Capacity planning - PowerPoint PPT Presentation

About This Presentation
Title:

Capacity planning

Description:

Capacity planning Capacity is the maximum output rate of a production or service facility Capacity planning is the process of establishing the output rate that may be ... – PowerPoint PPT presentation

Number of Views:103
Avg rating:3.0/5.0
Slides: 27
Provided by: Preferr1221
Category:

less

Transcript and Presenter's Notes

Title: Capacity planning


1
  • Capacity planning

2
  • Capacity is the maximum output rate of a
    production or service facility
  • Capacity planning is the process of establishing
    the output rate that may be needed at a facility
  • Strategic issues(long term) how much and when to
    spend capital for additional facility equipment
  • Tactical issues(short term) workforce
    inventory levels, day-to-day use of equipment

3
Measuring Capacity Examples
  • There is no one best way to measure capacity
  • Output measures are easier to understand
  • With multiple products, inputs measures work
    better

4
Capacity Information Needed
  • Design capacity
  • Maximum output rate under ideal conditions
  • A bakery can make 30 custom cakes per day when
    pushed at holiday time
  • Effective capacity
  • Maximum output rate under normal (realistic)
    conditions
  • On the average this bakery can make 20 custom
    cakes per day

5
Calculating Capacity Utilization
  • Measures how much of the available capacity is
    actually being used
  • Measures effectiveness
  • Use either effective or design capacity in
    denominator

6
Example of Capacity Utilization
5-6
  • During one week of production, a plant produced
    83 units of a product. Its historic highest or
    best utilization recorded was 120 units per week.
    What is this plants capacity utilization rate?
  • Answer
  • Capacity utilization rate Capacity
    used
  • Best operating
    level
  • 83/120
  • 0.69 or 69

7
(No Transcript)
8
Example of Computing Capacity Utilization In the
bakery example the design capacity is 30 custom
cakes per day. Currently the bakery is producing
28 cakes per day. What is the bakerys capacity
utilization relative to both design and effective
capacity?
9
Example
  • If operated around the clock under ideal
    conditions, the fabrication department of an
    engine manufacturer can make 100 engines per day.
    Management believes that a maximum output rate of
    only 45 engines per day can be sustained
    economical over a long period of time. Currently,
    the department is producing an average of 50
    engines per day. What is the utilization of the
    department relative to peak capacity? Effective
    capacity?

10
How Much Capacity Is Best?
  • The Best Operating Level is the output that
    results in the lowest average unit cost
  • Economies of Scale
  • Where the cost per unit of output drops as volume
    of output increases
  • Spread the fixed costs of buildings equipment
    over multiple units, allow bulk purchasing
    handling of material
  • Diseconomies of Scale
  • Where the cost per unit rises as volume increases
  • Often caused by congestion (overwhelming the
    process with too much work-in-process) and
    scheduling complexity

11
Best Operating Level and Size
  • Alternative 1 Purchase one large facility,
    requiring one large
  • initial investment
  • Alternative 2 Add capacity incrementally in
    smaller chunks as
  • needed

12
Economies Diseconomies of Scale
5-12
13
Capacity strategies
  • Sizing capacity cushions
  • Timing and sizing expansion
  • Operating decisions

14
Capacity cushion
  • The capacity cushion is the amount of reserve
    capacity that a firm maintains to handle sudden
    increases in demand or temporary losses of
    production capacity.
  • It measures the amount by which the average
    utilization (in terms of effective capacity)
    falls below 100 percent.
  • Capacity cushion 100 - Utilization rate ()

15
When to expand and by how much?
  • The timing and sizing of expansion are related.
    If demand is increasing and the time between
    increments increases, the size of the increments
    must also increase.
  • Expansionist strategy
  • which stays ahead of demand, minimizes the chance
    of sales lost to insufficient capacity.
  • Wait-and-see strategy
  • lags behind demand, relying on short-term options

16
  • Estimate capacity requirements(Single Machine)
  • Processing hours required for years demand
  • Hours available from one machine per year after
    deducting the desired cushion
  • Estimate capacity requirements(Multiple M/c)
  • Sum of Processing setup hours required for
    years demand for each product
  • Hours available from one machine per year after
    deducting the desired cushion

17
  • Estimate capacity requirements (Single M/c)
  • MD p /N1-C/100)
  • Where
  • M no of machines required for single process
  • D number of units (customers) forecast per
    year
  • p processing time (in hours per unit or
    customers)
  • N total number of hours per year during which
    the process operates
  • C desired capacity cushion

18
Estimate capacity requirements
  • MDp(D/Q)Sproduct1 Dp(D/Q)Sproduct2
    .. Dp(D/Q)Sproductn

  • N1-C/100)
  • Where
  • M no of machines required for multiple process
  • D number of units (customers) forecast per
    year
  • p processing time (in hours per unit or
    customers)
  • N total number of hours per year during which
    the process operates
  • C desired capacity cushion
  • Q number of units in each lot
  • s setup time (in hours) per lot

19
Example
  • A copy center in an office building prepares
    bound reports for two clients. The center makes
    multiple copies (the lot size) of each report.
    The processing time to run, collate, and bind
    each copy depends on, among other factors, the
    number of pages. The center operates 250 days per
    year, with an eight hours shift. Management
    believes that a capacity cushion of 15 is best.
    It currently has 3 copy machines. Based on the
    following table of information, determine how
    many machines are needed at the copy center.
  • Item Client X Client Y
  • Annual demand forecast (copies) 2000 6000
  • Standard processing time (hour/copy) 0.5 0.7
  • Average lot size (copies per report) 20
    30
  • Standard setup time (hours) 0.25 0.40

20
Identify Gaps
  • A capacity gap is any difference (positive or
    negative) between projected demand and current
    capacity. Identifying gaps requires use of the
    correct capacity measure. Complications arise
    when multiple operations and several resource
    inputs are involved.
  • In 1970 when airline executive states fly more
    seats to get more passengers many airlines
    responded by buying more jumbo jets, but
    competitors flying smaller planes were more
    successful. The correct measure of capacity was
    the number of departments rather than the number
    of seats.

21
Step 2 Identify Gaps
  • A restaurant is experiencing a boom in business.
    The owner expects to
  • serve a total of 80,000 meals this year. Although
    the kitchen is operating
  • at 100 percent capacity, the dining room can
    handle a total of 1,05,000
  • dinners per year. Forecasted demand for the next
    five years is as
  • follows
  • Year 1 90,000 meals
  • Year 2 1,00,000 meals
  • Year 3 1,10,000 meals
  • Year 4 1,20,000 meals
  • Year 5 1,30,000 meals
  • What are the capacity gaps in the restaurants
    kitchen and dining room
  • through year 5?

22
Develop alternatives
  • The next step is to develop alternative plans
  • to cope with projected gaps.
  • One alternative is base case, which is do
    nothing and simply lose orders from any demand
    that exceeds current capacity.
  • Other alternatives are various timing and sizing
    options for adding new capacity, including the
    expansionist and wait-and-see strategies.

23
Tools for Capacity Planning
  • Waiting Line Model
  • Simulation
  • Decision Tree

24
Example
5-24
A glass factory specializing in crystal is
experiencing a substantial backlog, and the
firm's management is considering three courses of
action A) Arrange for subcontracting B)
Construct new facilities C) Do nothing (no
change) The correct choice depends largely upon
demand, which may be low, medium, or high. By
consensus, management estimates the respective
demand probabilities as 0.1, 0.5, and 0.4.
25
5-25
The management also estimates the profits when
choosing from the three alternatives (A, B, and
C) under the differing probable levels of demand.
These profits, in thousands of dollars are
presented in the table below
26
Example Good Eats Café
  • Good Eats Café is about to build a new
    restaurant. An architect has developed three
    building designs, each with a different seating
    capacity. Good Eats estimates that the average
    number of customers per hour will be 80, 100, or
    120 with respective probabilities of 0.4, 0.2,
    and 0.4. The payoff table showing the profits
    for the three designs is on the next slide.
  • Payoff Table
  • Average Number of Customers Per Hour
  • c1 80 c2
    100 c3 120
  • Design A 10,000 15,000
    14,000
  • Design B 8,000 18,000
    12,000
  • Design C 6,000 16,000
    21,000
Write a Comment
User Comments (0)
About PowerShow.com