The Councils Approach to Modeling - PowerPoint PPT Presentation

1 / 47
About This Presentation
Title:

The Councils Approach to Modeling

Description:

Any quantile measure. Examples of coherent measures. TailVaR90 ... A quantile associated with the 'bad tail' of a distribution (e.g., 85th percentile) ... – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 48
Provided by: michaelsch7
Category:

less

Transcript and Presenter's Notes

Title: The Councils Approach to Modeling


1
The Councils Approach to Modeling
  • Michael Schilmoeller
  • Northwest Power and Conservation Council
  • for the
  • California Energy Commission
  • June 4, 2007

2
Overview
  • The Regional portfolio model
  • Council risk metric
  • Discussion of uncertainty specific to carbon risk

3
Different Risk Language
  • Uncertainty
  • Risk
  • Stochastic Analysis
  • Scenario Analysis

4
Different Risk Modeling
  • Scenario Analysis on Steroids
  • Probabilities associated with all uncertainties
  • Imperfect Foresight, Decision Criteria
  • Adaptive Plans

5
Background on the Efficient Frontier
  • Because we face uncertainty, we need to find
    Plans that perform well over wide range of
    possible Futures
  • Futures -- possible combinations of hydro
    conditions, loads, fuel prices, market prices,
    CO2 penalties and so on over planning period
  • Plans types and amounts of resources and
    earliest be prepared to start construction
    dates (options)

Background
6
And a Bit More Abstractly
  • Futures circumstances over which the decision
    maker has no control that will affect the outcome
    of decisions
  • Plans actions and policies over which the
    decision maker has control that will affect the
    outcome of decisions

Background
7
Example Demand Uncertainty
Background
8
Sources of Uncertainty

Load requirements Gas price Hydrogeneration Elect
ricity price Forced outage rates Aluminum
price CO2 tax Production tax credits Green tag
value (Renewable Energy Credit)
Background
9
Resource Plan
These dates represent the earliest that
construction would begin. All siting, licensing,
and other preparation must be completed by these
dates. The earliest in-service dates are 2 years
later for CCCT, 1 year for SCCT, 3 years six
months for Coal, and 1 year for Wind, due to
construction time requirements. Wind energy
assume a 30 percent availability. Turbines have 5
percent forced outages.
Background
10
The Construction Cycle
  • After an initial planning period, there typically
    large expenditures, such as for turbines or
    boilers, that mark decision points.

9 months
9 months
18 months
Cash expenditures
Background
11
Modeling Cohorts
  • Each period can have a cohort of plants, usually
    of different size or capacity
  • All cohorts will be affected by changing
    circumstances, but may be at different stages of
    development

Capacity
time
Background
12
Distribution of Cost for a Plan
Number of Observations
Background
13
Risk and Expected Cost Associated With A Plan
Risk average of costsgt 90 threshold
Likelihood (Probability)
Power Cost (NPV 2004 M)-gt
Background
14
Feasibility Space
Increasing Risk
Increasing Cost
Background
15
Feasibility Space
Increasing Risk
Increasing Cost
Background
16
Efficient Frontier
Background
17
Spinner Graphs
  • A given plan, across all futures
  • Illustrates scenario analysis on steroids
  • Link to L28X-f1232 (D)_P.xls

Background
18
Modeling Process
Portfolio Model
19
Olivia
  • Flexible
  • The user uses a high-level representation to
    describe their system
  • Exploration is easy
  • Specific to users system
  • Rich in features
  • Has a library of physical and financial
    resources, of uncertainty processes and risk
    measures
  • Builds on Councils data
  • Puts planning flexibility into modeling

Olivia
20
Overview
  • The Regional portfolio model
  • Council risk metric
  • Discussion of uncertainty specific to carbon risk

21
Importance of Multiple Perspectives on Risk
  • Standard Deviation
  • VaR90
  • 90th Quintile
  • Loss of Load Probability (LOLP)
  • Resource - Load Balance
  • Incremental Cost Variation
  • Average Power Cost Variation (Rate Impact)
  • Maximum Incremental Cost Increase
  • Exposure to Wholesale Market Prices
  • Imports and Exports

22
TailVaR90 Risk MeasureFor A Given Plan
Risk average of costsgt 90 threshold
Likelihood (Probability)
Power Cost (NPV 2004 M)-gt
Risk Measures
23
The Rationale for TailVaR90
  • Measure of likelihood and severity of bad
    outcomes, rather than of predictability
  • A measure should not penalize a plan because the
    plan produces less predictable, but strictly
    better outcomes
  • We want to pay only for measures that reduce the
    severity and likelihood of bad outcomes
  • The measure should capture portfolio
    diversification
  • The objective of economic efficiency
  • Determined by statute
  • Risk measure is denominated in same units as the
    objective, i.e., net present value dollars

Risk Measures
24
Coherent Measures of Risk
  • In 1999, Philippe Artzner, Universite Louis
    Pasteur, Strasbourg Freddy Delbaen,
    Eidgenossische Technische Hochschule, Zurich
    Jean-Marc Eber, Societe Generale, Paris and
    David Heath, Carnegie Mellon University,
    Pittsburgh, Pennsylvania, published Coherent
    Measures of Risk (Math. Finance 9 (1999), no. 3,
    203-228) or http//www.math.ethz.ch/delbaen/ftp/p
    reprints/CoherentMF.pdf
  • Addressing problems with VaR
  • Developed a system of desirable properties for
    financial and economic risk measures

Coherent Risk Measures
25
Desirable Properties For a Risk Metric r
  • Subadditivity For all random outcomes (losses)
    X and Y,
  • r(XY) ? r(X)r(Y)
  • Monotonicity If X ? Y for each future, then
  • r(X) ? r(Y)
  • Positive Homogeneity For all l ? 0 and random
    outcome X
  • r(lX) lr(X)
  • Translation Invariance For all random outcomes
    X and constants a
  • r(Xa) r(X) a

Metrics
Coherent Risk Measures
26
Risk Paradoxes
  • The following risk metrics are not coherent
  • Standard deviation
  • VaR
  • Loss of load probability (LOLP)
  • Any quantile measure
  • Examples of coherent measures
  • TailVaR90
  • Expected loss (average loss exceeding some
    threshold)
  • Risk measure which is sub-additive and monotonic
  • Unserved energy (UE)

Issues with Risk Measures
27
Risk Paradoxes
  • Case 1 We choose standard deviation for
    economic risk measurement.

Issue Plan B produces a more predictable
outcome, as measured by standard deviation, but
all of the outcomes are worse than those
associated with Plan A. This risk metric assigns
more risk to Plan A than to Plan B. Typically,
however, a decision maker is looking at cost,
too, and could discriminate between these cases.
B
A
Issues with Risk Measures
28
Risk Paradoxes
  • Case 1 We choose standard deviation for
    economic risk measurement.

Issue Two plans produce quite distinct
distributions for cost outcomes. For one of the
plans, the outcomes are much worse under certain
circumstances than for the other plan. However,
the distributions have identical mean and
standard deviation. The risk measure can not
discriminate between the plans.
Issues with Risk Measures
29
Risk Paradoxes
  • Case 2 We choose LOLP for assessing the
    engineering reliability of two power systems.
  • Issue We have two systems, both meeting a load
    of 150MW. The first consists of one 200 MW
    power plant, forced outage rate (FOR) of 8. The
    second system is two 100 MW power plants, FOR
    also 8.
  • We know intuitively that portfolio diversity of
    resources should result in a more reliable
    system.

Issues with Risk Measures
30
Risk Paradoxes
  • Case 2 We choose LOLP for assessing the
    engineering reliability of two power systems.

Issues with Risk Measures
31
Risk Paradoxes
  • Case 2 We choose LOLP for assessing the
    engineering reliability of two power systems.

The LOLP of the single unit is lower than that
for the diversified system. What is going on
here?
Issues with Risk Measures
32
Unserved Energy Gets It Right
Issues with Risk Measures
33
Risk Paradoxes
  • Case 3 We choose Value at Risk (VaR) to measure
    the economic risks associated with merging two
    power systems.
  • We believe that the diversity of the merged
    systems should result in less risk.

Issues with Risk Measures
34
Risk Paradoxes
  • VaR is an estimate of the level of loss on a
    portfolio which is expected to be equaled or
    exceeded with a given, small probability.
  • A quantile associated with the bad tail of a
    distribution (e.g., 85th percentile)
  • A time period (e.g., overnight)
  • A reference point (e.g., todays value of the
    portfolio)

Issues with Risk Measures
35
Risk Paradoxes
  • Assume a reference point of zero
  • Two values of outcome, a loss of 0.00 and a loss
    of 1.00
  • Ten futures

!??
Metrics
Issues with Risk Measures
36
Overview
  • The Regional portfolio model
  • Council risk metric
  • Discussion of uncertainty specific to carbon risk

37
CO2 Cost
  • May 2003 Advisory Committee Meeting
  • Characterizing probabilities where no information
    in known
  • Ultimately, used thresholding

38
CO2 Tax
39
CO2 Tax
40
Other EffectsRelated to Carbon Risk
  • Load requirements
  • Hydrogeneration
  • Green Tag Value
  • Production Tax Credits

41
Value of Renewable Energy Credit
  • Applies to more than emerging technologies for
    power generation
  • Will continue to influence power generation
    economics after technologies mature, after carbon
    risk cost is internalized

42
Value of Renewable Energy Credit
43
Production Tax Credits
  • Changing markets
  • As cost of non-fossil fuel technologies improve,
    less support for credits
  • Internalizes external costs

44
Production Tax Credits
45
Production Tax Credits
46
Production Tax Credits
47
Conclusions
  • There are optimal resource choices even when the
    future is uncertain.
  • Decision-makers change course based on outcomes
    to minimize adverse outcomes. Planning needs to
    have and cost exit strategies and contingency
    options.
  • To value exit strategies and contingency options,
    decision-makers need to assign probabilities to
    futures.
Write a Comment
User Comments (0)
About PowerShow.com