Sunshine-Moon River Basin (SMRB) Project. Project Location. Mushroom Sea. Country B. Country A ... Project Activities with possible Environmental Impacts ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 18
Provided by: WB1673
Category:
Tags: emp | case | impact | moon | preparation | study

less

Transcript and Presenter's Notes

Title: Case Study Preparation of an EMP


1
Case Study Preparation of an EMP
  • Integrated Ecosystem Management
  • of
  • Sunshine-Moon River Basin (SMRB) Project

2
(No Transcript)
3
Project Location
Country A
Earth Town
Sunshine River
HPP
HPP
Country X
Flower Town
Moon River
Country B
Red Nature Reserve RAMSAR site
Mouth of Sunshine River
Country Y
Mushroom Sea
4
Environmental Issues
  • Surface and ground waters pollution due to
    untreated industrial and municipal wastewaters
    discharged directly into reservoirs/rivers
  • Environmental degradation (eutrophication,
    habitat loss, erosion) of coastal habitats,
    inland surface waters and marshes
  • Salt water intrusion in Sunshine Delta due to
    long term agricultural practices (irrigation)

5
Project Environmental Goals
  • Reduction of water nutrients and other water
    pollution from municipal and industrial sources
    in selected municipalities in the Basin
  • Restoring and maintaining of coastal wetland
    ecosystem in Sunshine River through improved
    flood management, conservation of wetland sites
    and restoration of river banks
  • Reduction of salt water intrusion through a pilot
    scheme implemented in Sunshine river

6
Project Activities with possible Environmental
Impacts
  • Component 2 Improved management and use of
    wetlands eco-systems and biodiversity
  • Improvements in sites, services and management
    tools in Red Nature Reserve Ramsar site (Country
    A) and in two protected areas (Country B)
  • Restoration and improvement of small scale water
    existing infrastructure to maintain water flows,
    address the problems of saltwater intrusion,
    flood management and erosion (e.g.,
    rehabilitation of river gates, wooden irrigation
    wheels, restoration of river banks)
  • Enhancement of HPPs and dams operational
    capacities to maintain environmental flow
    requirements and control flood management (e.g.,
    dam safety monitoring equipment)

7
Project Activities with possible Environmental
Impacts contd
  • Component 3 - High priority investments in water
    pollution control with low cost, appropriate
    wastewater technology improvements
  • Rehabilitation and upgrading of wastewater
    treatment systems in 3 municipalities in Country
    A and 2 in Country B including fixing leaking
    wastewater collection system and additional
    treatment infrastructure for reduction of
    nutrients (e.g., improvement of primary treatment
    and installation of small design for biological
    process)
  • Upgrading the industrial wastewater treatment
    system at a metallurgical factory in the Flower
    Town (Country A) (e.g., replacement of existing
    equipment, additional treatment equipment to
    reduce chromium and nickel pollution during
    production process)

8
Applicable Safeguard Policies
  • Environmental Assessment category B (OP/BP 4.01)
  • Natural Habitats (OP/BP 4.04) - Ramsar
  • Safety of Dams (OP/BP4.37)
  • Projects on International Waterways (OP/BP7.50 )
    legal policy that is not included in EMP

9
OP/BP 4.01 Environmental Assessment
  • Preparation of an EA and site-specific
    Environmental Management Plans (EMPs)
  • EA identified and analyzed the potential
    environmental impacts of the different activities
    (on air, groundwater, surface water, soil, flora
    and fauna)
  • EA made recommendations and options for
    mitigation measures
  • EMPs addressed mitigation measures and monitoring
    activities

10
OP/BP 4.01 and public disclosure
  • Draft EA and site specific EMPs have been
    discussed during several consultations in both
    countries
  • Final EA and site-specific EMPs were disclosed in
    both countries in local language and at the Bank
    Infoshop in English

11
OB/BP 4.04 Natural Habitats(triggered because of
positive investments in protected areas)
  • Flood management in SMRB can be compromised by
    poor operations of HPPs or needs to meet other
    water use demands ? maintenance of environmental
    flows is complicated
  • Small-scale infrastructure to regulate the water
    regime in the Mini River within protected Red
    Nature Park in order to restore natural wetlands
    in the park
  • Improvements in sites which allows visitor access
    to sensitive ecosystems (promoting eco-tourism)

12
OP 4.37 Safety of Dams (policy application)
  • inspect and evaluate the safety status of the
    existing dam and its performance history
  • review and evaluate the owners operation and
    maintenance procedures and
  • provide a written report of findings and
    recommendations for any remedial work or
    safety-related measures necessary to upgrade the
    existing dam to an acceptable standard of safety

13
OP 4.37 Safety of Dams contd (Study findings
and recommendations)
  • dam is located in a seismically active area
  • installation of proper equipment would allow
    adequate response to earthquakes
  • needed dam safety monitoring equipment and
    development of emergency and evacuation plans

14
Other safeguard policies
  • Physical Cultural Resources (OP/BP 4.11) - The
    EMP notes that archaeological resources should be
    covered by chance-finds procedures clause
    incorporated in the contractors agreements
  • Involuntary Resettlement (OP/BP 4.12) - No land
    acquisition or relocation of people will be
    necessary for proposed infrastructure
    improvements

15
EMP
  • Mitigation Plan
  • Monitoring Plan
  • Proposed Environmental Training
  • Monitoring Equipment

16
Preparation of Mitigation Plan for a
site-specific EMP
Earth Town wastewater collection and treatment
infrastructure
17
Preparation of Mitigation Plan for a
site-specific EMP contd
Participants will be asked to develop the
Environmental Mitigation Plan for proposed
municipal infrastructure investments in the Earth
Town