Title: Designing and manufacturing overhead crane
1Designing and manufacturing overhead crane
- Omar Jaafar Hassan 199900307
- Humaid AL-Marzoqi 200000181
- Khalid AL-Hasani 199900342
- Zayed AL-Katheeri 199900295
- Advisor
- Prof. Kamal A.F.Moustafa
2Crane Mechanism
3Materials Handling
- 1) Picking up the load
- 2) Transporting the load
- 3) Setting the load down
4Importance of cranes
- 1.Avoid Congestion, Delays and unnecessary
handling.2. Improve production operations . - 3. Lower unit Materials handling Cost
5Importance of cranes cont.
- 4. Reduce damage due to Materials handling.
- 5. Maximize space utilization.
- 6. Reduce the accident rate and severity of
injury.
6Type of cranes
- Mobile cranes
- Stationary cranes
7Mobile cranes
- Mounted Cranes
- Crawler-Mounted Cranes
8Mounted Cranes
A wheel-mounted crane is mobile and flexible
crane that can be driven on or off roads over
rough terrain. Advantage small working area.
9Crawler-Mounted Cranes
Stable base. The advantage continuous work in
remote areas
10Stationary cranes
- Bridge Cranes
- Jib Cranes
- Gantry cranes
- Tower Cranes
11Bridge Cranes
- The most important part are girders, trucks, end
ties, walkway and a drive mechanism
12Jib Cranes
- Jib cranes consist of a horizontally mounted
beam, not unlike a monorail, but that can swing
in a semi-circle.
13Gantry cranes
- Bridge crane but with girders that used in free
space.
14Tower Cranes
- Construction crew uses the tower crane to lift
steel, concrete, large tools.
15Main Components of Overhead Crane
- Girder
- Trolley
- Hoist
- Runway Rail
16(No Transcript)
17Safety
- Safety instruction
- Steps to inspect the crane safety
- Maintenance of the overhead crane
18 Safety Instructions
- Loads should not be suspended over personnel
below. - Avoid rapid movements in any direction
19 Safety Instructions
- Do not exceed the rated load capacity of the
crane, hoist, chain, cable, slings, or other
component.
20Steps to inspect the crane safety
- Daily inspection
- Periodic inspection
21 Daily inspection
- Hoisting and lowering
- Trolley travel
- Bridge travel
22Periodic Inspections
- Deformed, cracked or corroded members
- Loose bolts or rivets
- Cracked or distorted parts such as bearings,
gears, rollers, etc - Excessive wear on brake system parts
23Maintenance Requirements
- A preventive maintenance program based on the
crane manufacturers recommendations must be
implemented. - Only specialist engineer may perform the required
maintenance and repairs.
24Procedure of designing
25Designing Techniques
- Newtons Second Law approach
- Lagranges approach
26Newtons Second Law approach
- Assumptions
- Cable is mass less
- The payload is lumped with the hook and
- modeled as a sphere
- The system is frictionless
27Newtons Second Law approach cont. Free body
diagram of the system
28 Newtons Second Law approach cont. Trolley
kinetic
29Newtons Second Law approach cont. Payload
kinetics
Force balance in the horizontal direction
30Newtons Second Law approach cont. Payload
kinetics
Force balance in the vertical direction
31Lagranges Approach
32Lagranges Approach Cont.
Kinetic energy expression
Potential energy expression
33Lagranges Approach Cont.
34State Variable Form
35State Space Form
36MAT-LAB Representation
37Force Behavior
38Displacement Behavior
39Velocity Behavior
40Swing Behavior