Title: Costs of Managing NORM


1
Costs of Managing NORM
  • Brett Young

2
Infrastructure
  • Replacement of contaminated equipment
  • Xmas trees, esps, tubulars, valves, pumps
  • Dedicated NORM Storage facility
  • Interim storage areas (Other locations)
  • Decontamination facility (fixed/mobile)
  • Long term disposal options
  • (Shallow burial/deep well/bioremediation)
  • Transportation of contaminated equipment

3
Administration
  • Specifications e.g. PDO SP 1170
  • Guidelines or Local Rules
  • Development/Review of NORM mgt system
  • Review and renewal of contracts (V.o.C.)
  • Hoists/rigs, pigging, tank/vessel cleaning, plant
    maintenance, NORM WTF Management
  • Contractors implementing Corporate NORM Mgt
    system into their HSE mgt systems
  • System Audits/inspections (Contract Holder and
    Company self assessments/audits)

4
Identification, Assessment and Control, Recovery
  • NORM meters - 3 types required
  • Each asset various contractors
  • Activity Analysis e.g. sludge/sands/wax
  • PPE
  • Medical surveillance

5
Human Resources
  • CRFP or SRPS
  • RPS
  • RPTs
  • External consultants e.g. RPA
  • Training
  • 5000 Awareness _at_ 1 hour 5000 hrs
  • 200 RPT _at_ 4 hours 800 hrs
  • 20 RPS _at_ 2-3 days 480 hrs
  • Total 5880 hrs
  • or 735 days

6
Examples
  • Production losses
  • Well head closed for 2 months (150m3/day)
  • Well closed for 3 weeks (300 m3/day)
  • Hoist and camp moved
  • Tanks not emptied for nine years
  • Known to contain NORM
  • Then delays with NORM storage facility
  • Confusion as to how to transport/store the sludge
  • Unable to collect sample prior to emptying tank
    contents

7
Hidden Costs
  • Meetings/Correspondence
  • Radiation Advisory Committee
  • Emails/phone calls/Advice and assistance
  • Morale - fear of exposure, uncertainty
  • Failing to comply with systems
  • Legal Responsibility Moral issues
  • Health of Workforce
  • Occupational Illnesses (lung cancer)
  • Loss of income earner
  • Reputation