual Sections
  • Soil Boring Data. Contractor should take own
    borings. Do not provide to them. Require new
    borings. Previous data should not be used.
  • Tower and Foundation Design. Designs must be
    approved by registered structural engineer in
    your state. Require stamped certifications prior
    to the delivery of materials to the site.
    Designs must meet applicable standards and codes.

27
Individual Sections
  • Grounding of Structures. Contractors must
    ground structures in accordance with application,
    applicable codes, and good engineering practice.
  • AM Ground System. Specify how ground system is
    to be constructed. Provide a plat drawing
    illustrating layout. Specify finish work for
    ground system as well.

28
Individual Sections
  • Work. Under this section contractor is required
    to coordinate with local trade unions to avoid
    labor issues. This section also requires
    contractor to return site to equal or better than
    original condition.
  • Concrete. Specifies form condition. Mechanic
    on site to maintain forms as necessary.
    Partially set concrete is to be rejected.
    Discuss proper temperature.

29
Individual Sections
  • Testing. This provision allows for independent
    testing at the discretion of the owner. Owner is
    economically responsible for such testing, but
    such testing if deemed necessary may help
    alleviate specification compliance issues down
    the road. Contractor is responsible at their
    expense for any remedial work necessary.

30
Individual Sections
  • For antennas and transmission line specify
    expected performance.
  • For transmitters power output, etc. should be
    specified.
  • For other construction such as buildings, specify
    dimensions desired, and other applicable
    information.
  • Provide as much detail as possible.

31
The Concept
  • Minimize the Liability of Owner/You.
  • Reduce Potential for Errors.
  • Specifically Identify Project Goals.
  • Specifically Identify Obligations.
  • Level the Playing Field for Potential
    Contractors.
  • Specify Critical Aspects of the Project Without
    Overstepping Your Expertise.
  • The Result is a Quality Project.

32
Specifications for Bid Submission
Thank You. Any Questions?
  • Jeremy D. Ruck, Senior Engineer
  • D.L. Markley Associates, Inc.
  • 2104 West Moss Ave.
  • Peoria, IL 61604
  • (309) 673-7511
  • jdr_at_dlmarkley.com
Write a Comment
User Comments (0)
About PowerShow.com