Title: The Councils Approach to Modeling
1The Councils Approach to Modeling
- Michael Schilmoeller
- Northwest Power and Conservation Council
- for the
- California Energy Commission
- June 4, 2007
2Overview
- The Regional portfolio model
- Council risk metric
- Discussion of uncertainty specific to carbon risk
3Different Risk Language
- Uncertainty
- Risk
- Stochastic Analysis
- Scenario Analysis
4Different Risk Modeling
- Scenario Analysis on Steroids
- Probabilities associated with all uncertainties
- Imperfect Foresight, Decision Criteria
- Adaptive Plans
5Background on the Efficient Frontier
- Because we face uncertainty, we need to find
Plans that perform well over wide range of
possible Futures - Futures -- possible combinations of hydro
conditions, loads, fuel prices, market prices,
CO2 penalties and so on over planning period - Plans types and amounts of resources and
earliest be prepared to start construction
dates (options)
Background
6And a Bit More Abstractly
- Futures circumstances over which the decision
maker has no control that will affect the outcome
of decisions - Plans actions and policies over which the
decision maker has control that will affect the
outcome of decisions
Background
7Example Demand Uncertainty
Background
8Sources of Uncertainty
Load requirements Gas price Hydrogeneration Elect
ricity price Forced outage rates Aluminum
price CO2 tax Production tax credits Green tag
value (Renewable Energy Credit)
Background
9Resource Plan
These dates represent the earliest that
construction would begin. All siting, licensing,
and other preparation must be completed by these
dates. The earliest in-service dates are 2 years
later for CCCT, 1 year for SCCT, 3 years six
months for Coal, and 1 year for Wind, due to
construction time requirements. Wind energy
assume a 30 percent availability. Turbines have 5
percent forced outages.
Background
10The Construction Cycle
- After an initial planning period, there typically
large expenditures, such as for turbines or
boilers, that mark decision points.
9 months
9 months
18 months
Cash expenditures
Background
11Modeling Cohorts
- Each period can have a cohort of plants, usually
of different size or capacity - All cohorts will be affected by changing
circumstances, but may be at different stages of
development
Capacity
time
Background
12Distribution of Cost for a Plan
Number of Observations
Background
13Risk and Expected Cost Associated With A Plan
Risk average of costsgt 90 threshold
Likelihood (Probability)
Power Cost (NPV 2004 M)-gt
Background
14Feasibility Space
Increasing Risk
Increasing Cost
Background
15Feasibility Space
Increasing Risk
Increasing Cost
Background
16Efficient Frontier
Background
17Spinner Graphs
- A given plan, across all futures
- Illustrates scenario analysis on steroids
- Link to L28X-f1232 (D)_P.xls
Background
18Modeling Process
Portfolio Model
19Olivia
- Flexible
- The user uses a high-level representation to
describe their system - Exploration is easy
- Specific to users system
- Rich in features
- Has a library of physical and financial
resources, of uncertainty processes and risk
measures - Builds on Councils data
- Puts planning flexibility into modeling
Olivia
20Overview
- The Regional portfolio model
- Council risk metric
- Discussion of uncertainty specific to carbon risk
21Importance of Multiple Perspectives on Risk
- Standard Deviation
- VaR90
- 90th Quintile
- Loss of Load Probability (LOLP)
- Resource - Load Balance
- Incremental Cost Variation
- Average Power Cost Variation (Rate Impact)
- Maximum Incremental Cost Increase
- Exposure to Wholesale Market Prices
- Imports and Exports
22TailVaR90 Risk MeasureFor A Given Plan
Risk average of costsgt 90 threshold
Likelihood (Probability)
Power Cost (NPV 2004 M)-gt
Risk Measures
23The Rationale for TailVaR90
- Measure of likelihood and severity of bad
outcomes, rather than of predictability - A measure should not penalize a plan because the
plan produces less predictable, but strictly
better outcomes - We want to pay only for measures that reduce the
severity and likelihood of bad outcomes - The measure should capture portfolio
diversification - The objective of economic efficiency
- Determined by statute
- Risk measure is denominated in same units as the
objective, i.e., net present value dollars
Risk Measures
24Coherent Measures of Risk
- In 1999, Philippe Artzner, Universite Louis
Pasteur, Strasbourg Freddy Delbaen,
Eidgenossische Technische Hochschule, Zurich
Jean-Marc Eber, Societe Generale, Paris and
David Heath, Carnegie Mellon University,
Pittsburgh, Pennsylvania, published Coherent
Measures of Risk (Math. Finance 9 (1999), no. 3,
203-228) or http//www.math.ethz.ch/delbaen/ftp/p
reprints/CoherentMF.pdf - Addressing problems with VaR
- Developed a system of desirable properties for
financial and economic risk measures
Coherent Risk Measures
25Desirable Properties For a Risk Metric r
- Subadditivity For all random outcomes (losses)
X and Y, - r(XY) ? r(X)r(Y)
- Monotonicity If X ? Y for each future, then
- r(X) ? r(Y)
- Positive Homogeneity For all l ? 0 and random
outcome X - r(lX) lr(X)
- Translation Invariance For all random outcomes
X and constants a - r(Xa) r(X) a
Metrics
Coherent Risk Measures
26Risk Paradoxes
- The following risk metrics are not coherent
- Standard deviation
- VaR
- Loss of load probability (LOLP)
- Any quantile measure
- Examples of coherent measures
- TailVaR90
- Expected loss (average loss exceeding some
threshold) - Risk measure which is sub-additive and monotonic
- Unserved energy (UE)
Issues with Risk Measures
27Risk Paradoxes
- Case 1 We choose standard deviation for
economic risk measurement.
Issue Plan B produces a more predictable
outcome, as measured by standard deviation, but
all of the outcomes are worse than those
associated with Plan A. This risk metric assigns
more risk to Plan A than to Plan B. Typically,
however, a decision maker is looking at cost,
too, and could discriminate between these cases.
B
A
Issues with Risk Measures
28Risk Paradoxes
- Case 1 We choose standard deviation for
economic risk measurement.
Issue Two plans produce quite distinct
distributions for cost outcomes. For one of the
plans, the outcomes are much worse under certain
circumstances than for the other plan. However,
the distributions have identical mean and
standard deviation. The risk measure can not
discriminate between the plans.
Issues with Risk Measures
29Risk Paradoxes
- Case 2 We choose LOLP for assessing the
engineering reliability of two power systems. - Issue We have two systems, both meeting a load
of 150MW. The first consists of one 200 MW
power plant, forced outage rate (FOR) of 8. The
second system is two 100 MW power plants, FOR
also 8. - We know intuitively that portfolio diversity of
resources should result in a more reliable
system.
Issues with Risk Measures
30Risk Paradoxes
- Case 2 We choose LOLP for assessing the
engineering reliability of two power systems.
Issues with Risk Measures
31Risk Paradoxes
- Case 2 We choose LOLP for assessing the
engineering reliability of two power systems.
The LOLP of the single unit is lower than that
for the diversified system. What is going on
here?
Issues with Risk Measures
32Unserved Energy Gets It Right
Issues with Risk Measures
33Risk Paradoxes
- Case 3 We choose Value at Risk (VaR) to measure
the economic risks associated with merging two
power systems. - We believe that the diversity of the merged
systems should result in less risk.
Issues with Risk Measures
34Risk Paradoxes
- VaR is an estimate of the level of loss on a
portfolio which is expected to be equaled or
exceeded with a given, small probability.
- A quantile associated with the bad tail of a
distribution (e.g., 85th percentile) - A time period (e.g., overnight)
- A reference point (e.g., todays value of the
portfolio)
Issues with Risk Measures
35Risk Paradoxes
- Assume a reference point of zero
- Two values of outcome, a loss of 0.00 and a loss
of 1.00 - Ten futures
!??
Metrics
Issues with Risk Measures
36Overview
- The Regional portfolio model
- Council risk metric
- Discussion of uncertainty specific to carbon risk
37CO2 Cost
- May 2003 Advisory Committee Meeting
- Characterizing probabilities where no information
in known - Ultimately, used thresholding
38CO2 Tax
39CO2 Tax
40Other EffectsRelated to Carbon Risk
- Load requirements
- Hydrogeneration
- Green Tag Value
- Production Tax Credits
41Value of Renewable Energy Credit
- Applies to more than emerging technologies for
power generation - Will continue to influence power generation
economics after technologies mature, after carbon
risk cost is internalized
42Value of Renewable Energy Credit
43Production Tax Credits
- Changing markets
- As cost of non-fossil fuel technologies improve,
less support for credits - Internalizes external costs
44Production Tax Credits
45Production Tax Credits
46Production Tax Credits
47Conclusions
- There are optimal resource choices even when the
future is uncertain. - Decision-makers change course based on outcomes
to minimize adverse outcomes. Planning needs to
have and cost exit strategies and contingency
options. - To value exit strategies and contingency options,
decision-makers need to assign probabilities to
futures.