Procurement Systems - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Procurement Systems

Description:

Masterman, An introduction to building procurement systems, Spon. ... team as client employed 'Novation' potential conflict of interest, blurs ... – PowerPoint PPT presentation

Number of Views:652
Avg rating:3.0/5.0
Slides: 17
Provided by: mrjl9
Category:

less

Transcript and Presenter's Notes

Title: Procurement Systems


1
Procurement Systems
The organisational structure adopted by the
client for the management of the design and
construction of a building project Masterman,
An introduction to building procurement systems,
Spon.
ARBE121 PROCUREMENT OPTIONS
2
The need for different procurement routes
  • Differing project objectives
  • Time, Cost and Quality aims
  • Differing clients
  • Degree of involvement, risk attitudes,
    experience
  • Operating in a changing environment
  • Political, economic, legal etc
  • No single route will suit all circumstances

ARBE121 PROCUREMENT OPTIONS
3
The key variables in the procurement process
  • Design control
  • Who employs/directs the designers?
  • Usually a choice between client contractor
  • Constructors involvement
  • When do you employ the contractors?
  • Usual choice is between when outline design is
    complete or when design is finally complete
  • Contract to construct or to manage construction?
  • Who employs the subcontractors?

ARBE121 PROCUREMENT OPTIONS
4
The key variables in the procurement process
  • Team selection
  • Competition or negotiation for selection?
  • Open or selected tendering?
  • Paying for the construction
  • Pay on Price or Cost?
  • Price contractor tenders to do work for a
    total amount estimated costs profit
    overheads /- risk adjustments
  • Cost contractor tenders to do the work for
    actual costs (calculated as work proceeds)
    allowance for profit etc
  • Pay in timed instalments or on completion of
    stages?

ARBE121 PROCUREMENT OPTIONS
5
The key variables in the procurement process
  • Form of contract used
  • Contracts specify obligations of parties to one
    another client designers, client
    contractor, contractor subcontractor etc
  • Main variation in client/contractor contract
  • Main choice influenced by basic procurement
    route used
  • Standard forms exist for most routes e.g. JCT
    Forms
  • Modification of contracts is common to suit
    strong partys requirements

ARBE121 PROCUREMENT OPTIONS
6
The available routes
  • The range of options
  • In excess of 100 recognised variants
  • In fact permutations are infinite
  • Better to treat options as lying on continuous
    spectra of the procurement variables
  • The most common routes
  • Four systems dominated the UK industry in recent
    times
  • Traditional, Design Build, Management
    Contracting Construction Management

ARBE121 PROCUREMENT OPTIONS
7
The Traditional or conventional route
  • The process
  • Client employs designers to produce complete
    design
  • Contractor tenders on PRICE after design
    complete
  • Tenders sought typically on competitive,
    selected basis
  • Often lowest price wins
  • Winning contractor carries out construction
    through employed sub- contractors
  • Client pays price in monthly instalments based
    on amount of work done

ARBE121 PROCUREMENT OPTIONS
8
The Traditional or conventional route
  • Advantages
  • Client retains good control of design process
  • Widely used - all parties understand roles etc
  • Fairly even split of financial risk between main
    parties
  • Cost certain after tender and tenders easily
    comparable
  • Disadvantages
  • Slow because design and construction sequential
  • Contractors expertise not used in design
  • Creates sides potential for adversarial
    attitudes, conflict

ARBE121 PROCUREMENT OPTIONS
9
The Traditional or conventional route
  • Variants
  • Subcontractors may be nominated specified by
    client potential for divided loyalties, blurs
    responsibilities
  • Accelerated tenders sought on outline design
    may be quicker but cost certainty lost, time
    pressures on design etc

ARBE121 PROCUREMENT OPTIONS
10
The design build route
  • The process
  • Client employs designers to produce outline
    design
  • Contractor tenders PRICE to complete design and
    perform construction
  • Tendering usually competitive selected best
    overall submission should win price, design,
    programme etc
  • Winning contractor carries out design and
    construction through employed design consultants
    and sub-contractors
  • Client pays price in monthly instalments as
    traditional
  • Significant shift in risk to contractor c.f.
    Traditional

ARBE121 PROCUREMENT OPTIONS
11
The design build route
  • Advantages
  • Design construction overlapped rapid
    procurement
  • Contractors expertise influences design cost
    savings
  • Early cost certainty possible
  • Client has single point of contact with team
  • Disadvantages
  • Client relinquishes control over design
    quality problems?
  • Client changes difficult after contract let
  • Adversarial attitudes remain, perhaps worse
    than traditional

ARBE121 PROCUREMENT OPTIONS
12
The design build route
  • Variants
  • Client may require contractor to employ same
    design team as client employed Novation
    potential conflict of interest, blurs
    responsibility, authority etc
  • Tenders may be sought on Guaranteed Maximum
    Price basis redistributes risk as savings may
    be split between parties. Arriving at the right
    Maximum is the key issue.
  • Most extreme form Package or Turnkey
    approach. Contractor provides full service ALL
    design, even finding site, finance etc in some
    cases.

ARBE121 PROCUREMENT OPTIONS
13
The management contracting route
  • The process
  • Client employs designers to produce outline
    design
  • Contractor tenders on estimated COST to perform
    construction fee to manage process
  • Tendering usually competitive selected
  • Best overall submission should win fee,
    management, programme, track record etc
  • Winning contractor joins team advises
    designers in completion of design, organises
    construction in parallel by employing works
    package contractors
  • Client pays COST of packages fee on monthly
    basis

ARBE121 PROCUREMENT OPTIONS
14
The management contracting route
  • Advantages
  • Design construction overlapped rapid
    procurement
  • Contractors expertise influences design cost
    savings
  • Contractor in team reduces adversarial nature of
    process
  • Client retains control of design
  • Late changes in design can be accommodated
  • Disadvantages
  • Client assumes high level of TCQ performance
    risk
  • Client involvement high
  • Possible time pressures on design

ARBE121 PROCUREMENT OPTIONS
15
The construction management route
  • The process
  • Same as management contracting except that
    client employs each package contractor directly
  • Advantages
  • Client can exercise high degree of control over
    entire procurement process
  • Disadvantages
  • Client share of risk is even higher than MC
  • Client commitment/involvement is very high

ARBE121 PROCUREMENT OPTIONS
16
Further reading
  • Many texts give general descriptions of the
    procurement routes and associated contracts as
    part of coverage of the industry e.g. Chapters 7
    8 of Harvey Ashworth, The construction
    industry of GB, Newnes and Chapter 6 of Cadman
    Topping, Property development, Spon.
  • More detailed consideration of the routes can be
    found in Masterman, An introduction to building
    procurement systems, Spon and Franks, Building
    procurement systems, Spon.
  • Murdoch Hughes, Construction contracts law
    and management, Spon.As its name suggests gives
    an in-depth coverage of the legal aspects and
    case law etc

ARBE121 - PROCUREMENT OPTIONS
Write a Comment
User Comments (0)
About PowerShow.com