Title: CENTRAL PUBLIC WORKS DEPARTMENT
1CENTRAL PUBLIC WORKS DEPARTMENT
- A look at 2006-07
-
- Plans for 2007-08
2FINANCIAL MILESTONES ACHIEVED
Rs. in Crores
3WORK DONE BUT NOT REFLECTED IN WORKLOAD OF
2006-07
- Technical assistance rendered
- 172 DPR for development of urban infrastructure
under JNNURM scheme, valued at Rs. 9955 crore
processed - 405 DPR for works being taken up in North East
and under UIDSSMT, valued at Rs. 3760 crore also
processed - Large number of valuation cases, rent assessment
cases.
4OTHER ACHIEVEMENTS
- Following technical publications have been
brought out in 2006-07, for use by our field
staff and for use by other organizations - Specifications for sub-stations
- Wet riser systems for fire fighting
- Specifications for diesel generating sets
- Schedule of rates for internal electrical
installations
5STOCK TAKING OF WORKS
- Number of works completed during
- 2006-07 3191
- Number of works in progress as on
- 1.4.2007 - 5123
SEBI, Mumbai, 2006
65152 RESIDENTIAL UNITS COMPLETED IN 2006-07
Transit Hostel, Delhi, 2007
7- 84 Non residential buildings having plinth area
of 6 million sq.ft. completed during - 2006-07
IT Tower, Hyderabad 2007
8RPO, Bangalore 2007
9(No Transcript)
10(No Transcript)
110UR ORDER BOOK(CPWD only)
Archeological Survey of India, Kolkata, 2007
- Total number of capital works (i.e. excluding
minor/maintenance works) costing more than Rs. 1
Lakh as on 12.07.2007 is 13497 - Value of these works is Rs. 23,783 crore
CISF, Hyderabad
12MAJOR PROJECTS IN HAND
- Commonwealth Games -2010
- Roads under RSVY PMGSY in Bihar
- Parliament building for Afghanistan in Kabul
- Tsunami Reconstruction Programme
- Border fencing roads along IBB, Indo Pak,
Indo-China - PMSSY health sector
- Married Accommodation Project for MoD
13MAJOR PROJECTS IN HAND
- Indian Chancery, Kabul
- Works for MEA in Beijing, Myanmar, Mauritius
- Inland Waterways (NW 1,2 3)
- Tourism Sector
- Education sector
- Sports tracks, stadiums and other infrastructure
facilities for SAI
14Inside view of proposed Jawaharlal Nehru Stadium
15S.P.Mukherjee Talkatora Stadium Cut Section
Through Roof Showing Different Components
16- Development of 2000 Km. of
- State highways under
- Rashtrya Sam Vikas Yojna
- in 33 districts of Bihar
- (3000 crore)
17(No Transcript)
18RSVY Works in progress
19RSVY Works in progress
20PMGSY117 Roads 1088 Km
21- Proposal for 2500 Km being sent
22PROPOSED PARLIAMENT COMPLEX FOR AFGHANISTAN (400
CRORE)
23Tsunami Reconstruction Programme AN Islands-2007
24SCOPE OF PROJECT FOR CPWD
Name of Islands Type of Construction No. of Permanent Shelters
Hut bay Single Storied 965
Carnicobar Stilt 3369
Chowra Single Storied 376
Teresa Single Storied 506
Nancowry Single Storied 269
Katchal Single Storied 315
Kamorta Single Storied 518
Campbell bay Single Storied 1112
Total 7699
25Carnicobar
26(No Transcript)
27BORDER FENCING AND LIGHTING WORKS
28- Completed during 2006-07
- 33 Km of roads
- 38 Km of new fencing
- Up-gradation of 300 Km of existing
fencing - 184 Km of flood lighting
- 9 Border out posts
29(No Transcript)
30Mechanisation in Border fencing works
31ROADS ALONG INDO-CHINA BORDER
- Uttaranchal
- Ghamsali to Geldung 24 km
- Sonam to PDA 15 km
- PDA to Sumla 05 km
- PDA to Mendi 03 km
- Sela to Tendang 24 km
32ROADS ALONG INDO-CHINA BORDER
- Sikkim (Altitude- 14000-17000ft.)
- Dombang Chaubakha 25 Km
- - Gorala
- Giagong Kerong 24 Km
- - ITBP Post
- Thangu-kugnakla- 13 Km
- - Muthang
33HEALTHPMSSY
- Hospitals being done
- Srinagar
- Jammu
- Varanasi
- Ranchi
34CN Tower, AIIMS-2007
3550 bedded hospital for BSF At Agartala, 2006
36Jetty at Patna For IWAI
37(No Transcript)
38(No Transcript)
39PROMOTING TOURISM
Tomb of Malik Ibrahim, Bihar Sharif, 2006
Huen Tshang Memorial, Nalanda,
2006
40- A very large number of works of Ministry of
Tourism Culture in JK, Assam, Uttaranchal,
Rajasthan, Madhya Pradesh, UP, Gujarat, Bihar,
West Bengal, Tamil Nadu, Haryana, New Delhi,
Kerala, Punjab, Maharashtra etc. are being
executed
Bodh Gaya, 2006
41Illumination of temple at Halebeedu, Karnataka
42Fatehpur Sikri
43Holiday Home, Nainital-2006
44EDUCATION SECTOR
- Large number of works being executed for
- IIT Delhi
- IIT Kharagpur
- IIT Roorkee
- IHMs
- Many Universities and institutions of higher
learning - Schools for JNV and kendrya Vidyalaya Sanghatan
45Library, IIT Roorkee-2006
46IIT, Kharagpur
47EDUCATION
48Hostel Mizoram University, Aizwal 2007
49JNV, Phudong, Sikkim
KV, Joka, Kolkata
50IHM, Srinagar, 2007
IHM, Guwahati, 2006
51RESIDENTIAL ACCOMMODTAION FOR MOD
Sriganganagar, Rajasthan
Jullandhar, Punjab
Janglote, Jammu
52NEW CLIENTS ADDED IN 2006-07
- National Law Institute, Jodhpur
- Advanced Research Centre for Bamboo Rattan,
Guwahati - Vishakhapatnam Steel Plant
- Lakshmi Narsimha Swamy Devsthanam (temple)
Simhachalam, Vizag - Jawaharlal Nehru Industrial Development Bank,
Hyderabad - Jawaharlal Nehru Vishwa Vidyalya, Jabalpur
- Maharishi Sandpani Ved Vidya Prathisthan, Ujjain
- NITs at Hamirpur, Jallandar, Kurukshetra, Raipur,
Durgapur etc. - National Atlas Thematic Organisation
- Contd..
53NEW CLIENTS ADDED IN 2006-07
- JK Tourism
- Gujarat Ayurveda University
- National Institute of Industrial Training, Mumbai
- Centre for Earth Studies
- Indian Institute of Cooperative Management
- National Aerospace Laboratories
- Indian Institute of Astrophysics
- Indian Institute of Science
- IIM
- Gandhi Krishi Vikas Kendra
- ICCR
- ..
54NEW THRUST IN MAINTENANCE
- Repair
- Retrofitting
- Aesthetic improvement
- Enhanced interaction with clients
55REPAIR RETROFITTING
Process
Process
56PROGRAMME FOR AESTHETIC IMPROVMENT
57Government colonies, Delhi
58Type-V quarter Belveder, Kolkata
Before
After
59Council House, Kolkata
5, Esplanade Road, Kolkata
60AESTHETIC IMPROVEMENT OF OFFICE BUILDINGS
61IMPROVED OFFICE ENVIRONMENT
62GLIMPSES OF FEW WORKS COMPLETED IN 2006-07
63NABARD, Lucknow-2006
64Residential accommodation, Lucknow-2006
65Administrative Block, ITBP, Sarhan, 2006
Officers Mess, ITBP, Sarhan, 2006
66Officers Mess, Humhuma, Srinagar-2006
67ITBP, Barracks, Leh-2006
68ITPO Guwahati, 2006
69Positional Astronomy Centre, Kolkata
Admn. Block, Orissa
Admn. Block, BSF, Azadnagar, WB
70DELHI POLICE
71CBSE, Mandawali, Delhi 2006
72Type-VI Bungalow, Pune-2006
73(No Transcript)
74Chitradurga Gramin Bank, Bangalore -2006
75Auditorium for BSF, karnatka-2007
76Proposed Office building For CAG, Raipur, MP
77IDBI, Mumbai
78INCOME TAX QUARTERS, BANDRA KURLA COMPLEX, MUMBAI
WESTERN ZONE I
79(No Transcript)
80SOME MAJOR GPOA/GPRA WORKS IN HAND
- GPOA
- Delhi
- Pushpa Vihar (180 crore)
- Rouse Avenue (100 crore)
- INA (85 crore)
- Shahadra (22 crore)
- Hyderabad (24.0 crore)
- Port Blair
- Silchar
- Cochin (19.80 crore)
81- GPRA
- Delhi
- Rouse Avenue (272 crore)
- Dev nagar ( 175 crore)
- Aliganj (140 crore)
- Vasant Vihar ( 45 crore)
- Bangalore (15.85 crore)
- Shimla (17.26 crore)
- Mumbai (11.95 crore)
82GPOA, Akurdi, Pune-2007
83GPRA at Summer Hill, Simla
84Proposed GPOA, Kavadiguda, Secbad
85PROPSED GPOA Port Blair AN Islands
Perspective View
86MODEL FOR FLATS AT ROUSE AVENUE
87THRUST AREA FOR 2007-08
- Construction
- Mechanization of construction to ensure
- Speed
- Quality
- Introducing improved construction technologies
- Ensuring all new buildings are Green
Sustainable - Maintenance
- Carrying out improvements in existing building
stock - Ensuring better client satisfaction in
maintenance - HRD
- Skill up-gradation of workers by CPWD Training
Institute with help of IGNOU CIDC - General
- Better working environment for engineers
- Early enactment of Engineers Bill
- Passing of a Construction law for India
88Building for Cabinet Secretariat at Delhi
89(No Transcript)
90MODERN FULLY OUTFITTED BUILDINGS
- New buildings designed by CPWD reflect
- Local Architectural practices
- Latest trends in Architecture
- Use latest building materials
- Have building management systems
- Are barrier free
- Have rainwater harvesting systems
- Can be fully outfitted, if required by client
91Income tax office Solan, 2006
92Fully outfitted buildings
93HIDCO BUILDING KOKATA FOR GOVERNMENT OF WEST
BENGAL
94OTHER THRUST AREAS
- New Works manual to be brought by September-2007
- Methodology and rates for fast track construction
of mass housing by September-2007 - New Plinth Area Rates, incorporating provisions
for mechanical construction by October-2007 - Revised Electrical Schedule of rates by
October-2007
95REORIENTING STRATEGY FOR GROWTH
- Govt. departments and ministries have freedom of
choice and CPWD has moved away from a situation
of captive clients - Strategy adopted
- Attract new clients
- Project specific focused management
- Concentrate on major works and stop taking small
works - Strategy has resulted in high value projects
being entrusted to CPWD
96MISSION TO TURNAROUND CPWD
- We need to make CPWD
- An attractive destination for clients and
professionals - Competitive and modern
- We need to ensure
- Delivery of projects with quality and speed
- Client satisfaction
- We need to give value for money
97NEED
- More flexibility
- More say in personnel management
- More delegation
- More manpower to handle large volume of work and
consultancy assignments of JNNURM etc - Certain additional facilities for staff working
on high value projects and in difficult areas
98THANK YOU