BID DOCUMENTS AND CONTRACT DOCUMENTS - PowerPoint PPT Presentation

1 / 52
About This Presentation
Title:

BID DOCUMENTS AND CONTRACT DOCUMENTS

Description:

BID DOCUMENTS AND CONTRACT DOCUMENTS * The difference between bid and contract documents. The bid document applies to before the contract is signed, whereas the ... – PowerPoint PPT presentation

Number of Views:225
Avg rating:3.0/5.0
Slides: 53
Provided by: ComputerA3
Category:

less

Transcript and Presenter's Notes

Title: BID DOCUMENTS AND CONTRACT DOCUMENTS


1
  • BID DOCUMENTS AND CONTRACT DOCUMENTS
  • The difference between bid and contract
    documents.
  • The bid document applies to before the contract
    is signed, whereas the contract document applies
    to after the contract agreement is signed by the
    owner and contractor .
  • The bid documents consist of
  • The invitation to bid .
  • Bid forms.
  • Drawings.
  • Specifications.
  • Requirements of bonds and insurance.
  • Addenda.

1
Bid Documents
2
  • Why we need to bid documents?
  • The contractor used it in prepare an estimate
    and submit a bid.
  • Its legal documents for construction and
    completion of the project.
  • Who is write a bid documents?
  • Architect Engineer.

2
Bid Documents
3
  • Contract Requirements
  • 1) Competitive contract.
  • 2) Negotiated.
  • In most municipal, state, and federal
    projects are awarded by competitive bidding.
  • -- Competitive bidding involves
  • _ Advertisement for bids in public media.
  • _ Bid opening is performed in the open public.
  • _ Contractor performs a detailed estimate and
    submits a bid price accordance with the contract
    documents.

3
Bid Documents
4
  • _ The owner and engineer perform the evaluation
    of bids at later date.
  • _ Most governments award contract to the lowest
    bidder, provided all conditions of the contract
    have been met.
  • _ Private owners are not required to award the
    contract to the lowest bidder but may select to
    the contractor deemed most desirable for the
    project.
  • -- Negotiated contracts Award of the contract
    is made to the contractor the owner feels can
    provide the best total performance , which may or
    may not be lowest initial cost.

4
Bid Documents
5
  • Arrangement of contract documents
  • Legal matters
  • - Bid forms.
  • - Bond requirements.
  • - Insurance requirements.
  • - General condition.
  • - Supplementary conditions of the contract.

5
Bid Documents
6
  • 2) Technical matters
  • - Plans (drawings).
  • - Specifications that describe the material,
    workmanship, and methods of construction that are
    required to build the project.
  • where conflicts exist between the drawings
    and written specifications, it is common practice
    that the written specifications govern.

6
Bid Documents
7
  • Building Construction Specifications
  • Its defined
  • 1) The quality of material.
  • 2) Performance rating of equipment.
  • 3) Level of workmanship.
  • 4) Warranty requirements.
  • Construction Specification Institute (CSI) Master
    format organizes project information into major
    divisions.

7
Bid Documents
8
  • A list of the CSI numbers and titles includes
  • 0-Introductory Information Bidding and
    Contracting Requirements.
  • 1-General Requirements.
  • 2-Site Construction.
  • 3-Concrete.
  • 4-Masonry.
  • 5-Metals.
  • 6-Wood and Plastics.
  • 7-Thermal and Moisture Protection.
  • 8-Doors and Windows

8
Bid Documents
9
  • Heavy/Highway Specifications
  • 1-General Provisions.
  • 2-Excavation and Embankment.
  • 3-Base Courses.
  • 4-Surfaces Courses bituminous, concrete paves.
  • 5-Structuressteel,concrete bridges.
  • 6-Materialsaggregate,asphalt.
  • 7-Traffic Control signals, signs.
  • 8-Incidental Construction guard rails, fences.

9
Bid Documents
10
Bidding requirements
  • The information contained in this section of the
    contract documents is extremely important to the
    estimating team . typical information in the
    bidding requirements includes

10
Bid Documents
11
Bid solicitation(???? ??????)
  • The bidding solicitation some times called the
    invitation to bid contain the time that bids
    must be submitted . the estimator must establish
    a plan to complete all work to meet the deadline
    of the bid date , other wise the bid will be
    disqualified. The bid solicitation also gives the
    name and address of the owner and design
    organization with instructions on how to obtain
    the bid documents.

11
Bid Documents
12
instruction to bidders
  • The instruction to bidders section describes
    vital information that is required to submit a
    bid. For example that may appear in the
    instruction to is a statement that the
    contractor must make a provision during
    execution of the contract document to allow the
    owner to take advantage of the owner's contract
    documents to allow the owner to take advantage of
    the owner's tax exempt status for materials and
    equipment purchased for the project.

12
Bid Documents
13
information Available to Bidders
  • The information available to bidders section may
    include such items as referencing a subsurface
    exploration report that has been prepared for the
    project , but is not shown in contract documents
    . the information available to bidders may
    include information about the project from a
    material testing laboratory .

13
Bid Documents
14
Bid forms
  • The bid form defines the format that is required
    for submission of the bid.
  • The format of the bid form impacts the
    assembly and summary of costs in the final
    estimate . the owner may request the bid as lump
    sum, unit prices based on predefined pay
    quantities in the bid documents , or combination
    of both.

14
Bid Documents
15
  • For construction project the work may priced by
    several method or combination of the pricing
    method. The method selected depends on
    distribution of risk between the owner and
    contractors.

15
Bid Documents
16
Bid form for lump-sum contracts
  • for project where a complete set of plans and
    specification have been prepared prior to
    construction and quantity of work is well
    defined, the estimate is normally prepared for
    the purpose of submitting a lump sum bid on the
    project. Building type project are usually bid on
    a lump sum basis .

16
Bid Documents
17
  • Its common practice for project to have one or
    more "alternates" attached to the bid documents
    of lump sum contracts the alternate may be to add
    or deduct a work item from the base of lump sum
    bid.
  • A lump sum estimate must include the cost of all
    material, labor, equipment, overhead, taxes,
    bonds and profit.

17
Bid Documents
18
  • Unit Price contracts
  • - It is used for most heavy engineering
    constructions such as
  • a. Earth works
  • b. Various kinds of pipelines
  • We use it because the precise quantities of
    materials may not be known in advance of
    construction.
  • Total cost actual quantity completed by the
    contractor X bid price per unit
  • So the actual cost of the project can be
    determined at the end of the project based on the
    actual quantities that results at the completion
    of the project.
  • The cost per unit submitted in abed includes
    furnishing of materials, labor, equipment,
    supervision, insurances, taxes, profit, and bonds
    as required for completely installing a unit.

18
Bid Documents
19
  • Negotiated work
  • It is used when the owner wants to start
    construction at the earliest possible date to
    benefit from an early completion and use of the
    project.
  • A representative of the owner works with the
    contractor to evaluate alternatives to obtain a
    project configuration that meets the needs of the
    owner, yet with a cost within the owners
    allowable budget.
  • The final contract agreement usually is a cost
    plus a fixed fee with a guaranteed maximum
    amount. If the cost is above or below the
    guaranteed maximum amount, then the owner and the
    contractor agree to a splitting of the
    difference.
  •  

19
Bid Documents
20
  • Addendum
  • It is a change in the contract documents during
    the bidding process, before a ward of the
    contract.
  • Addenda are issued to correct errors in the
    contract documents or clarify an issue. May
    concern addition to the work at the request of
    the owner.
  • The estimating team must be certain that the
    costs of all addenda are included in the estimate.

20
Bid Documents
21
  • Alternate
  • It is an addition or subtraction to a base bid
    price for substitutions requested by the owner
    during the bidding process.
  • Each alternate is listed and numbered separately
    in the bid documents.
  • For example
  • An alternate No.1 may be add the parking lot.
  • An alternate No.2 may be deduct the sidewalks.
  •  

21
Bid Documents
22
  • Change order
  • It is issued by the designer but signed by the
    owner and contractor
  • Making a change in the contract documents during
    construction.
  • Upon approval by the owner change orders become a
    part of the contract documents.
  •  
  •  

22
Bid Documents
23
  • Warranties
  • They are guarantees by the contractor that
    specific components of the project will be free
    from defects due to materials or workmanship for
    a specified warranty period.
  • They cover specific items, such as a roofing
    warranty or an equipment warranty that are part
    of the construction project.
  • The type of warranty and warranty periods are
    defined in the written specifications of the
    contract documents.

23
Bid Documents
24
Bonds
  • Bidders submit bonds as qualifications for
    submitting a bid for a project.
  • The contractor secures bonds from a bonding
    company or a bank on behalf of the owner as
    financial and legal protection for the owner.

25
Type of bonds
  • Three type of bonds are commonly required in
    construction contracts (as the book)
  • Bid bond.
  • Prepayment bond.
  • Performance bond.
  • Maintenance bond.
  • Payment bond.

26
Bid Bond
  • It is ensure the owner that the contractor will
    sign the contract for the bid amount, if the
    bidder refuses or fails to sign the contract, the
    owner may retain the bond or check as liquidated
    damages.
  • Its amount equal to (5-20) of the amount of the
    bid.

27
Performance Bond
  • It is ensure the owner that the contractor will
    perform all work in accordance with the contract
    documents.
  • Performance bond last for the period of
    construction of a project.
  • Its amount 25,50,100 of the contract, but the
    cost of the bond usually is based on
  • Amount of the contract.
  • Duration of the project..

28
Payment Bondor Material and Labor Payment Bond
  • This bond is issued to ensure the owner that all
    wages and bills for material will be paid upon
    completion of the project.

29
  • If the contractor
  • default,
  • or fails to complete the project,
  • or fails to pay labor and material cost
  • the bond company or the bank agrees to fulfill
    the contract agreement.

30
Insurance
  • The contractor must secured insurance, because
    there are many risks involved in construction.
  • The precise losses that are reimbursable from
    insurance are based on predetermined losses named
    in the insurance policy.

31
Types of Available Insurance for Construction
Projects
  1. Basic Builder's Risk Insurance.
  2. Public Liability and Property Damage Insurance.
  3. Workmens Compensation Insurance.
  4. Contractors Equipment Floater.

32
Basic Builder's Risk InsuranceGeneral All Risk
(GAR)
  • General Builder's Risk which covers damages to
    the project due fires, wind, and hail.
  • Insurance is based on the estimated completed
    value of the project, so the premium rate usually
    is set at 60 of the complete value.
  • Basic Builder's Risk Insurance varies with the
    type and location of the structure.

33
Public Liability and Property Damage Insurance
  • It protects the contractor against injuries to
    the general public or public property due to
    actions of the employees while performing works.
  • The cost of this insurance depends on the type of
    work and the safety record of the contractor.
  • It is range from (2-8) of the base cost of the
    labor.

34
Workmens Compensation Insurance
  • To protect workers as a result of injury or death
    on a project.
  • It provides medical expenses and payment of lost
    wages during the period of injury.
  • The cost can rang from (10-30) of the base cost
    of the labor, depending on the type of work that
    is performed by each worker.

35
Contractors Equipment Floater
  • It provides protection against loss or damages to
    equipment because of fire, tornado, flood, perils
    of transportation, and theft.
  • The cost varies with location, it is about 1.50
    per 100.00 of equipment value per year.

36
Building construction drawings
  • title sheet (This sheet contains the name of the
    project, owner, designer, and other pertinent
    information related to the project).

36
Bid Documents
37
Title sheet
37
Bid Documents
38
Building construction drawings
  • index sheet (which provides a summary of all the
    remaining sheet in the drawings, Its shows the
    list of drawing. For building type project, the
    remaining sheets generally follow this
    arrangement civil, architectural, structural,
    mechanical, electrical, plumbing, and fire
    protection. A letter before the sheet number
    identifies each drawing. For example, the civil
    drawing are number C1, C2, C3, etc. the
    architectural drawings are number as S1, S2, S3,
    etc).

38
Bid Documents
39
Index sheet
Bid Documents
39
40
Building construction drawings
  • Plans, elevations, and sections(he pictorial
    presentations used in drawings are shown from
    several viewing angles).
  • plane views (Views looking vertically down on the
    object ).
  • elevation views (Views looking horizontally at an
    object ).

40
Bid Documents
41
Plane views
Bid Documents
41
42
Building construction drawings
  • perspective views (Views looking at an object
    from a point that is not perpendicular to any
    face of the object).
  • A section view (view of the object as seen by
    passing a cutting plane through the object)
  • A detail (is an enlargement of a specific area of
    a project. Connections of structural components
    are generally sown as details).

42
Bid Documents
43
Detail drawing
Bid Documents
43
44
Building construction drawings
  • isometric or pictorial drawings (Some items in a
    project are difficult to show by plan, elevation,
    or section view. Items such as the routing of
    conduits for electrical or mechanical work are
    examples. It is a common practice to show the
    routing in three-dimensional pictorial drawings).

44
Bid Documents
45
Building construction drawings
  • Line Work
  • Several types of line work that are used in
    preparing drawings include
  • Thick lines-outline edges of objects (plans and
    elevations).
  • Thin lines with short dashes-denote the
    centerline of an object
  • Phantom lines-show the path of moving parts
  • Broken lines-denote the object is longer than
    shown
  • Short dashed lines-denote edges on the object
    that cannot be seen from the near side surface of
    the object

45
Bid Documents
46
Building construction drawings
  • Scales
  • Usually the type of scale used is identified at
    the bottom of the page on the drawings. However,
    several different scale may be used on a single
    sheet. Therefore, it is important to be certain
    that the correct scale is used in determining the
    quantities for estimating. Occasionally, a
    portion of the drawing is shown without any
    scale. When this condition exists, there should
    be a note that states the drawing is not to
    scale. The estimator must also be cautious
    because sometimes the drawings are reduced in
    size, such as a half-size drawing, to permit
    easier handling during construction.

46
Bid Documents
47
Building construction drawings
  • Scales
  • Two types of scales are used in construction
    drawings, the architects scale and the
    engineers scale. The architects scales that are
    commonly used for plans and elevations include
    1/32 in. 1 ft and 1/16 in. 1 ft. Complicated
    areas often use the ¼ in. 1 ft, or ½ in. 1 ft
    on the architects scale. Special applications
    that require high details are 1.5 in. 1 ft, or
    3 in. 1 ft, or may be drawn to a half or even a
    full scale.
  • The engineers scale, graduated in tenths of an
    inch, is often used for civil, structural, and
    mechanical drawings. The scales are 10, 20, 30,
    40, 50, and 60. The higher numbers of 50 or 60
    are used for large areas, such as site-work or
    plot plans. Details of drawings often use the
    smaller numbers, such as 10, 20, or 30. The 40 on
    the engineers scale is equivalent to the ¼ in.
    on the architects scale.

47
Bid Documents
48
Building construction drawings
  • Schedules
  • To simplify the presentation of repetitious items
    (such as footings, columns, doors, windows, room
    finishes, etc.) a schedule is frequently used. A
    schedule is a tabular listing of the repetitive
    items in the project. For example, a room
    schedule is a tabular list of all rooms in the
    structure, showing the type of floor covering,
    wall covering, and type of ceiling. Likewise, a
    footing schedule is a listing of all footings in
    the foundation, showing the diameter, depth,
    type, size, and number of reinforcing bars. Thus,
    a schedule is a concise and convenient method to
    show all common types of items in one location.

48
Bid Documents
49
Building construction drawings
  • Symbols and abbreviations
  • Symbols are used on the drawings to identify the
    types of materials and work required during
    construction. Examples are valves, pumps, type of
    welds, electrical outlets, etc. Abbreviations of
    organization that produce technical information
    and standards for materials and construction
    procedures are frequently referenced in the
    specifications of contract documents.

49
Bid Documents
50
Detail drawing
Bid Documents
50
51
Thank You for Listening
51
Bid Documents
52
Any question
52
Bid Documents
Write a Comment
User Comments (0)
About PowerShow.com