Title: Procurement Systems
1Procurement Systems
The organisational structure adopted by the
client for the management of the design and
construction of a building project Masterman,
An introduction to building procurement systems,
Spon.
ARBE121 PROCUREMENT OPTIONS
2The need for different procurement routes
- Differing project objectives
- Time, Cost and Quality aims
- Differing clients
- Degree of involvement, risk attitudes,
experience - Operating in a changing environment
- Political, economic, legal etc
- No single route will suit all circumstances
ARBE121 PROCUREMENT OPTIONS
3The key variables in the procurement process
- Design control
- Who employs/directs the designers?
- Usually a choice between client contractor
- Constructors involvement
- When do you employ the contractors?
- Usual choice is between when outline design is
complete or when design is finally complete - Contract to construct or to manage construction?
- Who employs the subcontractors?
ARBE121 PROCUREMENT OPTIONS
4The key variables in the procurement process
- Team selection
- Competition or negotiation for selection?
- Open or selected tendering?
- Paying for the construction
- Pay on Price or Cost?
- Price contractor tenders to do work for a
total amount estimated costs profit
overheads /- risk adjustments - Cost contractor tenders to do the work for
actual costs (calculated as work proceeds)
allowance for profit etc - Pay in timed instalments or on completion of
stages?
ARBE121 PROCUREMENT OPTIONS
5The key variables in the procurement process
- Form of contract used
- Contracts specify obligations of parties to one
another client designers, client
contractor, contractor subcontractor etc - Main variation in client/contractor contract
- Main choice influenced by basic procurement
route used - Standard forms exist for most routes e.g. JCT
Forms - Modification of contracts is common to suit
strong partys requirements
ARBE121 PROCUREMENT OPTIONS
6The available routes
- The range of options
- In excess of 100 recognised variants
- In fact permutations are infinite
- Better to treat options as lying on continuous
spectra of the procurement variables - The most common routes
- Four systems dominated the UK industry in recent
times - Traditional, Design Build, Management
Contracting Construction Management
ARBE121 PROCUREMENT OPTIONS
7The Traditional or conventional route
- The process
- Client employs designers to produce complete
design - Contractor tenders on PRICE after design
complete - Tenders sought typically on competitive,
selected basis - Often lowest price wins
- Winning contractor carries out construction
through employed sub- contractors - Client pays price in monthly instalments based
on amount of work done
ARBE121 PROCUREMENT OPTIONS
8The Traditional or conventional route
- Advantages
- Client retains good control of design process
- Widely used - all parties understand roles etc
- Fairly even split of financial risk between main
parties - Cost certain after tender and tenders easily
comparable - Disadvantages
- Slow because design and construction sequential
- Contractors expertise not used in design
- Creates sides potential for adversarial
attitudes, conflict
ARBE121 PROCUREMENT OPTIONS
9The Traditional or conventional route
- Variants
- Subcontractors may be nominated specified by
client potential for divided loyalties, blurs
responsibilities - Accelerated tenders sought on outline design
may be quicker but cost certainty lost, time
pressures on design etc
ARBE121 PROCUREMENT OPTIONS
10The design build route
- The process
- Client employs designers to produce outline
design - Contractor tenders PRICE to complete design and
perform construction - Tendering usually competitive selected best
overall submission should win price, design,
programme etc - Winning contractor carries out design and
construction through employed design consultants
and sub-contractors - Client pays price in monthly instalments as
traditional - Significant shift in risk to contractor c.f.
Traditional
ARBE121 PROCUREMENT OPTIONS
11The design build route
- Advantages
- Design construction overlapped rapid
procurement - Contractors expertise influences design cost
savings - Early cost certainty possible
- Client has single point of contact with team
- Disadvantages
- Client relinquishes control over design
quality problems? - Client changes difficult after contract let
- Adversarial attitudes remain, perhaps worse
than traditional
ARBE121 PROCUREMENT OPTIONS
12The design build route
- Variants
- Client may require contractor to employ same
design team as client employed Novation
potential conflict of interest, blurs
responsibility, authority etc - Tenders may be sought on Guaranteed Maximum
Price basis redistributes risk as savings may
be split between parties. Arriving at the right
Maximum is the key issue. - Most extreme form Package or Turnkey
approach. Contractor provides full service ALL
design, even finding site, finance etc in some
cases.
ARBE121 PROCUREMENT OPTIONS
13The management contracting route
- The process
- Client employs designers to produce outline
design - Contractor tenders on estimated COST to perform
construction fee to manage process - Tendering usually competitive selected
- Best overall submission should win fee,
management, programme, track record etc - Winning contractor joins team advises
designers in completion of design, organises
construction in parallel by employing works
package contractors - Client pays COST of packages fee on monthly
basis
ARBE121 PROCUREMENT OPTIONS
14The management contracting route
- Advantages
- Design construction overlapped rapid
procurement - Contractors expertise influences design cost
savings - Contractor in team reduces adversarial nature of
process - Client retains control of design
- Late changes in design can be accommodated
- Disadvantages
- Client assumes high level of TCQ performance
risk - Client involvement high
- Possible time pressures on design
ARBE121 PROCUREMENT OPTIONS
15The construction management route
- The process
- Same as management contracting except that
client employs each package contractor directly - Advantages
- Client can exercise high degree of control over
entire procurement process - Disadvantages
- Client share of risk is even higher than MC
- Client commitment/involvement is very high
ARBE121 PROCUREMENT OPTIONS
16Further reading
- Many texts give general descriptions of the
procurement routes and associated contracts as
part of coverage of the industry e.g. Chapters 7
8 of Harvey Ashworth, The construction
industry of GB, Newnes and Chapter 6 of Cadman
Topping, Property development, Spon. - More detailed consideration of the routes can be
found in Masterman, An introduction to building
procurement systems, Spon and Franks, Building
procurement systems, Spon. - Murdoch Hughes, Construction contracts law
and management, Spon.As its name suggests gives
an in-depth coverage of the legal aspects and
case law etc
ARBE121 - PROCUREMENT OPTIONS