Title: Owen Russell


1
  • Owen Russell
  • General Manager - Customer Services
  • Darren Raeck
  • Manager Engineering Services

2
Robinvale High Pressure Pipeline Project-
Reticulation System- Pump Station
3
Reticulation System
  • High Pressure Pipeline Construction Contract
  • Awarded to Akron Pty Ltd on 21 May 2008.
  • Contract Value approx 9 Million.
  • 60 week contract with an originals date for
    Completion of mid July 2009, Extension of time to
    contract completion date has been granted till
    September.

4
Reticulation System
  • High Pressure Pipeline Construction
  • Current Status
  • 75 Complete
  • Pipe (High Pressure)
  • 500 mm or greater - All 20 km installed
  • 450mm to 375mm - 85 (17 km) installed
  • 300mm to 225mm - 50 (14 km) installed
  • Pipe (On-farm)
  • 225 mm (5 km installed, 5 km remaining)
  • Fittings
  • Valves (Air Scour) 50 (120 off) installed
  • Meter Assemblies 40 (90 off) installed

5
Construction Progress
6
Construction Progress
7
Construction Progress
8
Reticulation System
  • High Pressure Pipeline Construction
  • Future Works
  • Pipe
  • Install the remaining 20 km of pipe
  • Majority is 450 mm and smaller pipe
  • Pipeline pressure testing
  • Involves pumping water into pipes and
  • building pressure up to 110m water head
  • and successfully hold for half an hour.
  • Fittings
  • Install remaining 100 valves
  • Install remaining 140 meter assemblies

9
Reticulation System
  • Domestic Stock Installation
  • Some 150 new Domestic and Stock meter assemblies
    required
  • Flow restricted to 0.75 L/s
  • Pressure reducing valves to reduce pressure to 35
    m head
  • LMW to apply same main to meter policy as Urban
    Water.
  • Horticultural properties will have meters to be
    located either next to irrigation outlet or
    nearest boundary, House on separate title will
    have separate connection and independent meter
    (approximately 15 km of 50 mm HDPE pipe)
  • Internal works responsibility of landowner
    (depends on pipe condition)
  • Future Works
  • Tender to be issued late June 09
  • Award Aug 09
  • On-going Landholder Liaison as the works are
    installed
  • Installations complete Dec 09

10
IRRIGATION OUTLETS
11
IRRIGATION OUTLETS WITH FILTER
12
(No Transcript)
13
  • ROBINVALE HIGH PRESSURE PROJECT
  • Scott Barnes
  • Projects Manager

14
Pump Station
  • Pump Station built next to the Existing Pump
    Station
  • Designed by consultant Kellogg Brown Root.
  • Jetty construction with in the Murray River with
    intake 5 m below normal pool level.
  • Six flooded intake lines for pump efficiency.
  • Pumps housed in an open concrete basement with
    colourbond building for electricals etc.
  • 4 Jacking Pumps for Low Supply (up to 25 ML/d) /
    High Pressure System
  • 5 Main Pumps (each able to deliver 64 ML/d)
  • Total system delivery of 320 ML/d at 110 m water
    pressure

15
(No Transcript)
16
Pump Station
  • Contracts
  • Supply Contracts
  • Pump and Motor Units and Variable Speed Drives
    Supply
  • Flowserve and valued at 3 M
  • Pumps - Thompson Kelly Lewis
  • Motors - Teco
  • Variable Speed Drives - Siemens.
  • Electrical Supply approx 0.5M
  • - Transformers - Schneider Electrical
  • - Upgrade of Power - Powercor
  • Construction Contract
  • High Pressure Pump Station Construction

17
Pump Station
  • High Pressure Pump Station Construction Contract
  • Awarded to Fulton Hogan Pty Ltd on 20 January
    2009.
  • Contract Value approx 9.5 Million.
  • 45 week contract with an originals date for
    Completion of mid November 2009.
  • Current completion date is early December 2009.

18
Pump Station
  • High Pressure Pump Station Construction
  • Current Status
  • 20 Complete
  • Pump Station
  • Excavation down to water table level (4 m)
  • Installation of de-watering system and pumps (2
    ML/d)
  • Excavation down to final foundation level
    (further 3 m)
  • Installation of Base Slab
  • Special Water Retaining Concrete Mix
  • supplied by Robinvale Concrete
  • 32 m long x 18 m wide x 1.5 m thick
  • Two 500 cubic m concrete pours
  • Steel Work for Concrete Walls
  • 5.5 m high

19
Pump Station
  • High Pressure Pump Station Construction
  • Future Works
  • Pump Station
  • Complete Walls / Building
  • Internal Pipework / Pumps / Fitout
  • Connection to Reticulation
  • Suction Line
  • Remove Levee Bank
  • Excavation / Sheet piling
  • Install HD Polyethylene Pipes
  • Reinstatement
  • Jetty Works
  • Pile Driving
  • Jetty Structure
  • Install Suction Inlets
  • Walkway

20
Commissioning
  • Scheduled to commence in Dec 2009
  • Pump Station will commence delivery into the
    Reticulation System with a
  • transferred into the existing Irrigation
    Channel.
  • As Pump Station commissioning continues
  • Pipelines and irrigation meters will be scoured
  • Pressure reducing valves calibrated
  • Domestic (garden) works checked
  • Other various system checks will occur
  • Handover of the On-farm Pipeline
  • Irrigation
  • Domestic (Garden)

21
Connection
  • Connections to commence early in the 2010
  • Dual System to operate while connections are
    occurring
  • Exsiting System will be turned off (with
    pre-warning) when the majority of connections are
    made.
  • Issues
  • Growers need to commence
  • preparation for connections.
  • LMW staff available to assist
  • with teething issues
  • As a contingency measure
  • Existing system to remain
  • dormant for 6 months

22
(No Transcript)
23
(No Transcript)
24
(No Transcript)
25
Further information
  • Lower Murray Water
  • lmw.vic.gov.au
  • 03 50513400

26
(No Transcript)