Title: Generation Interconnection Cost Allocation Policy
1Generation Interconnection Cost Allocation Policy
- Teresa Mogensen
- Director of Transmission Planning
- and Service
2ATC Objectives
- Strengthen ATC transmission network
- Improve access of ATC customers to competitive
energy market - Additional generation interconnections
- Impacts on import capability
3Policy
- Include the costs of transmission network
facilities associated with generation
interconnections in the network costs of the ATC
system - Subject to tests
- Network facilities
- Reasonableness
- Eligibility
4Network Facilities
- Facilities must carry network flow and be judged
beneficial to network - Radial generation leads to network
interconnection point are not included
5Example Interconnecting to an ATC Line
SUB D
Stability
X
SUB B relay
SUB A Â
? Miles
SUB C relay Â
X
____ Interconnection Facilities (new facilities
necessary to interconnect generation) ____
Required Upgrades (breakers, system protection
and control) resulting from short
circuit and stability studies ____ Subset of
Required Upgrades line addition due to
stability ____ Optional Upgrades (thermal and
associated upgrade) ____ Existing Facilities
Â
6Example Interconnecting to an ATC Substation
Line 4
Line 5
Line 3
Line 1
Line 2
____ Interconnection Facilities (new facilities
necessary to interconnect
generation) ____ Required Upgrades (breakers,
system protection and control)
resulting from short circuit and stability
studies ____ Subset of Required Upgrades line
addition due to stability ____ Optional Upgrades
(thermal and associated upgrade) ____ Existing
Facilities Â
Â
7Reasonableness Tests
- ATC will assess factors including, but not
limited to - Distance from generator to existing ATC system
- Application of general least cost planning
principles - Point-to-point revenue to annual revenue
requirement comparison
8Eligibility Requirements
- Financial screening of generating firm
- Guarantee to cover ATC costs expended if project
fails or does not proceed as planned - Executed interconnection agreement
9Policy Subject to Change
- Policy may be changed at some time in the future
as generation becomes more plentiful, system
configuration changes, RTO congestion management
systems are implemented or other relevant
conditions occur.
10Least Cost Redispatch
- I want to suggest a method that will combine most
effective use of generation to solve a constraint
along with selecting the Least Cost.
11Least Cost Redispatch Process
12Least Cost Redispatch
- This method will provide Least Cost Plans for 10
of the most probable flowgates that could be
subjected to TLR 5 each day. - These plans will be made available to the ATC
System Operators Prior to any TLR 5 event.
13Least Cost Redispatch
- The ATC Operator will control the TLR 5
Redispatch. - All Non Firm transactions with gt5 PTDF have been
curtailed. - If the overloaded element is in the WEP, WPS or
UPP Control Area, the Pewaukee ATC Operator will
be responsible. - If the overloaded element is in the ALTE or MGE
Control Area, the Cottage Grove ATC Operator will
be responsible. - The responsible ATC Operator will request the
needed relief.
14Least Cost Redispatch
- The ATC Operator will control the TLR 5
Redispatch. - MAIN issues Firm transaction curtailment list.
- MAIN also issues Load curtailments, these load
curtailments may be accomplished by redispatch of
generation. - The responsible ATC Operator will combine the
needed load curtailments and issue the Least Cost
Redispatch.
15Least Cost Redispatch
- Least Cost Redispatch Plans
- Will use Unit Costs.
- Will provide plans for the 10 most probable TLR
flowgates. - Will use NERC Generation Shift Factors.
- These probable plans will be updated daily.
16Unit Costs
- Generation Information will be communicated to
ATC each day/week. - General Cost, to the nearest dollar.
- Unit availability.
- ATC will provide a spreadsheet to be filled out.
17Unit Costs
- Each Control Area would provide Generation Costs
to ATC. - Example of Wisconsin Electric's costs.
1810 Most Probable TLR's
- Each Night Shift, ATC System Operator will select
10 possible Flowgates that could be subjected to
TLR 5. - Based on Knowledge of System Topology
- Recent Past History
- ATC System Operator will gather NERC GSF's for
the selected flowgates.
19(No Transcript)
20Least Cost Redispatch Plans
21Least Cost Redispatch Plans
MW Relief Required 50 Paris
Albers 138 Kv 3503
Redispatch Redispatch Increment Unit
Inc Decrement Unit Dec
GSF Delta Cost Needed Cost
Cost Cost WEC_PRS GT2
13.8_2 50.00 WEC_PL PRG2 24.0_2 10.00
-50.8 40.00 98.43
3,937.01 WEC_UNIV GT 13.8_1 65.00
WEC_PL PRG2 24.0_2 10.00 -19.4 55.00
257.73 14,175.26
Delta Cost Inc Cost - Dec Cost Redispatch
Needed Mw Relief Required / GSF Redispatch Cost
Redispatch Needed Delta Cost
22Least Cost Redispatch Plans
- Items the responsible ATC Operator will have to
consider during TLR 5 event. - ATC Operator may not know the current dispatch of
units and/or the availability to move them. - ATC Operator will have to inquire if a generator
pair is available. - If the Least Cost Redispatch spans two control
areas, the control areas will have to enter
schedules.
23Summary
- ATC Operator controls Redispatch
- MAIN issues Firm curtailment lists and Load
Relief numbers - Control Area's supply Unit Costs
- ATC Operator calculates and issues Redispatch
orders. - If Redispatch is not available, load shedding
will be necessary.
24Update on Single System ATC
- Teresa Mogensen
- Director of Transmission Planning and Service
25Single System ATC Non-Firm
- The Proposed Changes to the Calculation of
Non-firm ATC for the ATCLLC Transmission System
document was approved by the MAIN ATCSC on April
10, 2001 and implemented on April 25, 2001
26Single System ATCNon-Firm (cont.)
- A single ATCLLC non-firm ATC value is calculated
and shared by all network customers of the ATCLLC
for each of the interconnected directions - CE??WUMS, DPC??WUMS, NSP??WUMS, UPPCo??WUMS and
MECS??WUMS. - Note that WUMS is a proxy for ATCLLC
- UPPCo will be added to this group when they
become a network customer
27Single System ATC Firm
- There are several issues associated with a single
zone approach to granting firm transmission
service including - Identification of true source/sink
- Impacts on the transmission system based on the
true source/sink - The work group has been unable to reach
consensus - The work group is drafting a proposal titled
Single Zone Firm ATC for executive review
28Single Zone Firm ATC Latest Proposal
- Only applies to studies within the next 13 months
- Continue to calculate every control area to
control area path - Calculate the Firm Service Load Ratio Share
(FSLRS), based on each network customers load in
proportion to total ATCLLC network load - Determine which path is most constrained, taking
into account the FSLRS - Constrain all directions based on the most
constrained path and FSLRS - Please refer to the draft proposal for details
29Single System ATCCongestion Management
- In order to track ATCLLC customer costs due to
Zero ATC or TLR events, we have asked all
customers impacted by TLR and/or denied
transmission requests (based on No ATC) to
report their estimated replacement costs and
summarize by event - This data will be summarized by constraint
(flowgate) and used, in part, to justify new
projects - ATCLLC is also exploring ways to facilitate use
of the NERC Market Redispatch program for our
customers
30Single System ATCNext Steps
- Next SSATC Working Group meeting is June 5 at ATC
HQ - Main goal of June 5 meeting is to finalize best
proposal(s) for implementation of single zone ATC
for firm - Ongoing series of biweekly meetings (June 5, June
19 etc.) to continue to discuss issues - Your ongoing input and participation is requested
and appreciated.
31Maintenance Scheduling Process
32Who Do I Talk To?
- On the old WEP system ATC-Pewaukee
- On the old WPS system WPS Operating
- On the old ALTE system ATC-CG
- On the old MGE system MGE
33Who Is ATC-Pewaukee?
- Manager Mike Zahorik 262-544-7002
- Team Leader Eric Solberg 262-544-7228
- Security Coordinator Darrel Yohnk
262-544-7106 - Outage Coordinator Ed Funk
- Outage Coordinator Liz Gehrt
- Real Time Operator 262-544-7008
34Who Is ATC-Cottage Grove?
- Manager Kurt Dickinson 608-877-8237
- Security Coordinator Francis Esselman
608-877-8172 - Outage Coordinator Jon Staff 608-877-8208
- Outage Coordinator Bill Hoesly 608-877-8209
- Real Time Operator 608-877-8233
35Upcoming Changes
- ATC-Pewaukee Control Center Move New Phone s
- ATC-CG Assumes Functional Control of Old MGE
System - ATC-Pewaukee Assumes Functional Control of Old
WPS System
36Load Shedding Subcommittee
- Kurt Dickinson
- Manager, System Control
- Cottage Grove
37LSS - Members
- The following ATC customers have volunteered to
discuss Load Shedding procedures - Chuck Spargo ACEC
- Phil Hansen Pat Conners WPPI
- Dale Koch Manitowoc Public Utilities
- Paul Roehr MGE
- Tony Jankowski WE
- Jim Maenner (or Chris Plante) WPS
- Ron Graber Alliant
- Kurt Dickinson ATCLLC 608.877.8237
38LSS To Date
- The LSS has NOT met yet.
- E-mail sent recently asking for concurrence on
the issues. - Conference call scheduled Tuesday, June 5, 2001.
Kurt will contact everyone with details.
39LSS The Issues
- Load shedding due to capacity deficiency.
Rolling blackouts/distribution load shedding.
This would be the responsibility of the
individual control areas/local distribution
companies or load balancing areas. There would be
little or no involvement by ATCLLC. - Underfrequency load shedding and manual load
shedding due to frequency decline as required by
NERC/MAIN. This issue will be a little different
for each customer and will have to be discussed.
40LSS The Issues
- Load shedding orders as a result of a
Transmission Loading Relief (TLR) procedure, i.e.
TLR level 5. We will definitely have to
determine an acceptable procedure for this
situation. If we run out of Redispatch and
Schedule curtailment options, the act of shedding
load to provide relief on a flowgate may get a
bit complicated. - Specific load shedding as a result of a local
transmission problem. If TLR could not help a
particular situation, the ATCLLC System Control
Operator may order shedding of some
specific/local loads to prevent a worse problem
(e.g.low voltage, voltage collapse or major
overloads).
41LSS Temporary Measures
- Until there are specific procedures and processes
developed by ATCLLC and its customers, we will
continue to operate within the procedures and
practices already in place by the utility or
control area.