Title: Capacity Requirement Planning
1Capacity Requirement Planning
2Defining Capacity
- Capacity is the amount of work that can be done
in a period of time - It is usually stated in standard hours of work
- It must be determined at plant, department, and
work center levels.
3Capacity Planning Process
- Determine the capacity available
- Translate the released and planned orders into
capacity required - Sum up capacities required for each work center
- Resolve differences between available capacity
and required capacity
4Determining Capacity Available
- Capacity available is the capability of a system
or resource to produce a quantity of output in a
particular time period. - Available (theoretical) capacity can be
calculated or measured - To calculate available capacity, one needs to
know - Available time
- Utilization
- Efficiency
5Capacity Measurements
- Theoretical capacity
- Demonstrated capacity
- Calculated capacity
6Utilization and Efficiency
Actual Hours
Charged Utilization
Scheduled Available Hours
Standard Hours Earned Efficiency
Actual Hours Charged
7Rated Capacity
- Rated Capacity Available time x Utilization x
Efficiency
8Load Sources
- Open Orders
- MRP - Planned Order Releases
- Other Sources
- Rework
- Excess scrap
- Quality problems
9Routing Data
- Operation identification code
- Operation description
- Planned work center
- Standard setup time
- Standard run time per unit
- Tooling requirements
10Lead-Time Elements
- Queue
- time waiting before operation begins
- Setup
- time getting ready for operation
- Run
- time performing operation
- Wait
- time waiting after operation ends
- Move
- time physically moving between operations
11Adjustments to Capacity or Load
- Increasing Capacity
- Add extra shifts
- Schedule overtime or weekends
- Add equipment and/or personnel
- Reducing Load
- Subcontract work to outside suppliers
- Reduce lot sizes
- Hold work in production control
- Reduce the MPS
- Reducing Capacity
- Eliminate shifts or reduce length of shifts
worked - Reassign personnel temporarily
12Continued
- Increasing Load
- Make items normally purchased or subcontracted
- Release orders early
- Increase lot sizes
- Increase the MPS
- Redistributing the Load
- Use alternate work centers
- Use alternate routings
- Adjust operation start dates forward or backward
in time - Revise the MPS
13Production Activity Control
14Objectives of PAC
- Execute the MPS and MRP
- Optimize use of resources
- Minimize work in process
- Maintain customer service
15PAC Functions
- Plan
- Ensure resources available
- Schedule start and completion dates
- Execute
- Gather relevant shop order information
- Release shop orders
- Control
- Establish and maintain order priority
- Track actual performance
- Monitor and control WIP, lead times, and queues
- Report work center performance
16Data Requirements
- What and how many to produce?
- When parts are needed?
- What operations are needed?
- How much time operations will take?
- How much capacity is available at each work
center?
17Scheduling
- Objectives
- Meet delivery dates
- Effectively use manufacturing resources
- Involves
- Establishing start and finish dates for each
operation needed to complete an order
18Scheduling and Loading Techniques
- Forward scheduling
- Activity starts as soon as the order is received
.regardless of due date - Backward scheduling
- Activities are scheduled back from the due date
- Infinite loading
- Assumes capacity is infinite at any work center
- Finite loading
- Assumes there is a definite limit to capacity at
any work center
19Bottlenecks Management
- Bottlenecks control the throughput of all
products processed by them - Work centers feeding bottlenecks should be
scheduled at the rate the bottlenecks can process - A time buffer inventory should be established
before the bottleneck - Work centers fed by the bottleneck have their
throughput controlled by the bottleneck
20Input/Output Analysis
21Input, Output, Queue, and Capacity
Input Input Input
Queue
Capacity
22Actual Output Less Than Planned Output
Input Input Input
Not enough input? Queues and lead times
increase Insufficient Capacity?
Queue
Capacity
23Actual Input Less Than Planned Output
Input Input Input
Feeding work centers behind schedule Work
released late Late orders
Queue
May run out of work
Capacity
24Actual Output Greater Than Planned Output
Input Input Input
Queue
Excess Capacity
May run out of work
Capacity
25Actual Input Greater Than Planned Input
Input Input Input
Queue
Feeding work centers ahead of schedule Work
released early Queues and lead times will
increase
Capacity
26Actual Output Less than Actual Input
Input Input Input
Queue
Preceding work centers ahead Releases early
Queues and lead times increase Not enough
capacity?
Capacity
27Actual Output greater Than Actual Input
Input Input Input
Feeding centers behind Releases late Idle
capacity Late orders
Queue
May run out of work
Capacity