Title: JWST Project Status AAAC, October 12, 2005
1JWST Project StatusAAAC, October 12, 2005
- John C. Mather
- JWST Senior Project Scientist
- NASA GSFC
2Topics
- Science summary
- Mission summary
- Technology status
- Test plan status
- Contamination and Stray Light plan
3Top JWST Goal - Find the First Light after the
Big Bang
- How and from what were galaxies assembled?
- What is the history of star birth, heavy element
production, and the enrichment of the
intergalactic material? - How were giant black holes created and what is
their role in the universe? - Three instruments to do this NIRCam (NASA/CSA),
NIRSpec (ESA), MIRI (ESA/consortium/NASA), plus
FGS-TF (CSA)
???????? as seen by COBE
?
Galaxy assembly
?
Galaxies, stars, planets, life
4The Epoch of Reionization
Redshift
Neutral IGM
.
zzi
zltzi
zgtzi
Wavelength
Wavelength
Wavelength
Lyman Forest Absorption
Black Gunn-Peterson trough
Patchy Absorption
5JWST Science
- End of the dark ages first light and
reionization - The assembly of galaxies
The Eagle Nebula as seen by HST
- Birth of stars and protoplanetary systems
- Planetary systems and the origins of life
Galaxies in the UDF
64
3
2
Spectra obtained with the JWST MIRI on the
nearest systems can provide detailed insights
to the minerals in ring particles and the
nature of giant planets
1
R2000, 1-s 100 sec
0
mJy
Simulated Vega Observation
7Model Picture
8JWST Observatory Architecture
- Optical Telescope Element (OTE)
- Stable over total field-of-regard
- Beryllium (Be) optics with GFRP/Boron structure
- Performance verified on the ground
9JWST Orbit about the Sun-Earth L2 and Launch
Configuration
10Ball AMSD II Be Mirror in Optical Test
11Primary Mirror Segment Actuations
Lightweighted Beryllium Mirror Substrate
Observatory optical quality (mid and high
spatial frequency) is manufactured into segments
Actuator for radius of curvature adjustment
12A NIRCam Imaging Module
A dichroic allows simultaneous observing at two
wavelengths. This modules dual filter wheels
include pupils for wavefront sensing.
13Detector Technology Development
- NICMOS and IRAC arrays have demonstrated the
basic detector architecture but with lower
performance and smaller formats. - TRL 4 achieved Feb 2002 with JWST performance
levels achieved - TRL 5 achieved Feb 2003 with JWST size 2Kx2K
devices, mosaicing - Astronomical Image with prototype, Sept. 2003
- Flight detectors being manufactured
14NIRSpec ESA Astrium
- gt 100 Objects Simultaneously
- 9 square arcminute FOV
- Implementation
- 3.5 Large FOV Imaging Spectrograph
- 4 x 175 x 384 element Micro-Shutter Array
- 2 x 2k x 2k Detector Array
- Fixed slits and IFU for backup, contrast
- SiC optical bench optics
15NIRSpec Schematic
16SAT Recommendations and Response
17Technology Status
- All technologies to be ready for by Non-Advocate
Review (NAR) - Key technologies
- Mirrors - flight mirror blanks made and being
machined EDU being polished operator error (due
to an unexpected feature in the machine) at Axsys
drilled hole in one blank, no effect on schedule - Detectors - TRL 5 achieved in 2003, all
performance specifications met some HgCdTe
detectors disintegrated, apparently due to
insufficient cleaning prior to bonding to BCS
(Balanced Composite Substrate) new recipe
verified by repeated thermal cycles - Microshutters - GSFC - recipe found for keeping
shutters flat at room temperature and cold on
track with all needed tests - ASICs - all performance specifications met final
foundry run starting with revised masks - Cryocooler - will select contractor in January
18Baseline Cup Down Tower Configuration at JSC
(Before)
Most recent Tower Design shows an Inner Optical
Tower supported by a Outer structure with
Vibration Isolation at the midplane. Everything
shown is in the 20K region (helium connections,
etc. not shown) except clean room and lift
fixture. Plan called for 33KW He cooldown
capability, 12 KW steady state, major challenges
for JSC JSC currently has 7 KW He capability Plan
required 10 trucks of LN2/day during
cooldown Large Risk on Cooldown Time Assumptions
Clean room
Clean room
Interferometers, Sources, Null Lens and Alignment
Equipment Are in Upper and Lower Pressure Tight
Enclosure Inside of Shrouds where Cryo Cycle
Needed to Fix Problems
19JSC Cup Up Test Configuration
Center of Curvature Null and Interferometer
Accessible from top
Auto-Collimating Flats (isolators above
connected to hard points on top of chamber).
Telescope Cup Up Gravity offloaded and On Ambient
Isolators Connected to Concrete)
Focal Plane Interferometer and sources accessible
from below
- Isolators moved outside of shroud/vacuum
- Telescope comes in deployed on tracks with
minimal time in chamber before pump down
20Contamination Plan
- Cup Up test at JSC is not a major contaminant
source - Launch effects are major driver
- Ariane meeting planned for this fall
- Particle generation by sunshield rubbing during
launch? - We will be able to clean mirrors
- Need independent review of all models,
assumptions, methods - Detail required cleaned mirrors have different
particle size distributions and different BRDF
shapes than before cleaning - Goal is twofold
- Cost-effective particulate contamination plan
- Consistency with SAT assumptions regarding
sensitivity losses
21Summary
- All review committees endorse JWST plans
- Scientific descope recommended by SAT accepted
and being implemented - Cost control and risk reduction approach endorsed
by SAT and IPAO reviews - Replan in progress for new launch date and budget
- Technology progress excellent, will be ready for
NAR