Generation Interconnection Cost Allocation Policy - PowerPoint PPT Presentation

About This Presentation
Title:

Generation Interconnection Cost Allocation Policy

Description:

Generation Interconnection Cost Allocation Policy Teresa Mogensen Director of Transmission Planning and Service – PowerPoint PPT presentation

Number of Views:130
Avg rating:3.0/5.0
Slides: 42
Provided by: ATC84
Category:

less

Transcript and Presenter's Notes

Title: Generation Interconnection Cost Allocation Policy


1
Generation Interconnection Cost Allocation Policy
  • Teresa Mogensen
  • Director of Transmission Planning
  • and Service

2
ATC Objectives
  • Strengthen ATC transmission network
  • Improve access of ATC customers to competitive
    energy market
  • Additional generation interconnections
  • Impacts on import capability

3
Policy
  • Include the costs of transmission network
    facilities associated with generation
    interconnections in the network costs of the ATC
    system
  • Subject to tests
  • Network facilities
  • Reasonableness
  • Eligibility

4
Network Facilities
  • Facilities must carry network flow and be judged
    beneficial to network
  • Radial generation leads to network
    interconnection point are not included

5
Example Interconnecting to an ATC Line

SUB D
Stability
X
SUB B relay
SUB A  
? Miles
SUB C relay  
X
____ Interconnection Facilities (new facilities
necessary to interconnect generation) ____
Required Upgrades (breakers, system protection
and control) resulting from short
circuit and stability studies ____ Subset of
Required Upgrades line addition due to
stability ____ Optional Upgrades (thermal and
associated upgrade) ____ Existing Facilities
 
6
Example Interconnecting to an ATC Substation
Line 4
Line 5
Line 3
Line 1
Line 2
____ Interconnection Facilities (new facilities
necessary to interconnect
generation) ____ Required Upgrades (breakers,
system protection and control)
resulting from short circuit and stability
studies ____ Subset of Required Upgrades line
addition due to stability ____ Optional Upgrades
(thermal and associated upgrade) ____ Existing
Facilities  
 
7
Reasonableness Tests
  • ATC will assess factors including, but not
    limited to
  • Distance from generator to existing ATC system
  • Application of general least cost planning
    principles
  • Point-to-point revenue to annual revenue
    requirement comparison

8
Eligibility Requirements
  • Financial screening of generating firm
  • Guarantee to cover ATC costs expended if project
    fails or does not proceed as planned
  • Executed interconnection agreement

9
Policy Subject to Change
  • Policy may be changed at some time in the future
    as generation becomes more plentiful, system
    configuration changes, RTO congestion management
    systems are implemented or other relevant
    conditions occur.

10
Least Cost Redispatch
  • I want to suggest a method that will combine most
    effective use of generation to solve a constraint
    along with selecting the Least Cost.

11
Least Cost Redispatch Process
  • Mike Zahorik

12
Least Cost Redispatch
  • This method will provide Least Cost Plans for 10
    of the most probable flowgates that could be
    subjected to TLR 5 each day.
  • These plans will be made available to the ATC
    System Operators Prior to any TLR 5 event.

13
Least Cost Redispatch
  • The ATC Operator will control the TLR 5
    Redispatch.
  • All Non Firm transactions with gt5 PTDF have been
    curtailed.
  • If the overloaded element is in the WEP, WPS or
    UPP Control Area, the Pewaukee ATC Operator will
    be responsible.
  • If the overloaded element is in the ALTE or MGE
    Control Area, the Cottage Grove ATC Operator will
    be responsible.
  • The responsible ATC Operator will request the
    needed relief.

14
Least Cost Redispatch
  • The ATC Operator will control the TLR 5
    Redispatch.
  • MAIN issues Firm transaction curtailment list.
  • MAIN also issues Load curtailments, these load
    curtailments may be accomplished by redispatch of
    generation.
  • The responsible ATC Operator will combine the
    needed load curtailments and issue the Least Cost
    Redispatch.

15
Least Cost Redispatch
  • Least Cost Redispatch Plans
  • Will use Unit Costs.
  • Will provide plans for the 10 most probable TLR
    flowgates.
  • Will use NERC Generation Shift Factors.
  • These probable plans will be updated daily.

16
Unit Costs
  • Generation Information will be communicated to
    ATC each day/week.
  • General Cost, to the nearest dollar.
  • Unit availability.
  • ATC will provide a spreadsheet to be filled out.

17
Unit Costs
  • Each Control Area would provide Generation Costs
    to ATC.
  • Example of Wisconsin Electric's costs.

18
10 Most Probable TLR's
  • Each Night Shift, ATC System Operator will select
    10 possible Flowgates that could be subjected to
    TLR 5.
  • Based on Knowledge of System Topology
  • Recent Past History
  • ATC System Operator will gather NERC GSF's for
    the selected flowgates.

19
(No Transcript)
20
Least Cost Redispatch Plans
21
Least Cost Redispatch Plans
MW Relief Required 50 Paris
Albers 138 Kv 3503
Redispatch Redispatch Increment Unit
Inc Decrement Unit Dec
GSF Delta Cost Needed Cost
Cost Cost WEC_PRS GT2
13.8_2 50.00 WEC_PL PRG2 24.0_2 10.00
-50.8 40.00 98.43
3,937.01 WEC_UNIV GT 13.8_1 65.00
WEC_PL PRG2 24.0_2 10.00 -19.4 55.00
257.73 14,175.26
Delta Cost Inc Cost - Dec Cost Redispatch
Needed Mw Relief Required / GSF Redispatch Cost
Redispatch Needed Delta Cost
22
Least Cost Redispatch Plans
  • Items the responsible ATC Operator will have to
    consider during TLR 5 event.
  • ATC Operator may not know the current dispatch of
    units and/or the availability to move them.
  • ATC Operator will have to inquire if a generator
    pair is available.
  • If the Least Cost Redispatch spans two control
    areas, the control areas will have to enter
    schedules.

23
Summary
  • ATC Operator controls Redispatch
  • MAIN issues Firm curtailment lists and Load
    Relief numbers
  • Control Area's supply Unit Costs
  • ATC Operator calculates and issues Redispatch
    orders.
  • If Redispatch is not available, load shedding
    will be necessary.

24
Update on Single System ATC
  • Teresa Mogensen
  • Director of Transmission Planning and Service

25
Single System ATC Non-Firm
  • The Proposed Changes to the Calculation of
    Non-firm ATC for the ATCLLC Transmission System
    document was approved by the MAIN ATCSC on April
    10, 2001 and implemented on April 25, 2001

26
Single System ATCNon-Firm (cont.)
  • A single ATCLLC non-firm ATC value is calculated
    and shared by all network customers of the ATCLLC
    for each of the interconnected directions
  • CE??WUMS, DPC??WUMS, NSP??WUMS, UPPCo??WUMS and
    MECS??WUMS.
  • Note that WUMS is a proxy for ATCLLC
  • UPPCo will be added to this group when they
    become a network customer

27
Single System ATC Firm
  • There are several issues associated with a single
    zone approach to granting firm transmission
    service including
  • Identification of true source/sink
  • Impacts on the transmission system based on the
    true source/sink
  • The work group has been unable to reach
    consensus
  • The work group is drafting a proposal titled
    Single Zone Firm ATC for executive review

28
Single Zone Firm ATC Latest Proposal
  • Only applies to studies within the next 13 months
  • Continue to calculate every control area to
    control area path
  • Calculate the Firm Service Load Ratio Share
    (FSLRS), based on each network customers load in
    proportion to total ATCLLC network load
  • Determine which path is most constrained, taking
    into account the FSLRS
  • Constrain all directions based on the most
    constrained path and FSLRS
  • Please refer to the draft proposal for details

29
Single System ATCCongestion Management
  • In order to track ATCLLC customer costs due to
    Zero ATC or TLR events, we have asked all
    customers impacted by TLR and/or denied
    transmission requests (based on No ATC) to
    report their estimated replacement costs and
    summarize by event
  • This data will be summarized by constraint
    (flowgate) and used, in part, to justify new
    projects
  • ATCLLC is also exploring ways to facilitate use
    of the NERC Market Redispatch program for our
    customers

30
Single System ATCNext Steps
  • Next SSATC Working Group meeting is June 5 at ATC
    HQ
  • Main goal of June 5 meeting is to finalize best
    proposal(s) for implementation of single zone ATC
    for firm
  • Ongoing series of biweekly meetings (June 5, June
    19 etc.) to continue to discuss issues
  • Your ongoing input and participation is requested
    and appreciated.

31
Maintenance Scheduling Process
  • Don Morrow

32
Who Do I Talk To?
  • On the old WEP system ATC-Pewaukee
  • On the old WPS system WPS Operating
  • On the old ALTE system ATC-CG
  • On the old MGE system MGE

33
Who Is ATC-Pewaukee?
  • Manager Mike Zahorik 262-544-7002
  • Team Leader Eric Solberg 262-544-7228
  • Security Coordinator Darrel Yohnk
    262-544-7106
  • Outage Coordinator Ed Funk
  • Outage Coordinator Liz Gehrt
  • Real Time Operator 262-544-7008

34
Who Is ATC-Cottage Grove?
  • Manager Kurt Dickinson 608-877-8237
  • Security Coordinator Francis Esselman
    608-877-8172
  • Outage Coordinator Jon Staff 608-877-8208
  • Outage Coordinator Bill Hoesly 608-877-8209
  • Real Time Operator 608-877-8233

35
Upcoming Changes
  • ATC-Pewaukee Control Center Move New Phone s
  • ATC-CG Assumes Functional Control of Old MGE
    System
  • ATC-Pewaukee Assumes Functional Control of Old
    WPS System

36
Load Shedding Subcommittee
  • Kurt Dickinson
  • Manager, System Control
  • Cottage Grove

37
LSS - Members
  • The following ATC customers have volunteered to
    discuss Load Shedding procedures
  • Chuck Spargo ACEC
  • Phil Hansen Pat Conners WPPI
  • Dale Koch Manitowoc Public Utilities
  • Paul Roehr MGE
  • Tony Jankowski WE
  • Jim Maenner (or Chris Plante) WPS
  • Ron Graber Alliant
  • Kurt Dickinson ATCLLC 608.877.8237

38
LSS To Date
  • The LSS has NOT met yet.
  • E-mail sent recently asking for concurrence on
    the issues.
  • Conference call scheduled Tuesday, June 5, 2001.
    Kurt will contact everyone with details.

39
LSS The Issues
  • Load shedding due to capacity deficiency.
    Rolling blackouts/distribution load shedding.
    This would be the responsibility of the
    individual control areas/local distribution
    companies or load balancing areas. There would be
    little or no involvement by ATCLLC.
  • Underfrequency load shedding and manual load
    shedding due to frequency decline as required by
    NERC/MAIN. This issue will be a little different
    for each customer and will have to be discussed.

40
LSS The Issues
  • Load shedding orders as a result of a
    Transmission Loading Relief (TLR) procedure, i.e.
    TLR level 5. We will definitely have to
    determine an acceptable procedure for this
    situation. If we run out of Redispatch and
    Schedule curtailment options, the act of shedding
    load to provide relief on a flowgate may get a
    bit complicated.
  • Specific load shedding as a result of a local
    transmission problem. If TLR could not help a
    particular situation, the ATCLLC System Control
    Operator may order shedding of some
    specific/local loads to prevent a worse problem
    (e.g.low voltage, voltage collapse or major
    overloads).

41
LSS Temporary Measures
  • Until there are specific procedures and processes
    developed by ATCLLC and its customers, we will
    continue to operate within the procedures and
    practices already in place by the utility or
    control area.
Write a Comment
User Comments (0)
About PowerShow.com