Title: DEX Publication Project
1- DEX Publication Project
- OASIS PLCS TC Telecon
- 22 January 2008
- Trine Hansen
2Overall object
- 2 DEXs ready for publication 1 March 08 including
- Templates
- Reference data
- Minimum sub-set of Info pages documents ready for
publication by 1 March 08
3Project main activities
- The following slides report status and progress
for each main activity per 22 January 08
4Activity 1 - Management
- Runs as planned
- Reminded OASIS (Mary McRae) about more feedback
on our publication format. Awaits final
acceptance ? see next slide.
5Activity 1 ManagementPublication format
Preliminary Feedback from OASIS
- E-mail received 29 November 07 from Mary McRea
- The frame with the PLCS logo that would need to
go basically the page could just shift left - The cover page information would need to be
changed so that the title has a real version
number (Version 1.0, Version 6.3.2, whatever you
like) - The stage (where you have Developer Draft)
would need to be Committee Draft 01 (assuming
this has been approved by the TC members). The
date of approval would then appear below that. - The file name OASIS_cover, while legal, is
pretty nondescript maybe dexlib-v1-index? (just
a suggestion) - The appendices should most likely be on a
separate page and just linked through the TOC so
it doesnt appear like an empty document. - Ill send more details later, but I think youre
just about ready to go!
6Activity 2 - Core Team Activities
- This activity runs according to plan
- High activity these days
7Activity 3 TOG Support Management
- Identifies OASIS requirements for having the DEXs
ready for publication - Completed (Ref. DEX Publication format)
- Discuss procedures for handling request for
external support such as training and consultancy
services - Not started. Low priority these days.
- Requirements for tool support of future TOG
management activities will also be identified - Not started. Low priority these days.
8Activity 4 Check lists and Processes
- Nothing new to report on Checklists
- Completed checklists
- Templates
- Checklists not completed
- Reference data on-going
- DEX on-going
- Capabilities (established, but has to be updated)
- PLCS Information Pages in DEXLib
- Established but not completed
Critical for Aviation M DEX
9Activity 5 DEXLib infrastructure
- This activity runs according to plan
- Consists of sub-activities
- Templates
- Acceptance test plan
- Longform generation
- Part 28 generation
- Business DEXs
- Business Objects
- Release environment
- Usage reporting tool
- General maintenance
- Configuration change management
- Configuration management of reference data
- Publication as standards
Acceptance test 26 Nov 07
10Activity 6 - DEXlib Help section
- All information required are available through
DEXLib with a few exceptions (How to read
DEXLib) - Need more systemising
- Need more quality assurance
- Plan forward
- Complete the structuring work
- Publication 1 March 08
- Additional budget for completion of Information
pages was offered by FMV last week. Start date?
11Activity 7 Develop, review and update
templates
- Funding for all template activities are
identified - A few templates still under development (for the
Task DEX) - Still some templates under development funding
available for completion. All these are related
to the Task DEX - Most templates have been reviewed
- Updates according to review comments on-going
12Activity 8 Develop, review and update
capabilities
13Activity 9 - Develop and harmonize DEXs
- Task DEXs
- Ready for publication 1 March 08
- Harmonization of PLCS solutions finished
- Results
- Aviation Maintenance DEX
- Awaits review checklist from Task DEX activities
- Ready for ballot 1 March 08
14Activity 10 - Review and update DEXs
- Task DEXs
- Review part of harmonization activities
- Formal review not performed Checklist not
completed - Aviation Maintenance DEX
- Business review performed
- Awaits checklist for formal OASIS review
15Activity 11 Preparations for establishing
Implementers Forum
- Prepare a proposal for scope of Implementers
Forum as input to next face-to-face meeting
(action on Tor Arne Irgens, Torbjörn Holm and
Nils Sandsmark )
16Activity 12 Final report
17- Summary We are very close..
18