Title: Capacity planning
1 2- Capacity is the maximum output rate of a
production or service facility - Capacity planning is the process of establishing
the output rate that may be needed at a facility - Strategic issues(long term) how much and when to
spend capital for additional facility equipment - Tactical issues(short term) workforce
inventory levels, day-to-day use of equipment
3Measuring Capacity Examples
- There is no one best way to measure capacity
- Output measures are easier to understand
- With multiple products, inputs measures work
better
4Capacity Information Needed
- Design capacity
- Maximum output rate under ideal conditions
- A bakery can make 30 custom cakes per day when
pushed at holiday time - Effective capacity
- Maximum output rate under normal (realistic)
conditions - On the average this bakery can make 20 custom
cakes per day
5Calculating Capacity Utilization
- Measures how much of the available capacity is
actually being used - Measures effectiveness
- Use either effective or design capacity in
denominator
6Example of Capacity Utilization
5-6
- During one week of production, a plant produced
83 units of a product. Its historic highest or
best utilization recorded was 120 units per week.
What is this plants capacity utilization rate?
- Answer
- Capacity utilization rate Capacity
used - Best operating
level -
- 83/120
- 0.69 or 69
7(No Transcript)
8Example of Computing Capacity Utilization In the
bakery example the design capacity is 30 custom
cakes per day. Currently the bakery is producing
28 cakes per day. What is the bakerys capacity
utilization relative to both design and effective
capacity?
9Example
- If operated around the clock under ideal
conditions, the fabrication department of an
engine manufacturer can make 100 engines per day.
Management believes that a maximum output rate of
only 45 engines per day can be sustained
economical over a long period of time. Currently,
the department is producing an average of 50
engines per day. What is the utilization of the
department relative to peak capacity? Effective
capacity?
10How Much Capacity Is Best?
- The Best Operating Level is the output that
results in the lowest average unit cost - Economies of Scale
- Where the cost per unit of output drops as volume
of output increases - Spread the fixed costs of buildings equipment
over multiple units, allow bulk purchasing
handling of material - Diseconomies of Scale
- Where the cost per unit rises as volume increases
- Often caused by congestion (overwhelming the
process with too much work-in-process) and
scheduling complexity
11Best Operating Level and Size
- Alternative 1 Purchase one large facility,
requiring one large - initial investment
- Alternative 2 Add capacity incrementally in
smaller chunks as - needed
12Economies Diseconomies of Scale
5-12
13Capacity strategies
- Sizing capacity cushions
- Timing and sizing expansion
- Operating decisions
14 Capacity cushion
- The capacity cushion is the amount of reserve
capacity that a firm maintains to handle sudden
increases in demand or temporary losses of
production capacity. - It measures the amount by which the average
utilization (in terms of effective capacity)
falls below 100 percent. - Capacity cushion 100 - Utilization rate ()
15When to expand and by how much?
- The timing and sizing of expansion are related.
If demand is increasing and the time between
increments increases, the size of the increments
must also increase. - Expansionist strategy
- which stays ahead of demand, minimizes the chance
of sales lost to insufficient capacity. - Wait-and-see strategy
- lags behind demand, relying on short-term options
16- Estimate capacity requirements(Single Machine)
- Processing hours required for years demand
- Hours available from one machine per year after
deducting the desired cushion
- Estimate capacity requirements(Multiple M/c)
- Sum of Processing setup hours required for
years demand for each product - Hours available from one machine per year after
deducting the desired cushion
17- Estimate capacity requirements (Single M/c)
- MD p /N1-C/100)
- Where
- M no of machines required for single process
- D number of units (customers) forecast per
year - p processing time (in hours per unit or
customers) - N total number of hours per year during which
the process operates - C desired capacity cushion
18 Estimate capacity requirements
- MDp(D/Q)Sproduct1 Dp(D/Q)Sproduct2
.. Dp(D/Q)Sproductn -
N1-C/100) - Where
- M no of machines required for multiple process
- D number of units (customers) forecast per
year - p processing time (in hours per unit or
customers) - N total number of hours per year during which
the process operates - C desired capacity cushion
- Q number of units in each lot
- s setup time (in hours) per lot
19Example
- A copy center in an office building prepares
bound reports for two clients. The center makes
multiple copies (the lot size) of each report.
The processing time to run, collate, and bind
each copy depends on, among other factors, the
number of pages. The center operates 250 days per
year, with an eight hours shift. Management
believes that a capacity cushion of 15 is best.
It currently has 3 copy machines. Based on the
following table of information, determine how
many machines are needed at the copy center. - Item Client X Client Y
- Annual demand forecast (copies) 2000 6000
- Standard processing time (hour/copy) 0.5 0.7
- Average lot size (copies per report) 20
30 - Standard setup time (hours) 0.25 0.40
20 Identify Gaps
- A capacity gap is any difference (positive or
negative) between projected demand and current
capacity. Identifying gaps requires use of the
correct capacity measure. Complications arise
when multiple operations and several resource
inputs are involved. - In 1970 when airline executive states fly more
seats to get more passengers many airlines
responded by buying more jumbo jets, but
competitors flying smaller planes were more
successful. The correct measure of capacity was
the number of departments rather than the number
of seats.
21Step 2 Identify Gaps
- A restaurant is experiencing a boom in business.
The owner expects to - serve a total of 80,000 meals this year. Although
the kitchen is operating - at 100 percent capacity, the dining room can
handle a total of 1,05,000 - dinners per year. Forecasted demand for the next
five years is as - follows
- Year 1 90,000 meals
- Year 2 1,00,000 meals
- Year 3 1,10,000 meals
- Year 4 1,20,000 meals
- Year 5 1,30,000 meals
- What are the capacity gaps in the restaurants
kitchen and dining room - through year 5?
22 Develop alternatives
- The next step is to develop alternative plans
- to cope with projected gaps.
- One alternative is base case, which is do
nothing and simply lose orders from any demand
that exceeds current capacity. - Other alternatives are various timing and sizing
options for adding new capacity, including the
expansionist and wait-and-see strategies.
23Tools for Capacity Planning
- Waiting Line Model
- Simulation
- Decision Tree
24Example
5-24
A glass factory specializing in crystal is
experiencing a substantial backlog, and the
firm's management is considering three courses of
action A) Arrange for subcontracting B)
Construct new facilities C) Do nothing (no
change) The correct choice depends largely upon
demand, which may be low, medium, or high. By
consensus, management estimates the respective
demand probabilities as 0.1, 0.5, and 0.4.
255-25
The management also estimates the profits when
choosing from the three alternatives (A, B, and
C) under the differing probable levels of demand.
These profits, in thousands of dollars are
presented in the table below
26Example Good Eats Café
- Good Eats Café is about to build a new
restaurant. An architect has developed three
building designs, each with a different seating
capacity. Good Eats estimates that the average
number of customers per hour will be 80, 100, or
120 with respective probabilities of 0.4, 0.2,
and 0.4. The payoff table showing the profits
for the three designs is on the next slide.
- Payoff Table
- Average Number of Customers Per Hour
- c1 80 c2
100 c3 120 - Design A 10,000 15,000
14,000 - Design B 8,000 18,000
12,000 - Design C 6,000 16,000
21,000