Project Overview Peter Napier, EVLA Project Manager - PowerPoint PPT Presentation

About This Presentation
Title:

Project Overview Peter Napier, EVLA Project Manager

Description:

Title: The Expanded Very Large Array Author: AOCPub Last modified by: tromero Created Date: 8/20/2001 2:45:28 PM Document presentation format: On-screen Show – PowerPoint PPT presentation

Number of Views:67
Avg rating:3.0/5.0
Slides: 12
Provided by: AOC55
Learn more at: http://www.aoc.nrao.edu
Category:

less

Transcript and Presenter's Notes

Title: Project Overview Peter Napier, EVLA Project Manager


1
Project Overview Peter Napier, EVLA Project
Manager
  • Status 2003 Committee Response

2
Status
  • Activities since last meeting
  • EVLA Test Antenna (13)
  • Prototype system. First light and fringes at
    X-band and L-band
  • Continuing addition of capabilities (eg time
    synchronization, fringe rotation)
  • Debugging and testing slower than expected
  • Robustness of prototypes, complexity of
    equipment, reduced monitor data, AOC-VLA
    separation.

3
Status (cont)
  • Second EVLA Antenna (14)
  • Second generation prototypes. First EVLA-EVLA
    fringes.
  • Came to life much more easily than 13
  • Production-like modules early 2005
  • Third EVLA Antenna (16)
  • Undergoing EVLA structural modifications
  • First production modules

4
Status (cont)
  • Lab test system
  • Mockup of antenna electronics system established
    in AOC lab.
  • Production orders
  • Lifetime supplies of adequately tested components
    being ordered to prevent obsolescence problem and
    reduce cost (eg DTS chips, cryo-refrigerators,
    feed support structures, antenna HVAC,
    synthesizer YIG oscillators).

5
Status (cont)
  • Correlator
  • Chip contract in final process
  • Prototype board construction beginning
  • Software
  • Monitor and Control (M/C) keeping up with
    antenna test needs, working on transition
    software.
  • e2e EVLA overall software design completed
  • AIPS passed ALMA acceptance test, EVLA
    specific tasks begun.

6
Status (cont)
  • Design Reviews Completed
  • Overall software design
  • M/C hardware and IF/LO/FO CDRs
  • Correlator PDR, Feeds, FE and software CDRs
    planned

7
2003 Committee Response
  • Last meeting 30 Sept., 2003. Project Response 4
    Nov., 2003.
  • Management Issues
  • Schedule delay. Recovery plan in place (see
    schedule presentation)
  • Hardware Issues
  • Location of FE hybrids. Detailed study concluded
    no change.
  • Calibration of solar data. Calibration procedure
    devised.
  • Dual LO phase stability test. Not yet achieved.
    Effort had to be used for synthesizer
    improvements, fringe rotation, temperature
    chamber phase stability tests.

8
2003 Committee Response(cont)
  • Obsolete electronic components. So far sufficient
    funds available to buy lifetime supplies of
    critical components.
  • Correlator
  • Chip schedule contingency. Study contracts with
    two vendors completed, detailed chip CDR planned
    ( Jan 2005).
  • Correlator software definition and management.
    Software specification documents in place, some
    NRAO programmers under HIA direction.
  • Simultaneous observations with EVLA, NMA and
    VLBA. Funds in Phase II budget for additional
    programming effort

9
2003 Committee Response(cont)
  • Correlator
  • Pulsar Observing. Supported by WIDAR correlator
    and correlator backend design.
  • Software
  • NRAO/EVLA computing management structure. The
    structure has worked all EVLA software under
    single lead. Major issue now is not management
    but resource availability. NRAO Director intends
    to appoint NRAO-wide Software Leader (Ulvestad
    talk).
  • VLA and VLBA observers should use AIPS. Not in
    current short-term plan, although VLA data is
    used for testing.
  • An algorithm development group is needed. A group
    is now functioning. (See Bhatnagar talk).

10
2003 Committee Response(cont)
  • Software
  • Need for overall EVLA Software System Design.
    Completed, (see Van Moorsel talk),
  • AIPS performance, robustness and interface.
    Significant improvements and plans. (see
    Myers/McMullin talks).
  • Need for User and Scientist involvement in
    testing. Good involvement in AIPS testing.
    Concern over resource availablity for EVLA
    software commissioning (see Owen talk).
  • RFI
  • Design for RFI excision. Significant module
    testing for self-generated RFI, no obvious
    problems on test antenna. Headroom specification
    revisited OK. Hooks for high time resolution
    data from samplers and total power detectors in
    place to allow auto-flagging.

11
2003 Committee Response(cont)
  • RFI
  • Need for Algorithm Development. New AIPS
    autoflagging algorithm, new excision algorithm
    (EVLA Memo 86) developed.
  • Phase II Issues.
  • Submit proposal ASAP. Proposal submitted April
    2004. NSF Review underway. (see Perley talk)).
  • Include low frequencies if possible. Low
    frequencies removed from this proposal because
    technical concept not sufficiently developed.
Write a Comment
User Comments (0)
About PowerShow.com