Difficulties with current - PowerPoint PPT Presentation

About This Presentation
Title:

Difficulties with current

Description:

... feedthroughs on the same big flange all cables and repeater cards on same side present choice of feedthrough limits total ... station alignment with ... surveying ... – PowerPoint PPT presentation

Number of Views:32
Avg rating:3.0/5.0
Slides: 9
Provided by: Onn80
Category:

less

Transcript and Presenter's Notes

Title: Difficulties with current


1
Difficulties with current mechanical design
  • recent FEA results to obtain sufficient
    stiffness of center frame,
  • a rather complex structure needs to be used
  • ? reduced space and accessibility
  • MAFIA WF suppressors on sides of the two
    detector boxes
  • are needed
  • ? not easy to find a solution with current
  • design because center frame is in the way
  • and because of the fact that the two boxes
  • are mounted separately into the tank
  • Dynamic vacuum we must have the option to
    insert a Titanium
  • evaporator
  • ? not easy with current design
  • must enter from the front of tank and, again,
  • center frame is in the way
  • ? we propose a new design

2
(No Transcript)
3
New tank frame design summary
  • Plus points
  • center frame much stiffer
  • optimally positioned short legs,
  • no more problems of bending
  • not any longer in our way (more accessibility
    to critical
  • items of VD, see below)
  • all referencing is achieved with a much
    simpler design
  • alignment and reproducibility
  • VD easier to mount and position in the tank
  • build in complete VD at once
  • solves accessibility problem on one side of
    the beam pipe
  • no more need of tilting mechanism during VD
    installation
  • easier access to the critical WF suppressor
  • more accessibility for connection to exit foil

4
New tank frame design summary (continued)
  • Minus points
  • re-do FEA calculations
  • two detector boxes are not interchangeable any
    longer
  • (but individual stations can be)
  • all feedthroughs on the same big flange
  • all cables and repeater cards on same side
  • present choice of feedthrough limits total
    number of pins
  • to about 25000 !!

Conclusion We like the new design.
5
NIKHEF VD responsibilities how do we currently
see it ? YES, ours NO, not ours (not
included here Pile-up and FEE)
  • Cabling in vacuum
  • provide FEE cabling from feedthroughs to some
    available
  • connectors coming from the hybrids
  • cabling for cooling system and control (see
    definition below)
  • cabling for temperature control of stations
  • we assume some group will take care of testing
    the complete
  • electrical chain
  • Alignment
  • provide reference points for station alignment
    with respect to
  • center frame
  • provide reference points for external alignment
    of boxes
  • guarantee internal alignment and reproducibility
    of boxes
  • provide possibility to move the center frame via
    a remote-
  • controllable XY-table
  • interactive alignment with respect to beams
    using tracking,
  • beam feedback control and XY-table
  • internal alignment and reproducibility of
    detector stations
  • we assume some group will take care of the
    complete LHCb

6
NIKHEF VD responsibilities how do we currently
see it ? (continued) YES, ours NO, not
ours
  • Cooling system and temperature control
  • provide a complete cooling system heat
    exchanger (pipes)
  • with sufficient cooling power at a fixed and
    stable temperature
  • control and monitor of this cooling system
    (hardware and
  • software)
  • cooling, temperature control and monitor of the
    stations
  • (though, we wish to be involved in this)
  • VD vacuum (tank and detector boxes)
  • provide important part of the vacuum system
    (chambers,
  • flanges, feedthroughs), but
  • we assume we do not have to provide the exit
    foil (CERN)
  • we see the pumps, gauges, quadrupole mass
    analyzers, and
  • LHC/VD interface valves as part of the
    infrastructure
  • control and monitor of VD vacuum system
    (hardware and
  • software).
  • Note this has to be integrated with LHC
    control system!

7
Timeline and Milestones (highlights)
strong impact on LEMIC (my
personal impression)
End April fix foil geometry and thickness
  • manufacture and test self-
  • opening valves
  • design a Ti evaporator
  • build and test cooling system

Early May formal approval by LHCb/VELO of VD
design
  • manufacture prototype Al box,
  • then leak pressure tests
  • manufacture a WF suppressor
  • model, perform RF studies

Mid May formal approval by LHCb of VD design
  • build and test Ti evaporator
  • complete testing (vacuum,
  • RF, motion mechanics,
  • cooling, etc.)

End June formal approval by LHC of VD design
(LEMIC?)
  • start producing manufacturing
  • drawings
  • build control and monitoring
  • systems
  • etc.

End December draft TDR
8
Some questions, en vrac
Partial bake out of Al box to clean surfaces on
the beam side could we consider baking the box
(e.g. at 80-100 ºC) while cooling the stations
? what are the sensitive components in the Si
stations ? Temperature cycling of Si
stations What will happen to the Si stations ?
Beneficial ? Deteriorating ? (we assume its no
problem) // commented out... // Water
condensation on (cooled) stations // No problems
? (Si, FEE, bonding, etc.) // Vapour pressure at
-30 ºC is 10-1 mbar ? only monolayer. Radiation
resistance of carbon-fiber support
structures how good ? Vacuum design In case
one detector half must be turned off, do we want
to have the possibility to operate the other
half ? Cabling How many wires in total ? What
kind ? cable properties impedance, attenuation,
etc. (what for ? signal, power, control,
digital/analog, etc.) How will the grouping be
done ?
Write a Comment
User Comments (0)
About PowerShow.com