Title: Project Interactions
1Project Interactions
2Applying the models
- So far we have discussed simple projects that are
mutually exclusive and made some assumptions - Competing projects have the same lives
- We know the future cash flows with certainty
- Management does not have the ability to make
decisions that change the cash flows after the
project is started. - This chapter expands on the basic decision
variables (NPV, IRR etc) in cases where projects
with different lives are compared, cash flows are
uncertain, and we discuss the value impact of
management.
3Capital Rationing
- Choosing among projects when limited by the
amount of resources available. - Previously we assumed that the firm could
undertake any positive NPV project, however it
may be limited by available resources.
4Spending Limits
- Assume that the company has a limit on the amount
of funds that it believes it can raise. - Example 3 projects Spending limit of 12M
- Project Investment NPV
- A 12,000,000 18,000,000
- B 7,000,000 14,000,000
- C 5,000,000 10,000,000
- Which project(s) should it undertake?
5Using Profitability Index
- Given the spending limits, the firm should also
look at the return per dollar invested. - Project Investment NPV PI
- A 12,000,000 18,000,000 1.5
- B 7,000,000 14,000,000 2.0
- C 5,000,000 10,000,000 2.0
- While B C have a lower NPV individually they
both have a higher profitability index.
6Problems
- Profitability index can be misleading if looked
at alone. - Project Investment NPV PI
- A 10,000,000 14,000,000 1.4
- B 5,000,000 6,000,000 1.2
- C 5,000,000 10,000,000 2.0
- The firm should still look at the total amount of
NPV!
7Problems with Profitability Index
- If more than one constraint is to be rationed
then PI can be misleading. For example, if one
project depends upon another. - Also PI ignores the amount of wealth created.
8Comparing Projects with Unequal Lives
- Replacement Chain Approach
- Repeat projects until they have the same life
span. - Compare a two year project with a four year
project by repeating the two year project
9Comparing Projects with Unequal Lives
- Equivalent Annual Annuity (finding an annualized
NPV) - To Find EA
- find the NPV of the Project
- Use the NPV as the PV of an annuity and solve for
payment - Choose the project with the highest EAA
10Abandonment Decisions
- Often one question is when to stop a project. By
quitting at different points in time the NPV and
EAA will vary due to the changes in salvage
value. - Use EAA and treat each abandonment time as a
separate project.
11Uncertain Cash Flows
- So far we have assumed that we can estimate the
cash flows from the project with certainty. - However, it is difficult to correctly forecast
future cash flows how can the risks associated
with changes in the economic environment and the
difficulties with forecasting cash flows be
accounted for?
12Three Types of Risk
- Stand Alone Risk
- Views project in isolation
- With-in firm (Corporate Risk)
- Looks at the firms portfolio of projects and how
they interact - Market Risk
- Risk from the view of a well diversified
investor.
13Definitions
- Risk
- Exposure to a chance of injury or loss
- Probability
- The likelihood an event occurs
- Risk vs. Uncertainty
- Risk the probability of the outcome is known
- Uncertainty includes judgment concerning the
probability
14Definitions and Terms Continued
- Objective Prob can measure prob. precisely
- Subjective Prob. Includes judgment or opinion
- Variation Risk We want to look at a range of
possible outcomes
15Issues in Risk Measurement
- Stand Alone Risk is the easiest to measure
- Market Risk is the most important to the
shareholder - To evaluate risk you need three things
- Standard deviation of the projects forecasted
returns - Correlation of the projects forecasted returns
with the firms other assets - Correlation of the projects forecasted returns
with the market
16Issues in Risk Management cont
- Using the numbers in 3) you can find the
corporate beta and market beta coefficient (equal
to ((s/s)r) - Most projects have a correlation with other
projects and a coefficient lt 1 - Most projects are positively correlated with the
market with coefficient lt 1 - Corporate risk should also be examined
- More important to small business
- Investors may look at things other than market
risk - Firm Stability is important to creditors,
suppliers etc
17Stand Alone Risk (Review)
- The easiest approach to measuring stand alone
risk is to use the standard deviation of the
projects returns. - Just like security analysis you need to be
careful looking at only standard deviation
dont forget coefficient of variation -
18Measuring Stand Alone Risk
- Sensitivity Analysis
- Scenario Analysis
- Monte Carlo Simulation
19Sensitivity Analysis
- Looks at the change in your decision variable
(NPV or IRR) when one input changes. - For example what if the cost of capital changes
(or sales or salvage value of the equipment or)
20Example 1 Change ONLY cost of capital
- Time CF
- 0 -5000
- 1 4000
- 2 4000
- 3000
- NPV _at_ 10 4196.09
- NPV _at_ 11 4043.67
- NPV _at_ 9 4352.99
21Example 2 change ONLYfuture cash flows
- Time CF CF 10 CF 10
- 0 -5000 -5000 -5000
- 1 4000 4400 3600
- 2 4000 4400 3600
- 3000 3300 2700
- NPV_at_10 4196.09 5155.70
3276.48
22Sensitivity Analysis
- Usually the results are represented in a table
where the response of the decision variable to
changes in more than one individual variable are
reported. - Then you can compare across variables to see
which one has the largest impact on your decision
23Example Results
- NPV When there is a change in
- Change from Cost of Future
- Base Case Capital Cash Flows
- -10 4352.99 3276.48
- Base 4196.09 4196.09
- 10 4043.67 5115.70
156.90
919.61
152.42
919.61
24Sensitivity Analysis
- Benefits
- Easy to Calculate and Understand
- Measures risk associated with individual inputs
- Weaknesses
- Ignores probability of event
- Ignores interaction among the variables
- Ignores gains from diversification
25Scenario Analysis
- Differences from Sensitivity Analysis
- Allows you to change more than one variable at a
time - Look at a group of scenarios (best case, base
case, and worst case) for example worst case
what if all variables change against us by 20. - Includes probability estimates of each scenario
26Scenario Analysis
- Now let both the future cash flows and the cost
of capital change. - Worst Case Scenario Best Case Scenario
- (WACChCFi) (WACCiCFh)
- -5000 -5000
- 3600 4400
- 3600 4400
- 2700 3300
- NPV_at_11 3139.30 NPV _at_ 9 5288.29
27Scenario Analysis
- Now let both the future cash flows and the cost
of capital change. - Scenario NPV
- Worst (WACChCFi) 3139.30
- Base 4196.09
- Best (WACCiCFh) 5288.29
28Scenario Analysis
- Given the NPV and Probability you can find the
expected NPV and standard deviation - Scenario NPV Prob. NPV(Prob)
- Worst 3193.30 .25 784.825
- Base 4196.09 .50 2,098.045
- Best 5288.29 .25 1,322.0725
- Expected NPV 4,204.94
- Standard Deviation 741.38
29Interpreting the Results
- The project has an expected return on 4204.94
with standard deviation of 741.38 - This implies a 68 confidence interval of
(3463.56 to 4946.32) a large range of possible
outcomes - The coefficient of variation would be .1763 (you
are accepting .1763 units of risk for each unit
of return)
30Scenario Analysis
- Benefits
- More than one variable changes at a time
- Accounts for probability
- Easy to perform
- Weaknesses
- Small number of scenarios is unrealistic
- Probability distributions difficult to estimate
31Monte Carlo Simulation
- A more advanced form of scenario analysis
- Utilizes the computer to make random choices for
each variable input then calculate the expected
return and standard deviation
32Mont Carlo Simulation
- Construct a model of the firms cash flows and
NPVs - Specify a probability distribution for each
uncertain variable (characterized by mean and
standard dev) and correlation among variables. - Allow computer to select a random draw form the
distribution for each variable - Calculate NPV (this is one scenario).
- Repeat 3) an 4) (10,000 or 100,000 times) equal
chance of each scenario Calculate expected NPV
and standard deviation.
33Monte Carlo Simulation
- Benefits
- More realistic selection of variables
- Easy to understand results
- Weaknesses
- Only as good as probability estimate and
correlation of variables
34Quick Review
- Sensitivity Analysis Scenario Analysis and Monte
Carlo Simulation were all used to measure stand
alone risk - Each is designed to provide more information
about the uncertainty associated with the project
they do not provide a clear cut decision rule.
35Applying Sensitivity and Scenario Analysis
- In our examples we simplified the problem by
changing the aggregate cash flows. - When evaluating the project, any assumptions
about inputs can change impacting the
incremental cash flows. - A few of many possible examples
- Changes in variable input costs
- Changes in sales
- Changes in tax laws
36Probability Review
- Mutually exclusive events
- If A occurs then B cannot. Example considering
building a new sports arena. There are two sites
North and South. - Prob North .5 Prob South .25
- This implies the prob that the stadium is built
is - .5 .25 .75
37Probability Review 2
- Independent Events
- Example Exxon is considering two drilling sites,
gulf coast and Alaska - P(A) New oil from gulf coast .7
- P(B) Prob of oil in Alaska .4
- Event B No Event B
- (.4) (.6)
- Event A (.7) .28 .42
- No event A (.3) .12 .18
38Probability Review 3
- Dependent Events Prob of one event depends upon
the other - North Side is voting on bonds for the new arena,
80 chance of the bond passing If passed there is
a 60 chance the stadium gets built in North. If
the bonds fail there is a 30 chance that the
stadium gets built in North
39Prob Review 3 cont
- North North
- Selected Rejected
- Bond (.8)(.6) (.8)(.4)
- Passes (.8) .48 .32
- Bond (.2)(.3) (.2)(.7)
- Fails (.2) .06 .14
40Decision Trees
- So far our decision making has ignored the role
of management. - We know that things change as a project
progresses and decision trees attempt to account
for this.
41Project Example
- Peripherals Inc. is considering making a new
copier/printer. - Stage 1 Conduct a market study to investigate
potential sales, cost 500,000 - Stage 2 If sizable market exists at time t1
spend 1,000,000 to build prototype (80 prob) - Stage 3 If it passes all test spend 10,000,000
at time t2 60 prob - Stage 4 Year t 3 to t 6
- High demand (20 prob) 12M in CF each yr
- Avg Demand (60 prob) 5M in CF each yr
- Low Demand (20 prob) 2M in CF each yr
-
42Building the decision tree
- t 0 t 1
- -1,000,000
- 80
- -500,000
- 20
- 0
- Stage 1 and Stage 2 represented on the tree
-
43Building the decision tree
- t 1 t 2
- -10,000,000
- 60
- -1,000,000
- 40
-
- 0
- Stage 2 and Stage 3 represented on the tree
-
44Stage 1 to 3
- t0 t1 t2
-
-10,000,000 - 60
- -1,000,000
- 80
- -500,000 40
- 0
- 20
- 0
45Decision Tree
- Continue to Build the tree (on the board in
class) - When finished find the NPV of each branch and
multiply it times the probability for each branch
to find the expected NPV.
46Real Options
- Opportunities arise that present the management
with the ability to make a choice. The decision
points in the above decision tree represent this. - For example At time t2, if we realize that the
project is going to produce only - -2,000,000 each year we would not proceed with
the project. There is an option to abandon the
project.
47Real Options
- Three main components
- Determining the value of a real option.
- Identifying the optimal response to changing
conditions. - Structuring projects to create real options.
48Valuing a Real Option Using the Decision Tree
- In the earlier decision tree. Assume we can
abandon the project if we find out that it is
going to result in 2,000,000 CF each year. - We would need to recalculate the NPV of that
branch without the 2,000,000 CFs - NPV -9,364,795.92
- instead of 14,207,508.52
- The total NPV is then 1,235,339.21 instead of
770,438.80 an increase of 464,900.41
49Other Benefits
- If the reduction in uncertainty decreases the
risk the firm can lower the WACC increasing the
NPV even further. - The key is building the decision points into the
capital budgeting process from the beginning
50Real Options and Financial Management
- Flexibility Option -- Switch inputs during the
production process. - Capacity options Ability to manage capacity in
response to changing economic conditions. - New Product Options May accept initial negative
NPV if it allows rights to future goods. - Timing Options Allow you to postpone or
increase production.
51Value of Real Options
- In each case the option can add value to the
project. - You would want to compare the added value of the
option to the cost of implementing the option. - Example it costs an extra 10Million to build a
plant that could allow inputs to be switched.
Given the volatility in the price of the inputs
you estimate the real option to switch inputs is
worth 20 Million
52Characteristics of Real Options
- Real options often increase the value of a
project - The value of most real options increases
- As the longer the amount of time that exists
before the option needs to be exercised increases - The source of risk becomes more volatile
- If interest rates increase.
53Options
- Call Option the right to buy an asset at some
point in the future for a designated price. - Put Option the right to sell an asset at some
point in the future at a given price
54Call Option Profit
- Call option as the price of the asset increases
the option is more profitable. - Once the price is above the exercise price
(strike price) the option will be exercised - If the price of the underlying asset is below the
exercise price it wont be exercised you only
loose the cost of the option. - The Profit earned is equal to the gain or loss on
the option minus the initial cost.
55Profit Diagram Call Option
S-X-C
S
X
56 Call Option Intrinsic Value
- The intrinsic value of a call option is equal to
the current value of the underlying asset minus
the exercise price if exercised or 0 if not
exercised. - In other words, it is the payoff to the investor
at that point in time (ignoring the initial cost)
- the intrinsic value is equal to
- max(0, S-X)
57Payoff Diagram Call Option
S-X
X
S
X
58Put Option Profits
- Put option as the price of the asset decreases
the option is more profitable. - Once the price is below the exercise price
(strike price) the option will be exercised - If the price of the underlying asset is above the
exercise price it wont be exercised you only
loose the cost of the option.
59Profit Diagram Put Option
X-S-C
S
X
60 Put Option Intrinsic Value
- The intrinsic value of a put option is equal to
exercise price minus the current value of the
underlying asset if exercised or 0 if not
exercised. - In other words, it is the payoff to the investor
at that point in time (ignoring the initial cost)
- the intrinsic value is equal to
- max(X-S, 0)
61Payoff Diagram Put Option
X-S
S
X
62Pricing an Option
- Black Scholes Option Pricing Model
- Based on a European Option with no dividends
- Assumes that the prices in the equation are
lognormal.
63Inputs you will need
- S Current value of underlying asset
- X Exercise price
- t life until expiration of option
- r riskless rate
- s2 variance
64PV and FV in continuous time
- e 2.71828 y lnx x ey
- FV PV (1k)n for yearly compounding
- FV PV(1k/m)nm for m compounding periods per
year - As m increases this becomes
- FV PVern PVert let t n
- rearranging for PV PV FVe-rt
65Black Scholes
- Value of Call Option SN(d1)-Xe-rtN(d2)
- S Current value of underlying asset
- X Exercise price
- t life until expiration of option
- r riskless rate
- s2 variance
- N(d ) the cumulative normal distribution (the
probability that a variable with a standard
normal distribution will be less than d)
66Black Scholes (Intuition)
- Value of Call Option
- SN(d1) - Xe-rt N(d2)
- The expected PV of cost Risk Neutral
- Value of S of investment Probability of
- if S gt X S gt X
-
67Black Scholes
- Value of Call Option SN(d1)-Xe-rtN(d2)
- Where
-
68Application to Real Options
- Investment
- Option Real Option
- Stock Price PV of projects Cash Flows
- Exercise Price Expenditure required to
acquire projects assets - Time to Expire Length of time the decision
can be deferred - Variance Riskiness of projects assets
69Example
- Disney Can spend 100M to create a Spanish
version of the Disney channel - PV of future CFs 80M
- Initial investment 100M
- The resulting NPV of the project is
- 80M 100M -20 Million
70A Real Option
- Assume the expansion will provide political
connections resulting in an advantage if they
expand into South America. Assume the expansion
would cost 150M and could be taken at any time
over the next ten years The firm believes that
the NPV of expanding is 100M. - S 100M X 150M r .065 Variance .40
71Plugging into the Black Scholes Model
- Value of Call Option SN(d1)-Xe-rtN(d2)
- 100(.8648) 150e(-.065)(10)(.435)
- 52.3 Million
- Original NPV 80M 100M - 20M
- Add the value of the option Total Value of
Project - -20M52.3 32.3M
72Put Option
- The black scholes value is similar for a put
option - Value of put option Xe-rtN(-d2)-SN(-d1)
73Option to Abandon
- An example of a real option that corresponds to a
put option would be an option to abandon a
project in the future.
74Developing Prob Estimates
- History What happened last year
- Experiments Test programs, market surveys etc
- Judgment Subjective adjustment
75Structuring Project Cash Flows to Help Manage
Risk
- Variable and Fixed Costs
- Pricing Strategy
- Sequential Investment
- Financial Leverage
76Measuring Corporate and Market Risk
- Corporate and Market betas